Latest / Pharmacy Made Simple / Pharmaceutical Engineering Guides for New and Renovated Facilities: Commissioning and Qualification
Transcript
- 0:00Speaker 1: Welcome back to the deep dive. You know, usually when
- 0:02Speaker 1: we talk about pharmacology or the drug industry, we're zooming
- 0:05Speaker 1: in on the uh microscopic level, receptor binding, enzyme inhibition,
- 0:11Speaker 1: that kind of thing.
- 0:12Speaker 2: The stuff that happens inside the body exactly.
- 0:14Speaker 1: But today I want to zoom out, way out. I
- 0:16Speaker 1: want to walk onto the factory floor, because there is
- 0:20Speaker 1: a huge step between discovering a molecule and you know,
- 0:25Speaker 1: giving a pill to a patient. You have to actually
- 0:28Speaker 1: make the stuff. And you can't do that in a
- 0:30Speaker 1: facility that's just good enough.
- 0:32Speaker 2: That is putting it mildly. We are entering the world
- 0:35Speaker 2: of high stakes manufacturing. When you're building a facility to
- 0:39Speaker 2: make say injectables or sterile compounds, you aren't just dealing
- 0:42Speaker 2: with bricks and mortar, not at all. You're dealing with
- 0:44Speaker 2: federal laws, patient safety, and let's be honest, the potential
- 0:49Speaker 2: for massive financial catastrophe if you get it wrong, right.
- 0:52Speaker 1: I mean, if you spend five hundred million dollars building
- 0:55Speaker 1: a plant and the FDA comes in and says we
- 0:57Speaker 1: don't trust your water system. You don't just have a
- 1:00Speaker 1: plumbing problem, you have a business disaster exactly, And That
- 1:04Speaker 1: is why today is so important. We are decoding a
- 1:06Speaker 1: document that basically saved the industry from itself.
- 1:10Speaker 2: We are we're looking at the iSBC Baseline Pharmaceutical Engineering Guide,
- 1:14Speaker 2: Volume five Commissioning and Qualification, specifically the first edition from
- 1:19Speaker 2: March two thousand and.
- 1:20Speaker 1: One, which sounds incredibly dry on paper, Volume five Commissioning
- 1:25Speaker 1: and Qualification. But this was actually a revolutionary document, wasn't it.
- 1:29Speaker 2: It absolutely was. It was created by the International Society
- 1:32Speaker 2: for Pharmaceutical Engineering or ISPE. But the real headline here
- 1:37Speaker 2: is that they didn't do it alone. Oh, this is
- 1:39Speaker 2: a collaboration with the FDA. The guide actually opens with
- 1:43Speaker 2: a letter of support from Janet Woodcock, who was the
- 1:45Speaker 2: director of the Center for Drug Evaluation and Research.
- 1:48Speaker 1: That is a huge endorsement. That's essentially the regulator saying, please,
- 1:51Speaker 1: let's figure out a better way to do this together.
- 1:54Speaker 2: It signaled a massive shift. Before this guide, the industry
- 1:57Speaker 2: and the FDA were well often at all. This document
- 2:01Speaker 2: wasn't all a branch. It was the FDA saying, look,
- 2:04Speaker 2: we want to help you build compliance facilities without wasting
- 2:07Speaker 2: billions on useless paperwork.
- 2:09Speaker 1: So our mission today is to demystify this guide. Whether
- 2:13Speaker 1: you're a pharmacy student, a young engineer, or just someone
- 2:15Speaker 1: who wants to know how we ensure drugs are safe
- 2:18Speaker 1: without bankrupting the system. We're going to break this down,
- 2:22Speaker 1: and we.
- 2:22Speaker 2: Were going to do it by exploring the problem. It
- 2:24Speaker 2: tried to solve validation one upmanship.
- 2:28Speaker 1: I love that phrase, but I also hate what it implies.
- 2:31Speaker 1: Validation one up in ship. Okay, let's unpack that. Before
- 2:35Speaker 1: two thousand and one, why were companies acting so irrationally, Well, you.
- 2:40Speaker 2: Have to look at the background section of the guy.
- 2:42Speaker 2: Costs for new facilities were just skyrocketing. But it wasn't
- 2:46Speaker 2: because steel or concrete was getting more expensive.
- 2:48Speaker 1: It's the uncertainty.
- 2:49Speaker 2: It was total uncertainty. Companies were terrified of the FDA.
- 2:52Speaker 1: Oh wait, these are huge, sophisticated, multinational corporations. Why would
- 2:57Speaker 1: they voluntarily burn cash validating system that don't matter? That
- 3:01Speaker 1: sounds completely illogical.
- 3:03Speaker 2: It was illogical, but it was rationalized by fear. Imagine
- 3:06Speaker 2: you're a VP of engineering in say, nineteen ninety nine,
- 3:09Speaker 2: there's no clear baseline standard. If you decide not to
- 3:13Speaker 2: validate the lighting system in the cafeteria and then an
- 3:16Speaker 2: FDA inspector shows up and notes it as an observation.
- 3:19Speaker 1: You get a four eighty three citation. Your drug launch
- 3:21Speaker 1: gets delayed six months, and you probably.
- 3:23Speaker 2: Get fired precisely so you pay the insurance premium. You
- 3:27Speaker 2: validate the cafeteria lighting, you validate the office HVAC, you
- 3:31Speaker 2: validate the landscaping sprinklers. You do excessive documentation just to
- 3:35Speaker 2: be safe.
- 3:35Speaker 1: And if your competitor validates their sprinklers, you feel like
- 3:38Speaker 1: you have to validate yours too. Hence one upmanship.
- 3:42Speaker 2: You got it, and the result was an industry just
- 3:45Speaker 2: drowning in paper, with delayed drug launches and no actual
- 3:48Speaker 2: increase in patient safety. The ISPE Guide was created to
- 3:52Speaker 2: stop the madness. It established a baseline interpretation of cgmp's
- 3:57Speaker 2: current good manufacturing practice.
- 3:59Speaker 1: It said, here, here is the line. You don't need
- 4:01Speaker 1: to go ten miles past it exactly now. Just to
- 4:03Speaker 1: be crystal clear for anyone listening, this guide isn't a law,
- 4:06Speaker 1: is it. I mean, Jenna Woodcock wrote a nice letter,
- 4:08Speaker 1: but it's not a regulation.
- 4:09Speaker 2: That's a crucial distinction. The guide is owned by ISPE.
- 4:13Speaker 2: It is not an FDA regulation. However, it's a tool
- 4:17Speaker 2: a powerful one. If you follow its logic, you're on
- 4:21Speaker 2: safe ground because the FDA helped create.
- 4:23Speaker 1: That logic and the core philosophy is well, it's brilliant
- 4:27Speaker 1: in its simplicity.
- 4:28Speaker 2: It is restrict qualification practices to systems that actually matter.
- 4:33Speaker 1: And use what they call good engineering practice or GEP
- 4:36Speaker 1: for everything else.
- 4:37Speaker 2: That is the key. Not everything needs to be qualified
- 4:40Speaker 2: with a capital Q. Most things just need to be engineered.
- 4:44Speaker 1: Well, okay, but that brings up the million dollar question.
- 4:47Speaker 1: If the strategy is only focus on what matters, you
- 4:50Speaker 1: need a rock solid way to decide what matters.
- 4:51Speaker 2: You can't just guess no, you can't, and that brings
- 4:54Speaker 2: us to the system impact assessment. This is the heart
- 4:58Speaker 2: of the entire strategy. The guide P is that very
- 5:00Speaker 2: early in project you sit down and categorize every single
- 5:03Speaker 2: system in your factory.
- 5:05Speaker 1: Based on its impact on product quality. And it gives
- 5:07Speaker 1: us three buckets for this right.
- 5:08Speaker 2: Yes, the first and most critical is direct impact systems.
- 5:11Speaker 1: So how do we define that?
- 5:13Speaker 2: A direct impact system is one that's expected to have
- 5:15Speaker 2: a direct impact on product quality. So the system literally
- 5:19Speaker 2: touches the product where it controls a parameter that defines
- 5:22Speaker 2: the product, like the temperature in a sterile reactor.
- 5:26Speaker 1: That makes sense. If the reactor gets too hot, the
- 5:28Speaker 1: drug is ruined. Direct impact. So what happens if a
- 5:31Speaker 1: system falls into this bucket?
- 5:33Speaker 2: It triggers the full rigorous process. It must be designed
- 5:36Speaker 2: and commissioned using good engineering practice, and it's subject to
- 5:39Speaker 2: qualification practices. That means full testing, quality assurance, oversight, the
- 5:45Speaker 2: whole nine yards, all right.
- 5:46Speaker 1: Bucket number two. Indirect impact. This is where I think
- 5:50Speaker 1: people get tripped up.
- 5:51Speaker 2: This is definitely the category that causes the most debate.
- 5:55Speaker 2: Indirect impact systems are systems that support the facility but
- 5:58Speaker 2: don't directly touch or affect the product quality.
- 6:01Speaker 1: Can you give us the classic example?
- 6:03Speaker 2: The classic example is a chilled water system that cools
- 6:05Speaker 2: the jacket of a manufacturing tank.
- 6:07Speaker 1: Hang on, I need to push back on that a bit.
- 6:10Speaker 1: If the chilled water system fails, the tank gets hot.
- 6:13Speaker 1: If the tank gets hot, the drug cooks and is ruined.
- 6:15Speaker 1: That feels pretty direct to me.
- 6:18Speaker 2: And that is the single most common point of confusion.
- 6:21Speaker 2: Here's the distinction the quality of the chilled water. It's purity,
- 6:26Speaker 2: its bacteria account. It doesn't transfer to the drug.
- 6:29Speaker 1: Oh, because it never touches the drug. There's a steel
- 6:31Speaker 1: wall in between.
- 6:32Speaker 2: Exactly. We aren't worried about the water contaniny of the drug.
- 6:35Speaker 2: We're just worried about the water doing its job. If
- 6:38Speaker 2: the pump fails, your process control system on the tank,
- 6:42Speaker 2: which is a direct impact system, will detect the temperature
- 6:45Speaker 2: rise and stop the batch.
- 6:47Speaker 1: Ah. Okay, the safety net is already there. You don't
- 6:49Speaker 1: need to validate the water purity of the coolant, just
- 6:53Speaker 1: to note that the tank's temperature sensor works.
- 6:56Speaker 2: Exactly. It's an engineering reliability issue, not a pharmacitceutical quality issue.
- 7:01Speaker 1: That clicks for me now.
- 7:02Speaker 2: So for indirect impact systems, good engineering practice is sufficient.
- 7:06Speaker 2: You commission it, make sure it works, but you do
- 7:08Speaker 2: not need full.
- 7:09Speaker 1: Qualification, which saves the mountain of paperwork. And then, finally,
- 7:12Speaker 1: bucket number three is no impact system.
- 7:14Speaker 2: Right. This is your general office HVAC, the plumbing and
- 7:17Speaker 2: the restrooms, the cafeteria lighting. Zero effect on the process.
- 7:21Speaker 1: So the AHA moment here is that by strictly defining
- 7:25Speaker 1: these categories, you stop treating the office thermostat like it's
- 7:29Speaker 1: a sterile filling machine.
- 7:30Speaker 2: Exactly. You focus your energy and your documentation where the
- 7:35Speaker 2: risk to the patient actually lies. It's about being precise
- 7:39Speaker 2: with your resources.
- 7:40Speaker 1: So once we've done this assessment, we know what's direct,
- 7:43Speaker 1: indirect or no impact. We need a roadmap, a way
- 7:46Speaker 1: to actually build and test these things, and the guide
- 7:49Speaker 1: introduces the V model.
- 7:50Speaker 2: The V model is iconic and engineering. I mean the
- 7:53Speaker 2: diagram in the text literally looks like a giant letter V.
- 7:56Speaker 2: It connects the dreaming phase to the reality check phase.
- 7:59Speaker 1: I like that. Walk us through it.
- 8:01Speaker 2: So imagine the letter V. You start with the top left.
- 8:04Speaker 2: This is the design side. You begin with user requirements.
- 8:07Speaker 2: This is the big picture. I need a tank to
- 8:09Speaker 2: make product X simple enough. Then you move down the
- 8:12Speaker 2: left side, getting more specific. You go to functional design.
- 8:15Speaker 2: How does it work schematically? That all the way down
- 8:17Speaker 2: to the bottom point of the V, which is detailed design,
- 8:20Speaker 2: the nuts and bolts, the real nuts and bolts, What
- 8:22Speaker 2: specific valves are we buying? What's the wiring diagram?
- 8:25Speaker 1: So the left side is placing the order and the
- 8:27Speaker 1: right side is checking the receipt.
- 8:30Speaker 2: Checking the bag to make sure they got the order right.
- 8:33Speaker 2: For every step down the left side, there's a corresponding
- 8:35Speaker 2: test on the right side.
- 8:36Speaker 1: Okay, so let's talk about those tests. This brings us
- 8:39Speaker 1: to the acronyms that terrorize pharmacy students everywhere, IQ, OQ, and.
- 8:45Speaker 2: PQ, the holy trinity of validation. Yes.
- 8:47Speaker 1: Yeah.
- 8:47Speaker 2: At the bottom right of the V you have IQ
- 8:49Speaker 2: or installation qualification that corresponds directly to the detailed design.
- 8:54Speaker 1: Did we build exactly what we said we would build?
- 8:56Speaker 2: That's the question. Then, moving up, you have OQ or
- 9:00Speaker 2: operational qualification that matches the functional design. Does it operate
- 9:05Speaker 2: the way the schematics set it would? And at the
- 9:07Speaker 2: top right PQ or performance qualification that matches the user requirements?
- 9:12Speaker 2: Does it actually make the product we needed to make?
- 9:14Speaker 1: Okay? Now, sitting right in the middle of this via
- 9:16Speaker 1: bridging the gap is a word we've used a few times, commissioning.
- 9:20Speaker 2: Correct, and this is one of the most important concepts
- 9:23Speaker 2: in the guide. Commissioning is the bridge.
- 9:25Speaker 1: How does the guide distinguish commissioning from qualification because to
- 9:30Speaker 1: a layman they both sound like testing to see if
- 9:33Speaker 1: it works.
- 9:34Speaker 2: There's similar activities, but the intent is different. The guide
- 9:37Speaker 2: defines commissioning as a well planned, documented and managed engineering
- 9:43Speaker 2: approach to the startup and turnover of facilities. Basically, it's
- 9:47Speaker 2: what you pay engineers to do.
- 9:48Speaker 1: Yet the machine running tune it, debug it exactly and qualification.
- 9:54Speaker 2: Qualification is the assurance piece for those direct impact systems.
- 9:57Speaker 2: It's the formal evidence provided to the quality a unit
- 10:00Speaker 2: to prove compliance.
- 10:01Speaker 1: So commissioning is make it work. Qualification is prove it
- 10:05Speaker 1: works and is compliant.
- 10:06Speaker 2: That's a great way to put it. But here is
- 10:08Speaker 2: the efficiency hack the guide introduces. Commissioning can support qualification.
- 10:13Speaker 2: They shouldn't be two completely separate silos.
- 10:16Speaker 1: Give me a real world example of how that integration works.
- 10:18Speaker 2: Sure, let's look at a p and idea of piping.
- 10:20Speaker 2: An instrumentation diagram. It's a blueprint of every pipe in
- 10:24Speaker 2: valve okay, drink commissioning. An engineer has to walk down
- 10:26Speaker 2: the system and verify that every valve matches that diagram.
- 10:29Speaker 2: That's just standard engineering, right.
- 10:31Speaker 1: You have to do that anyway.
- 10:32Speaker 2: To turn the thing on, you have to. So the
- 10:34Speaker 2: guide says, if that engineer documents that walk down properly,
- 10:40Speaker 2: using what they call qualification practices, then you don't have
- 10:44Speaker 2: to do it all over again during the formal installation qualification.
- 10:48Speaker 1: You just reference the commissioning report.
- 10:50Speaker 2: Yes, it makes total sense. Why check the same valve twice?
- 10:54Speaker 1: It seems so obvious when you put it like that.
- 10:56Speaker 2: But the catch is the documentation. You can't just say yeah,
- 11:00Speaker 2: I looked at it. It's fine. It has to follow
- 11:03Speaker 2: a rigorous protocol. If you do good engineering, you get
- 11:06Speaker 2: the compliance for free.
- 11:07Speaker 1: Okay, let's get our hands dirty. Let's dive deeper into
- 11:10Speaker 1: those three testing stages. Let's start with IQ installation qualification.
- 11:15Speaker 1: If I'm walking onto the factory floor to do in IQ,
- 11:17Speaker 1: what am I physically doing?
- 11:19Speaker 2: You are doing a forensic investigation. You're verifying reality against
- 11:23Speaker 2: the blueprint. For example, the design said this pipe should
- 11:26Speaker 2: be three hundred and sixteen L stainless steel. You aren't
- 11:28Speaker 2: just trusting the box it came in.
- 11:29Speaker 1: You're looking at the markings on the pipe itself.
- 11:32Speaker 2: You're looking at the mill stamp etched onto the steel
- 11:35Speaker 2: to prove it is three hundred and sixteen L. Because
- 11:38Speaker 2: if it's a cheaper grade of steel, it might rust,
- 11:41Speaker 2: and that rust ends up in a vial of medicine.
- 11:44Speaker 1: So it's a physical check. The guide gives some specific.
- 11:46Speaker 2: Examples, right it does for a clean and play system.
- 11:49Speaker 2: They check welding documentation and they check passivation.
- 11:53Speaker 1: Let's pause on that word passivation. I hear it all
- 11:55Speaker 1: the time. What does it actually mean?
- 11:58Speaker 2: So stainless steel isn't naturally immune to rust, you have
- 12:01Speaker 2: to treat it. Passivation is basically giving this deal an
- 12:04Speaker 2: acid bath to create a protective oxide layer a shield.
- 12:08Speaker 2: If you don't have the certificate saying that was done,
- 12:10Speaker 2: that tank is basically scrap metal as far as the
- 12:12Speaker 2: FDA is concerned.
- 12:13Speaker 1: Wow, okay. And the guide also mentions checking loop documentation.
- 12:18Speaker 1: That sounds like electrical jargon.
- 12:19Speaker 2: It is. Think about the thermostat in your house. You
- 12:22Speaker 2: turn the dial to seventy degrees. You assume the furnace
- 12:25Speaker 2: knows you want seventy degrees R. A loop check is
- 12:27Speaker 2: the engineer physically heating the sensor to seventy degrees and
- 12:30Speaker 2: then running to the control room to see if the
- 12:32Speaker 2: computer screen says seventy degrees. You're verifying the wire isn't cut,
- 12:36Speaker 2: the sensor isn't broken, and.
- 12:38Speaker 1: The computer isn't hallucinating. I get it.
- 12:41Speaker 2: That is IQ.
- 12:42Speaker 1: Got it? So IQ is the static check. Everything is there,
- 12:45Speaker 1: it's the right material, it's hooked up correctly. Now we
- 12:48Speaker 1: move to OQ Operational Qualification.
- 12:52Speaker 2: OQ is about function. It tests the functional design. Does
- 12:56Speaker 2: the system operate correctly throughout its recommended ranges? This is
- 13:00Speaker 2: where you start pushing buttons.
- 13:01Speaker 1: But are we just turning it on and watching it
- 13:03Speaker 1: run smoothly?
- 13:04Speaker 2: No, that's too easy. The most critical part of OQ
- 13:08Speaker 2: is testing failure. You want to know what happens when
- 13:10Speaker 2: things go wrong.
- 13:11Speaker 1: So we're actually trying to break it.
- 13:13Speaker 2: We are trying to see if it saves itself when
- 13:15Speaker 2: it breaks. The guide mentions the power failure test. If
- 13:18Speaker 2: the power cuts out, does the system fail safely? Do
- 13:21Speaker 2: the valves close to protect the product? Or do they
- 13:23Speaker 2: pop open and dump everything on the floor.
- 13:26Speaker 1: That is so important. It's easy to prove it works
- 13:28Speaker 1: when everything is perfect.
- 13:29Speaker 2: It's harder to prove it fails safely. The source also
- 13:32Speaker 2: lists testing critical alarms and interlocks. For a vacuum system.
- 13:36Speaker 2: They mentioned vacuum leak testing. You pull a vacuum and
- 13:39Speaker 2: wait to see if it holds. If it leaks, you
- 13:42Speaker 2: fail OQ.
- 13:43Speaker 1: Okay, So IQ is it's built right? OQ is it
- 13:47Speaker 1: runs right? Now? We arrive at the final boss PQ.
- 13:51Speaker 1: Performance Qualification PQ is the.
- 13:53Speaker 2: Final assurance The purpose is to ensure the system performance
- 13:57Speaker 2: consistently achieves acceptance criteria.
- 14:00Speaker 1: Word there is consistently, So this isn't just turning it
- 14:03Speaker 1: on once. No.
- 14:05Speaker 2: PQ often involves testing over an extended period. The guide
- 14:09Speaker 2: mentions running three consecutive successful runs. If you pass once,
- 14:12Speaker 2: fail once, and pass again, you haven't finished PQ.
- 14:15Speaker 1: You need consistency. And there's a constraint here about who
- 14:17Speaker 1: runs the PQ, isn't there?
- 14:19Speaker 2: Yes, a very important one. During PQ, the system must
- 14:22Speaker 2: be operated using approved standard operating procedures SOPs by trained personnel.
- 14:27Speaker 2: You aren't testing the machine anymore, you're simulating the actual
- 14:30Speaker 2: manufacturing process.
- 14:31Speaker 1: The source gives a great example for an autoclave, a
- 14:33Speaker 1: giant steam sterilizer. What does PQ look like for that?
- 14:36Speaker 2: Oh, this is where it gets intense. For an autoclave,
- 14:39Speaker 2: PQ involves loaded chamber, temperature distribution and mapping. You literally
- 14:43Speaker 2: fill the chamber with the types of loads you'll be
- 14:45Speaker 2: sterilizing flasks, tooled gowns, and you place temperature sensors all over.
- 14:49Speaker 1: It to look for cold spots.
- 14:51Speaker 2: You have to prove there are no cold spots where
- 14:53Speaker 2: bacteria could survive, and they use biological indicator challenges. They
- 14:58Speaker 2: take vials of highly resis distant bacterial spores, stuff that
- 15:02Speaker 2: is incredibly hard to kill, and they hide them and
- 15:04Speaker 2: the hardest to reach places in the load.
- 15:06Speaker 1: And if the autoclave kills those spores, then you know
- 15:09Speaker 1: your cycle works.
- 15:10Speaker 2: That is the ultimate proof.
- 15:11Speaker 1: So we have the v model, we have the testing phases,
- 15:14Speaker 1: but the guide also mentions that none of this exists
- 15:17Speaker 1: in a vacuum. There are supporting programs.
- 15:20Speaker 2: Right, qualification isn't a one time event. It's a state
- 15:23Speaker 2: of control. The guide lists several foundations. First, training, it's
- 15:28Speaker 2: a regulatory requirement. If your operators aren't trained, your machine
- 15:32Speaker 2: isn't compliant, no matter how good this deal is.
- 15:35Speaker 1: And then there's change control.
- 15:36Speaker 2: This is massive once you've qualified a system. Once you've
- 15:40Speaker 2: done that IQOQPQ, you cannot just go in and change
- 15:43Speaker 2: a valve because you feel like it.
- 15:45Speaker 1: It's like breaking the seal on a warranty.
- 15:47Speaker 2: That's a great analogy. If you change a component, you
- 15:50Speaker 2: have to evaluate if you've invalidated your testing. You might
- 15:53Speaker 2: need to requalify. That is change control. Without it, your
- 15:57Speaker 2: validation status expires the moment you touch the machine.
- 16:01Speaker 1: It really highlights that this is a life cycle, not
- 16:03Speaker 1: a checklist.
- 16:04Speaker 2: That is the perfect way to summarize it.
- 16:05Speaker 1: So let's recap where we've been. We started with the
- 16:09Speaker 1: one upmanship problem. We looked at the ISPE guide solution,
- 16:13Speaker 1: the impact assessment.
- 16:15Speaker 2: We separate systems into direct impact and indirect impact.
- 16:18Speaker 1: We use the V model to map our design to
- 16:20Speaker 1: our testing, and we use IQOQ and PQ to prove
- 16:25Speaker 1: compliance for those direct impact systems.
- 16:27Speaker 2: And crucially, we leverage commissioning the engineering work to support
- 16:32Speaker 2: that qualification, so we aren't doing the same work twice.
- 16:34Speaker 1: That's the efficiency piece.
- 16:36Speaker 2: It is.
- 16:36Speaker 1: All right. Before we wrap this deep dive, let's test
- 16:38Speaker 1: if you're ready to save your future company some money.
- 16:41Speaker 1: We're going to give you a scenario based.
- 16:43Speaker 2: On the guide picture.
- 16:44Speaker 1: This.
- 16:45Speaker 2: You're the project manager for a new facility. You're installing
- 16:48Speaker 2: a waste neutralization system. This system takes the dirty water
- 16:52Speaker 2: from the plant, balances the pH so it's safe, and
- 16:56Speaker 2: sends it to the city sewer. It never touches the drug.
- 17:00Speaker 2: It ever touches the clean equipment.
- 17:01Speaker 1: Okay, I've got the picture. It's the sewer output waste
- 17:04Speaker 1: water only here's.
- 17:05Speaker 2: The question, does this system require the full holy trinity
- 17:11Speaker 2: of IQ, OQ and PQ.
- 17:13Speaker 1: Take a second, does the wastewater system need to be qualified?
- 17:17Speaker 1: What's the verdict?
- 17:18Speaker 2: The answer is no. Based on the ISPE guide, this
- 17:21Speaker 2: would be an indirect impact or possibly even no impact
- 17:24Speaker 2: system depending on the specific risk, meaning meaning we use
- 17:27Speaker 2: good engineering practice. We commission it to make sure it works. Obviously,
- 17:30Speaker 2: we don't have to pump ANSID into the sewer, but
- 17:32Speaker 2: we do not clug up the quality of department's inbox
- 17:35Speaker 2: with validation protocols.
- 17:36Speaker 1: If you got that right, you are well on your
- 17:38Speaker 1: way to understanding the philosophy of this guide.
- 17:40Speaker 2: And probably saving yourself a lot of headaches.
- 17:42Speaker 1: Before we sign off, I want to leave you with
- 17:43Speaker 1: one final thought. We've talked a lot about efficiency and
- 17:47Speaker 1: saving money in this deep dive, but I think the
- 17:49Speaker 1: real takeaway isn't just about the budget.
- 17:52Speaker 2: No, it's about clarity. When you strip away the unnecessary
- 17:56Speaker 2: paperwork for the non critical systems, you clear the clutter.
- 18:00Speaker 2: You allow your quality team and your engineers to focus
- 18:03Speaker 2: with laser precision on the systems that do touch the product.
- 18:07Speaker 1: Efficiency and engineering doesn't mean cutting corners on safety. It
- 18:10Speaker 1: means focusing your energy where the risk to the patient
- 18:13Speaker 1: actually lies, and that is what it's all about. Thanks
- 18:16Speaker 1: for listening to this deep dive into the ISPE Guide,
- 18:18Speaker 1: keep learning, stay curious, and we'll see you next time.
- 18:22Speaker 2: Goodbye, everyone,