Latest / Kendall County News - Shaw Local / Yorkville delays water rate hikes 2 more months; Lake Michigan project back to original $300M estimate
Transcript
- 0:05Yorkville delays water rate hikes two more months. Lake Michigan project back
- 0:10to original three hundred million dollars estimate. This
- 0:16article is being read by an automated voice, brought to you by
- 0:19Everlet. The city of Yorkville is pushing back water
- 0:24rate hikes after the final bid for the Lake Michigan Water Project
- 0:27came in under original estimates. The city said the good news is
- 0:32being able to delay the rates hikes for another two months while
- 0:36the city considers potentially altering the future increases. With concerns over rising
- 0:41construction costs avoided, The
- 0:43city may decrease the water rate hikes if alterations are favored. This
- 0:47is the third time the City Council has agreed to delay the
- 0:50next round of rate hikes over a cumulative six-month period. This will
- 0:55hold rates flat, Mayor John Purcell said. There's not been a rate
- 1:00increase in about a year and a half now. We will discuss
- 1:03this again in a couple months. The city first approved 20 annual
- 1:08water rate increases over five consecutive years in June 2025. Over that
- 1:13period, average residential water bills are expected to double to help cover
- 1:18the project’s costs The city is expecting the final tab to be
- 1:21around 224.4 million.
- 1:25While the joint Lake Michigan Water Project between Yorkville, Azwego, and Montgomery
- 1:31through the DuPage Water Commission, was originally estimated to cost around 300
- 1:35million. Estimates ballooned to around 427 million in July 2025
- 1:42after the first bids of the project came in way over projections.
- 1:47The construction bids on the subsequent legs of
- 1:50the project’s came in much lower, enabling the DuPage Water Commission to
- 1:55revise the total project costs to 30.6 million. Yorkville is responsible
- 2:01for 40.22 of the construction costs or 120.9 million dollars. City
- 2:07Administrator Bart Olson said the bidding process was an incredible effort by
- 2:12The DuPage Water Commission and thanked the group for working closely with
- 2:16the city’s After a nine-month delay, the city successfully closed on its
- 2:21170 million water Infrastructure Finance and Innovation Act loan from the U.S.
- 2:26Environmental Protection Agency. It carries an interest rate of 5.24. The city
- 2:32is covering the remainder of the project's costs through the city's bond
- 2:36issuance and loan proceeds. Together, the favorable construction bidding results and successful
- 2:42WIFIA closing provide greater certainty regarding the city's anticipated project costs and
- 2:48long-term financing requirements. Rob Frederickson, the city's finance director, said in City
- 2:54Documents. Fredericks said this enables city staff to reassess the water rate,
- 2:59scheduled increases, and evaluate potential adjustments. The city is required by state
- 3:05law to maintain water fund revenues at least 1.25 times the city's
- 3:10annual debt service for the project. According to city staff, a revised
- 3:14water rate plan may be presented to city council in November or
- 3:18early December. Frederickson said, Any alterations to the water rate plan must
- 3:23maintain the financial stability of the water fund and satisfy applicable debt
- 3:28service coverage requirements. The Lakechigan Water Sourcing Project was deemed necessary because
- 3:34of current unsustainable usage of the region's underground aquifer, primarily driven by
- 3:39a population increase. The vast majority of the construction still needs to
- 3:44be completed. Potential construction issues could drive the project's total costs higher.