- 0:00Speaker 1: Welcome back to the deep dive, where we take complex
- 0:02Speaker 1: technical sources and while we distill the essentials. Today we
- 0:07Speaker 1: are strapping in and hitting the massive projects, the infrastructure
- 0:11Speaker 1: that literally shapes our economic life.
- 0:14Speaker 2: Yeah, the big stuff.
- 0:15Speaker 1: We're deep diving into the calculated, rigorous world of heavy construction.
- 0:21Speaker 1: You know the dams, the railroads, the highways.
- 0:23Speaker 2: And these aren't just big piles of concrete. These are
- 0:27Speaker 2: multi billion dollar efforts where inefficiency, I mean it can
- 0:31Speaker 2: translate directly into catastrophic failure.
- 0:33Speaker 1: And that's the core challenge we're tackling. Right for civil
- 0:35Speaker 1: engineering students, young professionals, or even that self taught learner,
- 0:39Speaker 1: you quickly realize managing these projects isn't about intuition.
- 0:43Speaker 2: No, not at all. It requires absolute quantification. You have
- 0:46Speaker 2: to calculate every cubic yard, every minute of cycle time,
- 0:49Speaker 2: and every single pound of resistance exactly.
- 0:52Speaker 1: So our mission today is an in depth summary of s.
- 0:55Speaker 2: W and L.
- 0:55Speaker 1: E's foundational text, Construction Methods and Management a class. We're
- 0:59Speaker 1: pulling out the key engineering and calculation principles that turn
- 1:03Speaker 1: abstract physics into practical, quantified construction science. This deep dive
- 1:09Speaker 1: is your shortcut to understanding the applied math that governs
- 1:13Speaker 1: earth moving, excavation and hauling.
- 1:16Speaker 2: Okay, let's unpack this.
- 1:17Speaker 1: Let's start with the foundational structure.
- 1:19Speaker 2: To set the stage, we first have to understand the
- 1:21Speaker 2: industry itself. Construction is often broadly divided into two major categories.
- 1:26Speaker 2: There's vertical construction, which covers buildings.
- 1:29Speaker 1: Right the residential and commercial stuff most people think of exactly.
- 1:33Speaker 2: And then there's the segment we're focused on, horizontal construction,
- 1:36Speaker 2: also known as heavy construction.
- 1:38Speaker 1: This includes the massive public works highways, dams, tunnels, bridges, pipelines,
- 1:43Speaker 1: all the non building infrastructure.
- 1:45Speaker 2: And while private building construction still makes up you know,
- 1:48Speaker 2: the largest slice of the US construction PI, this horizontal segment,
- 1:53Speaker 2: especially public non building construction like roads and waterworks. That's
- 1:57Speaker 2: where you find the mega projects that require this tense
- 2:00Speaker 2: level of calculation.
- 2:01Speaker 1: And before a single permit is issued, the construction process
- 2:05Speaker 1: has to move through several critical preconstruction phases. It starts
- 2:09Speaker 1: with just recognizing.
- 2:11Speaker 2: The need and then determining the technical feasibility I mean,
- 2:14Speaker 2: can we actually build it? And of course the financial
- 2:17Speaker 2: feasibility can we afford it?
- 2:19Speaker 1: Then comes that long, detailed process of preparing final plans, specifications,
- 2:24Speaker 1: and critically getting regulatory approvals.
- 2:27Speaker 2: Oh, this is where the timeline often stalls. For major infrastructure,
- 2:31Speaker 2: you have to comply with zoning, building codes, environmental laws.
- 2:35Speaker 2: The environmental impact statement or EIS is often a colossal,
- 2:39Speaker 2: multi year effort that has to be nailed down before
- 2:42Speaker 2: you even think about breaking ground.
- 2:44Speaker 1: So once the plan is set, the owner needs to
- 2:46Speaker 1: decide how they're going to structure the build. The sources
- 2:49Speaker 1: outline three primary contracting methods.
- 2:51Speaker 2: And understanding the nuances of each tells you a lot
- 2:53Speaker 2: about the owner's priorities. Is it speed, cost control, or collaboration.
- 2:57Speaker 1: Let's start with the traditional one.
- 2:59Speaker 2: That's the general contractor model. The owner contracts a design firm,
- 3:03Speaker 2: first finalizes all the plans, and then contracts a prime
- 3:06Speaker 2: general contractor, often through competitive bidding, to execute the build.
- 3:11Speaker 1: So it completely separates.
- 3:12Speaker 2: Designing construction totally separate. But if the owner prioritizes speed
- 3:17Speaker 2: and minimizing conflict points, they might choose the second method, design.
- 3:23Speaker 1: Build, often called a turnkey contract.
- 3:25Speaker 2: Precisely, in design build, the owner hires a single firm
- 3:29Speaker 2: that's responsible for both the design and the construction, and.
- 3:32Speaker 1: The key advantage. There is speed.
- 3:33Speaker 2: It's speed because the designer and dilder are the same entity.
- 3:37Speaker 2: They can begin construction before the design is one hundred
- 3:40Speaker 2: percent complete. That's what enables the fast tracked delivery model.
- 3:44Speaker 2: The contract is often based on cost reimbursement rather than
- 3:47Speaker 2: a strict fixed price.
- 3:48Speaker 1: Which rewards efficiencies. What's the third option? Construction management?
- 3:52Speaker 2: Right? Construction management or CM is fundamentally different because the
- 3:55Speaker 2: professional construction manager acts purely as the owner's agent.
- 3:59Speaker 1: So they're like a specialized consultant.
- 4:00Speaker 2: That's a good way to put it. They advise on design,
- 4:03Speaker 2: manage scheduling, handle cost control, and oversee the execution of
- 4:07Speaker 2: separate trade contracts. CM typically assumes very little financial risk
- 4:12Speaker 2: for the final project cost. An owner chooses CM when
- 4:16Speaker 2: they want professional oversight across complex projects without assigning all
- 4:20Speaker 2: that risk to a single prime contractor.
- 4:22Speaker 1: That structural overview is essential because the contract is only
- 4:25Speaker 1: as good as our ability to execute, and execution starts
- 4:28Speaker 1: with understanding the very thing you're moving, the soil. Now
- 4:32Speaker 1: we get into the quantitative guts of heavy construction earth moving.
- 4:36Speaker 2: And this is where we really transition from management theory
- 4:39Speaker 2: to applied physics. Before you can select a piece of
- 4:42Speaker 2: equipment or even estimate a cost, you have to profile
- 4:45Speaker 2: the material. Engineers classify materials into five fundamental types gravel, sand, salt, clay,
- 4:51Speaker 2: and organic soil or peat, and.
- 4:52Speaker 1: We rely on specific standards to communicate that we do.
- 4:56Speaker 2: In construction. Two classification systems really dominate, the Unified Soil
- 5:01Speaker 2: Classification System and the AAHDO system. The HTO system, well,
- 5:07Speaker 2: it was developed by the American Association of State Highway
- 5:09Speaker 2: and Transportation Officials, so unsurprisingly it's geared heavily toward road
- 5:14Speaker 2: and subgrade.
- 5:14Speaker 1: Material and the unified system is broader.
- 5:16Speaker 2: Broader, and more common in general engineering.
- 5:19Speaker 1: Let's pause here because this is the financial core of
- 5:22Speaker 1: the entire deep dive. Understanding how material volume changes when
- 5:27Speaker 1: you handle it. This dictates both cost and payment.
- 5:30Speaker 2: This is truly fundamental. We measure earth in three principal
- 5:33Speaker 2: conditions or states. The first is bank volume denoted as
- 5:37Speaker 2: BCY for bank cubic yards.
- 5:39Speaker 1: And that's the material in its natural, undisturbed state, what's
- 5:42Speaker 1: in place before the shovel.
- 5:43Speaker 2: Hits it exactly, and that matters because the bank state
- 5:46Speaker 2: is the payyard. It's the unit volume for which the
- 5:49Speaker 2: contractor is typically paid by the owner.
- 5:51Speaker 1: Okay, so that's state number one. What happens when you
- 5:52Speaker 1: dig it.
- 5:53Speaker 2: Up, Well, once you dig it up, the particles separate,
- 5:55Speaker 2: creating air voids. This brings us to the second state,
- 6:00Speaker 2: volume or LCY. The volume has increased, sometimes significantly.
- 6:04Speaker 1: Like scooping sand.
- 6:05Speaker 2: It fluffs up exactly, It fluffs up and takes up
- 6:08Speaker 2: more space in the shovel than it did in the ground,
- 6:10Speaker 2: and you can't.
- 6:10Speaker 1: Leave it loose. Eventually, you put it in an embankment
- 6:13Speaker 1: or a roadway and you have to compact.
- 6:15Speaker 2: It, which is the third state compacted volume or CCY.
- 6:20Speaker 2: After rolling and tamping, the density increases and the volume decreases,
- 6:25Speaker 2: and crucially, a well compacted cubic yard is often less
- 6:28Speaker 2: volume than the original bankyard was.
- 6:31Speaker 1: So the difference between bank loose and compact it is
- 6:33Speaker 1: where a swell and shrinkage come in, and these are
- 6:36Speaker 1: the factor's management uses to prevent a budget meltdown.
- 6:39Speaker 2: Absolutely, swell is the percentage increase in volume from bank
- 6:43Speaker 2: to loose. If you're excavating rock, which is extremely dense
- 6:46Speaker 2: in place, it can swell by forty percent or more
- 6:49Speaker 2: when you blast it. Yeah, so that means one bank
- 6:52Speaker 2: cubic yard becomes one point four loose cubic yards in
- 6:55Speaker 2: the hauling truck. If you miscalculate that swell factor, you
- 6:59Speaker 2: suddenly need forty more truck space and time than you
- 7:01Speaker 2: plan for.
- 7:02Speaker 1: And the opposite happens when you fill.
- 7:04Speaker 2: That's shrinkage. Shrinkage is the percentage decrease in volume from
- 7:07Speaker 2: bank to compacted clay or softer ears often shrinks. If
- 7:12Speaker 2: a soil has twenty percent shrinkage, you need one point
- 7:15Speaker 2: to five bank cubic yards of material just to create
- 7:19Speaker 2: one compacted cubic yard of fill.
- 7:21Speaker 1: And if you don't account for that.
- 7:22Speaker 2: You realize too late that you haven't excavated enough material
- 7:25Speaker 2: from your cut sections to complete your fill sections, which
- 7:28Speaker 2: means you have to find and pay for material from
- 7:31Speaker 2: an outside source, what we call borrow.
- 7:33Speaker 1: So understanding these three states, in these two factors is
- 7:36Speaker 1: the difference between profitability and ruin.
- 7:39Speaker 2: It really is.
- 7:40Speaker 1: Now, let's move from a single cubic yard to a
- 7:42Speaker 1: whole highway. Project engineers need a way to visualize massive
- 7:46Speaker 1: volume distribution, and that's where the mass diagram comes in.
- 7:49Speaker 2: The mass diagram is a continuous curve plotted on a graph.
- 7:53Speaker 2: The x axis is the distance along the project center
- 7:56Speaker 2: line the link of the road, and theyx the y
- 7:58Speaker 2: axis represents the cumulative earthwork volume.
- 8:02Speaker 1: So what does the curve actually tell a manager?
- 8:04Speaker 2: Well, if the curve is rising, it means you're in
- 8:07Speaker 2: a cut section, you are excavating material. If the curve
- 8:10Speaker 2: is falling, you're in a fill section you're placing that
- 8:13Speaker 2: excavated material. A peak in the curve signifies the transition
- 8:17Speaker 2: point from cut to fill.
- 8:18Speaker 1: So you can just look at the diagram for a
- 8:20Speaker 1: stretch of highway and immediately see if you should be digging.
- 8:23Speaker 2: Or dumping exactly. And more importantly, by analyzing the diagram,
- 8:27Speaker 2: the manager can determine three crucial financial elements. First, the
- 8:31Speaker 2: length and direction of hall, Second, the average length of
- 8:35Speaker 2: hall for balance sections, which is vital for calculating cost.
- 8:39Speaker 2: And third, it immediately pinpoints areas that require borrow or waste.
- 8:44Speaker 1: Without this tool, you're basically guessing at your most expensive
- 8:47Speaker 1: operational costs. Okay, so if we connect this to the
- 8:50Speaker 1: bigger picture, Once we know the volumes in the hall distances,
- 8:54Speaker 1: we have to estimate how fast the equipment can actually
- 8:57Speaker 1: move the material.
- 8:58Speaker 2: Right, And this is where we get to the standard
- 9:00Speaker 2: production formula for excavating equipment. Equipment selection and job management
- 9:04Speaker 2: are directly tied to predictable output.
- 9:07Speaker 1: So what's the formula.
- 9:08Speaker 2: The core quantification principle for excavation is production is calculated
- 9:13Speaker 2: as C times S times V times B times E.
- 9:16Speaker 1: Okay, let's break down those variables. I'm guessing C is
- 9:19Speaker 1: cycles per hour and V is bucket volume. What about
- 9:22Speaker 1: the others?
- 9:23Speaker 2: Right? S is the swing factor. This is critical for
- 9:26Speaker 2: machines like hydraulic excavators. The swing factor adjusts the production
- 9:30Speaker 2: rate based on how far the operator has to rotate
- 9:33Speaker 2: to dump the bucket. Swinging one hundred and twenty degrees
- 9:36Speaker 2: takes a lot longer than swinging thirty degrees.
- 9:38Speaker 1: So you want to set up the job site to
- 9:39Speaker 1: minimize that swing.
- 9:41Speaker 2: Absolutely. The manager needs to optimize the truck spotting layout
- 9:44Speaker 2: to keep that swing factor high.
- 9:46Speaker 1: Then you have the two factors that are entirely dependent
- 9:48Speaker 1: on the material and the people B and E.
- 9:51Speaker 2: B is the bucket fill factor, which accounts for how
- 9:54Speaker 2: efficiently the bucket is loaded. Loose sand might give you
- 9:57Speaker 2: a one hundred percent fill factor or better, stick key
- 10:00Speaker 2: wet clay might cling to the sides, reducing your effective
- 10:03Speaker 2: volume down to eighty percent.
- 10:05Speaker 1: And e is job efficiency.
- 10:07Speaker 2: That's the percentage of the working hour that the machine
- 10:10Speaker 2: is actually moving dirt. This accounts for operator breaks, maintenance
- 10:14Speaker 2: waiting for trucks, weather delays. This is the manager's primary
- 10:18Speaker 2: lever for minimizing operational risk.
- 10:20Speaker 1: We also use equipment optimized for specific jobs like long reach.
- 10:25Speaker 2: For sure, grag lines are known for their extremely long reach.
- 10:29Speaker 2: They're suitable for large, wide area excavations and soft materials
- 10:33Speaker 2: like dredging canals.
- 10:35Speaker 1: And for really deep vertical shafts.
- 10:37Speaker 2: For that you use clamshells. Their vertical deeping ability makes
- 10:40Speaker 2: them perfect for deep trenches, constructing piers, things like that.
- 10:44Speaker 1: It's also worth a moment to mention trenchless technologies, especially
- 10:47Speaker 1: in cities.
- 10:48Speaker 2: Oh definitely, methods like pipe jacking, which uses hydraulic jacks
- 10:52Speaker 2: to force pipe segments horizontally through the soil or horizontal
- 10:56Speaker 2: earth boring. They allow for infrastructure placement with dramatic reduced
- 11:00Speaker 2: disruption and lower volumes of excavation.
- 11:03Speaker 1: Let's stalk safety and liability, which is deeply quantified in
- 11:06Speaker 1: the use of cranes. The source material is very clear.
- 11:10Speaker 1: There's one major factor that controls safe load capacity.
- 11:13Speaker 2: That factor is the operating radius, the horizontal distance from
- 11:16Speaker 2: the center of rotation to the hook. As that radius increases,
- 11:20Speaker 2: the safe lifting capacity just plummets exponentially.
- 11:24Speaker 1: And every crane has a tipping load.
- 11:26Speaker 2: It does, which is the load that causes the crane
- 11:27Speaker 2: to physically tip over. But safety regulations limit the maximum
- 11:31Speaker 2: safe capacity to a percentage of that tipping load, usually
- 11:34Speaker 2: eighty five percent for static loads.
- 11:36Speaker 1: And that's why we see mobile cranes using those strong
- 11:39Speaker 1: stabilizing beams the outriggers.
- 11:41Speaker 2: The outriggers are indispensable. They massively widen the effective base
- 11:45Speaker 2: of the crane, increasing its stability and thus its safe
- 11:47Speaker 2: lifting capacity. Every operator must use the manufacturer's load charts,
- 11:53Speaker 2: which are legal documents plotting safe capacity against the combination
- 11:57Speaker 2: of radius and boom length.
- 11:58Speaker 1: So this isn't just a number. This load chart dictates
- 12:02Speaker 1: the limit between a safe lift and catastrophic failure.
- 12:05Speaker 2: It absolutely does.
- 12:06Speaker 1: So what does this all mean for the hall cycle?
- 12:09Speaker 1: Moving the excavated dirt is often the single most expensive,
- 12:12Speaker 1: energy intensive part of the operation.
- 12:14Speaker 2: It is, so to control costs we have to calculate
- 12:18Speaker 2: vehicle travel time down to the.
- 12:19Speaker 1: Minute and estimating that hall time is broken into two sections.
- 12:23Speaker 2: That's right, First, the fixed time. These are repetitive actions
- 12:26Speaker 2: like loading, spotting the vehicle, and dumping. Second is variable time,
- 12:31Speaker 2: which is the travel time itself, and that is intensely
- 12:34Speaker 2: dependent on the vehicle's power and the road conditions.
- 12:37Speaker 1: This variable time forces us to confront physics through motion resistance. Yeah,
- 12:41Speaker 1: what exactly is the vehicle fighting.
- 12:42Speaker 2: Against the vehicle has to overcome total resistance or TR,
- 12:46Speaker 2: which has two main components. First is rolling resistance r R.
- 12:51Speaker 2: This is the resistance from the tires or tracks on
- 12:54Speaker 2: the travel.
- 12:54Speaker 1: Surface, and this is highly variable. A paved asphalt surface
- 12:58Speaker 1: might have a low RR of say forty pounds per
- 13:01Speaker 1: ton of vehicle weight.
- 13:03Speaker 2: Right, But if that road is poorly maintained, or if
- 13:06Speaker 2: a week of rain turns it into thick mud, that
- 13:09Speaker 2: resistance can skyrocket to three hundred or even four hundred
- 13:12Speaker 2: pounds per ton.
- 13:13Speaker 1: That's a ten full increase.
- 13:15Speaker 2: It's enormous. That difference represents a massive increase in required
- 13:18Speaker 2: engine power, fuel consumption, and cycle time. Managing rolling resistance
- 13:23Speaker 2: is often while you spend money just to maintain the
- 13:25Speaker 2: hall road itself.
- 13:26Speaker 1: Okay, So that's the messy variable one. The second component
- 13:29Speaker 1: is dictated by gravity and it's beautifully consistent.
- 13:31Speaker 2: That's grade resistance or GR. This is the resistance from
- 13:34Speaker 2: the incline, and it's calculated very cleanly twenty pounds per
- 13:38Speaker 2: ton of vehicle weight for each one percent of uphill grade.
- 13:41Speaker 1: So if one hundred ton scrapers going up a five
- 13:43Speaker 1: percent grade, that adds one hundred pounds per ton of resistance,
- 13:45Speaker 1: a fixed cost, a.
- 13:47Speaker 2: Fixed cost you have to overcome. Managers often combine the
- 13:50Speaker 2: two RR plus GR into a simplified metric called effective
- 13:54Speaker 2: grade to make performance calculations easier.
- 13:57Speaker 1: Now, beyond surface resistance in gravity, there are two other
- 14:00Speaker 1: environmental factors that can limit the usable power a machine
- 14:03Speaker 1: can put down.
- 14:04Speaker 2: Correct First, the effect of altitude internal combustion. Engines lose
- 14:09Speaker 2: power as elevation increases because the air gets less dense,
- 14:13Speaker 2: so engineers have to apply a d rating factor, typically
- 14:16Speaker 2: a three percent power decrease for every one thousand feet
- 14:19Speaker 2: above sea level.
- 14:20Speaker 1: And second, the ability to actually translate that power into movement.
- 14:24Speaker 2: That's the effect of traction. Maximum usable pulling force isn't
- 14:27Speaker 2: just about horse power. It's governed by the weight on
- 14:30Speaker 2: the drive wheels multiplied by the coefficient of traction. Rubber
- 14:33Speaker 2: tires on wet slick clay might have a very low coefficient,
- 14:37Speaker 2: maybe zero point.
- 14:38Speaker 1: Three, so a huge chunk of the engine's power is
- 14:40Speaker 1: just wasted in.
- 14:41Speaker 2: Slippage exactly regardless of the available horse power.
- 14:45Speaker 1: And all these calculations tr GRRR, altitude traction, they all
- 14:49Speaker 1: feed into a vital tool for managers, the manufacturer's performance curves.
- 14:52Speaker 2: These charts are like the engine's resume. They plot vehicle
- 14:56Speaker 2: speed against its available pulling power or rimple by calculating
- 15:00Speaker 2: the total resistance of the hall. Road Engineers use the
- 15:03Speaker 2: curve to find the maximum speed the vehicle can sustain
- 15:06Speaker 2: in each gear without stalling, so.
- 15:09Speaker 1: It provides the most realistic estimate of travel time. Without
- 15:12Speaker 1: using these curves, you're just guessing.
- 15:14Speaker 2: You're just guessing at your entire fleet's output. And it's
- 15:17Speaker 2: that combination of highly mobile loaders for moving material into trucks,
- 15:21Speaker 2: powerful dozers for short distance pushes, and efficient scrapers for
- 15:25Speaker 2: medium distances that lets the whole system function.
- 15:28Speaker 1: That continuous loop of quantifying soil volume changes, estimating production
- 15:32Speaker 1: rates with the formula and accurately modeling motion resistance.
- 15:36Speaker 2: That is the foundation of successful civil engineering project management.
- 15:40Speaker 2: This level of detail is what separates a predictable, profitable
- 15:44Speaker 2: job from a disaster.
- 15:45Speaker 1: Absolutely. We've covered the financial necessity of tracking soil volume
- 15:49Speaker 1: in its three states bank, loose and compacted, and the
- 15:53Speaker 1: three key resistances governing equipment performance rolling resistance, grade resistance,
- 15:58Speaker 1: and the often forgotten effect of altaude.
- 16:00Speaker 2: So let's reinforce this concept with the kind of fundamental
- 16:03Speaker 2: calculation you'd use on a job site every single day.
- 16:06Speaker 2: Imagine a fully loaded wheeled tractor scraper weighing one hundred
- 16:10Speaker 2: tons is traveling up a four percent grade. If the
- 16:13Speaker 2: rolling resistance factor for that Haull road is forty pounds
- 16:16Speaker 2: per ton, so a good surface, what is the ole
- 16:20Speaker 2: resistance in pounds that the vehicle must overcome?
- 16:23Speaker 1: All right, let's give you a moment to think through
- 16:24Speaker 1: those two resistance factors. Okay, here's how the engineering manager
- 16:28Speaker 1: tackles it. You calculate the grade resistance.
- 16:30Speaker 2: First, right, that's the four percent grade multiplied by twenty
- 16:33Speaker 2: pounds per ton for each percent, which equals eighty pounds
- 16:37Speaker 2: per ton of resistance. Just from the grade.
- 16:39Speaker 1: Then you add that to the rolling resistance, which was
- 16:42Speaker 1: supplied as forty pounds per ton, So your.
- 16:44Speaker 2: Total resistance is eighty plus forty, which is one hundred
- 16:46Speaker 2: and twenty pounds per ton.
- 16:48Speaker 1: And since the vehicle weighs one hundred tons, the total
- 16:51Speaker 1: force the engine has to supply just to overcome friction
- 16:53Speaker 1: and gravity is one hundred and twenty pounds per ton
- 16:56Speaker 1: multiplied by one.
- 16:56Speaker 2: Hundred tons, which is twelve thousand pounds of rimple just
- 17:00Speaker 2: to sustain movement. That calculation is the gateway to figuring
- 17:04Speaker 2: out your cycle time, your gear selection, and ultimately the
- 17:08Speaker 2: cost per cubic yard of material moved.
- 17:10Speaker 1: And this leads us to our final provocative thought for you.
- 17:13Speaker 1: The mathematical models we rely on, like the production and
- 17:17Speaker 1: resistance equations we just detailed, are only as accurate as
- 17:20Speaker 1: the input variables we choose. So if you estimate a
- 17:23Speaker 1: job efficiency of eighty three percent and use a coefficient
- 17:27Speaker 1: of traction suitable for dry earth, how drastically does the
- 17:31Speaker 1: operational cost of a multimillion dollar project change if a
- 17:35Speaker 1: rainy week shifts your rolling resistance factor from forty pounds
- 17:39Speaker 1: per ton to three hundred pounds per ton for an
- 17:41Speaker 1: extended period.
- 17:42Speaker 2: That's the true risk of construction management. Something for you
- 17:44Speaker 2: to mull over as you study those performance curves. Thank
- 17:47Speaker 2: you for diving deep into the foundations of heavy construction
- 17:50Speaker 2: with us.
- 17:50Speaker 1: We'll catch on the next deep dive.