Latest / Reliability Maintenance / Using Preventive Maintenance Programs as a Real Reliability Tool (Reissue)
Transcript
- 0:00Welcome back to another Episode of Maintenance Monday with James Couch
- 0:03from the FSO Institute.
- 0:05Where we dive into Reliability Maintenance at the Floor level.
- 0:05PM programs,
- 0:10we all have one, but do we truly use it correctly as the tool it was
- 0:14designed to do?
- 0:15I'm James Couch, and today we're gonna unpack that in the context of
- 0:19food manufacturing.
- 0:19And I'm Laura Mitchell.
- 0:22James, I love that opening, because in a lot of plants,
- 0:25a preventive maintenance program is basically just a big calendar and
- 0:29a stack of work orders that everybody complains about.
- 0:29Exactly.
- 0:34But at its core, a preventive maintenance program is a structured,
- 0:38scheduled set of activities designed to keep equipment operating reliably
- 0:42and safely by preventing failures before they occur.
- 0:45In food, that means it's a frontline tool for food safety,
- 0:48worker safety, and keeping the doors open.
- 0:48Right,
- 0:52and for folks who've been following this series,
- 0:54we've already talked about MTBF,
- 0:57MTTR, MTTF, and OEE.
- 1:00A solid PM program is where those metrics stop being abstract acronyms
- 1:05and start driving daily decisions.
- 1:05Yeah,
- 1:09so think about MTBF, mean time between failures.
- 1:12If your PM program is working,
- 1:14that interval stretches out.
- 1:16You're not fixing the same thing every few days.
- 1:18MTTR, mean time to repair, comes down because you've planned the work,
- 1:23you've got the right parts, and you're not scrambling at two in the morning.
- 1:23And
- 1:27OEE, overall equipment effectiveness,
- 1:29stops getting hammered by those little short stops and micro‑breakdowns.
- 1:33One of the big wins of good PM in food plants is cutting those frequent,
- 1:38annoying interruptions that kill throughput and create quality risk.
- 1:38Let's
- 1:43ground this in a concrete example: a thermoformer on a packaging line.
- 1:47If that thermoformer isn't maintained,
- 1:50you see film jams, sealing issues,
- 1:52vacuum problems.
- 1:53Every time it hiccups, somebody's rushing into a tight,
- 1:57hot, sometimes slippery area to clear a jam.
- 1:57So now it's not just downtime,
- 2:02it's worker safety.
- 2:04You've got hot plates, moving parts,
- 2:06sharp film edges, maybe even folks bypassing guards "just for a second"
- 2:11to get production running again.
- 2:13That's exactly the environment PM is supposed to prevent.
- 2:13That's right.
- 2:18A disciplined PM program for that thermoformer would address cleaning
- 2:22around the sealing station, inspections of chains and guides,
- 2:25lubrication where it's safe and appropriate,
- 2:28checking vacuum levels, calibrating temperatures and pressures,
- 2:31and verifying all guards and interlocks work as intended.
- 2:31And when you
- 2:36do that consistently, a couple of things happen.
- 2:38First, your MTBF on the thermoformer goes up-fewer failures.
- 2:43Second, you cut the number of emergency interventions in a hazardous
- 2:48area.
- 2:49That's less risk for your people and less chaos for your supervisors.
- 2:49The
- 2:54other big piece is culture.
- 2:55When a PM program is used correctly,
- 2:58it shifts the plant from firefighting to proactive reliability.
- 3:01Operators see issues early, maintenance is scheduled instead of begged
- 3:06for, and leadership has a measurable scorecard instead of just gut feel.
- 3:06And
- 3:11that scorecard is where those metrics-MTBF,
- 3:14MTTR, OEE-earn their keep.
- 3:16They tell you if your PM program is actually working,
- 3:20or if you've just created more paperwork without better performance or
- 3:23safer conditions.
- 3:23So if you're listening and thinking,
- 3:26"Yeah, we've got a PM program,
- 3:28but it sure doesn't feel like a reliability tool," you're not alone.
- 3:32In the next segment we'll break down the core building blocks so you
- 3:36can see where the gaps are and how to tighten them up.
- 3:36Let's talk about
- 3:39what a strong PM program is actually built on.
- 3:42Because it's more than just "grease it every Friday" taped to a clipboard.
- 3:42Yeah,
- 3:47if you start with "grease it every Friday," you're already in trouble.
- 3:50The first building block is an asset register with criticality ranking.
- 3:56That's just a fancy way of saying: list your equipment and decide which
- 3:59assets matter most for safety, throughput,
- 4:01and cost when they fail.
- 4:01And I'd add: worker safety and food safety should
- 4:07sit right at the top of that list.
- 4:09A thermoformer that can trap hands or burn people,
- 4:13or a piece of equipment that, if it fails,
- 4:16can contaminate product-that's high criticality,
- 4:20even if it's not the biggest motor in the plant.
- 4:20Exactly.
- 4:24Once you know what's critical,
- 4:25you define standardized PM tasks.
- 4:27These are clear, repeatable steps: inspections,
- 4:31lubrication, adjustments, cleaning,
- 4:33calibration, and planned part replacements.
- 4:36For each one you decide what to do,
- 4:38who does it, how long it takes,
- 4:40and how often.
- 4:40So on that thermoformer,
- 4:43standardized tasks might include checking the condition of sealing plates,
- 4:48cleaning product buildup off contact surfaces,
- 4:50inspecting chains and belts, verifying safety guards,
- 4:55and doing a basic visual hygiene check around the machine.
- 4:55The next building
- 4:59block is consistent failure mode definitions.
- 5:02You don't just write "broke" on the work order.
- 5:05You categorize: mechanical, electrical,
- 5:08process, or hygiene.
- 5:10And I'd argue you should note when a failure created or could have created
- 5:14a safety risk, too.
- 5:14That's huge for trend analysis.
- 5:17If everything is "mechanical," you can't see patterns.
- 5:21But if you can say, hey, we've had three process‑related failures on
- 5:25the thermoformer sealing station tied to contamination or adjustment issues,
- 5:30now you know where to tweak the PM content.
- 5:30Then we get into scheduling
- 5:35and work orders.
- 5:36At a basic level, you've got calendar‑based tasks-weekly,
- 5:39monthly-and usage‑based tasks tied to run hours or cycle counts.
- 5:44In a more mature setup, condition‑based triggers kick in when a measurement
- 5:48crosses a threshold.
- 5:48Condition monitoring is where you start using tools
- 5:52like vibration checks, temperature readings,
- 5:55maybe even oil analysis on certain assets.
- 5:58For that thermoformer, you might monitor vacuum pump performance,
- 6:03or temperature stability on the sealing bars,
- 6:06and only intervene when you see drift.
- 6:06That's how you move away from pure
- 6:10time‑based PM, which can lead to over‑ or under‑maintenance.
- 6:14You want enough frequency to protect safety and food quality,
- 6:17but not so much that you keep opening things up,
- 6:20creating more risk and more downtime than you're preventing.
- 6:20We also can't
- 6:24forget training and operator involvement.
- 6:26A good PM program doesn't say,
- 6:29"Maintenance does everything." Operators can handle basic autonomous
- 6:33tasks-simple inspections, cleaning,
- 6:36basic lubrication-while technicians focus on higher‑skill work.
- 6:36That's
- 6:41right.
- 6:41When operators own those frontline checks,
- 6:44you catch issues earlier.
- 6:45And they're usually the first to spot changes in noise,
- 6:48vibration, or product appearance.
- 6:50That's real‑time data you can feed back into the PM program.
- 6:50Which leads
- 6:55to the last building block: KPIs and feedback loops.
- 6:59You're watching MTBF, PM compliance,
- 7:03backlog, emergency work percentage,
- 7:05and OEE.
- 7:07If emergency work is high and MTBF is low on a critical asset,
- 7:12that's the program telling you,
- 7:13"Our PM strategy here isn't working."And you don't fix that by just adding
- 7:18more PMs.
- 7:19You analyze the failures, adjust the content or the frequency,
- 7:23or move some tasks from time‑based to condition‑based.
- 7:26That weekly or monthly review is where the PM program becomes a living
- 7:30tool, not a dusty binder.
- 7:30So if you've got the asset list,
- 7:35the standardized tasks, clear failure modes,
- 7:38smart scheduling, operator involvement,
- 7:41and a few solid KPIs on the wall,
- 7:43you're well on your way.
- 7:44In the next segment, we'll walk through a simple 90‑day roadmap to actually
- 7:49build or refresh that PM program and talk about the different PM types.
- 7:49Alright,
- 7:55let's say someone listening is thinking,
- 7:57"This all sounds good, but where do I start?" I like a simple 90‑day
- 8:01roadmap to get traction without trying to boil the ocean.
- 8:01Walk us through
- 8:06it, James.
- 8:07What happens in the first couple of weeks?
- 8:07Days one through fourteen,
- 8:11you build your asset list for a critical line and assign criticality.
- 8:15Ask: if this fails, what's the impact on food safety,
- 8:18worker safety, throughput, and cost?
- 8:21At the same time, standardize your failure categories-mechanical,
- 8:25electrical, process, hygiene, and flag anything with a safety angle.
- 8:25So
- 8:31you're not trying to map the entire plant on day one,
- 8:34you're picking one important line-say that thermoformer line-and getting
- 8:38really clear on the equipment and how it fails.
- 8:38Exactly.
- 8:42Then days fifteen through forty‑five,
- 8:45you create PM tasks for your top critical assets on that line.
- 8:49For the thermoformer, that might be inspection,
- 8:51lubrication, and a basic cleaning checklist,
- 8:54plus safety checks on guards and interlocks.
- 8:56You also configure your system-whatever you're using-to schedule those
- 9:00tasks and you train the people who'll execute them.
- 9:00And then days forty‑six
- 9:05through ninety is where the rubber meets the road.
- 9:08You start executing those PMs,
- 9:10you log every PM and every failure,
- 9:13and you hold a short weekly reliability huddle to look at what actually
- 9:17happened.
- 9:17That's where you calculate MTBF for that thermoformer,
- 9:22see how much emergency work you did,
- 9:24and ask, "Are we seeing fewer short stops?
- 9:27Fewer emergency interventions in hazardous areas?
- 9:30Is OEE improving?" If not, you adjust the PM content or the frequency
- 9:37instead of just doing more of the same.
- 9:37As teams go through that 90‑day
- 9:41cycle, they'll bump into different types of PM.
- 9:44Let's hit those quickly in plain language,
- 9:47because the terminology can sound more complicated than it is.
- 9:47Sure.
- 9:51Time‑based PM is triggered by the calendar or run hours-every week,
- 9:55every month, every thousand hours.
- 9:58It's great for routine cleaning,
- 9:59lubrication, and simple filter changes.
- 10:02The downside is, you can over‑ or under‑maintain because you're not looking
- 10:06at actual condition.
- 10:06Usage‑based PM leans on cycle counts or operating
- 10:11hours, so if one line runs harder than another,
- 10:14it gets more maintenance.
- 10:15That's handy for wear items tied closely to production volume.
- 10:19But you do need decent counters or you're guessing.
- 10:19Condition‑based PM
- 10:24uses sensor thresholds or inspections-vibration,
- 10:27temperature, oil condition, or visual checks.
- 10:30For example, watching vacuum pump performance on the thermoformer and
- 10:35acting when it drifts.
- 10:36It reduces unnecessary work but requires some monitoring tools and basic
- 10:40analysis.
- 10:40Predictive maintenance is where you use analytics and trends
- 10:45on those condition data points,
- 10:47usually for highly critical assets where failure is really expensive.
- 10:51Done well, it's the best balance of cost and reliability,
- 10:56but it does take investment in tools and skills.
- 10:56And then you've got proactive
- 11:01or RCM‑type actions focused on root cause elimination.
- 11:05Instead of just tightening the same bolt every week,
- 11:08you redesign the mount so it doesn't come loose.
- 11:10That's how you eliminate chronic failures entirely,
- 11:13though it often requires engineering time and sometimes capital money.
- 11:13Along
- 11:18the way there are some classic pitfalls.
- 11:20Over‑maintenance is one-doing so many PMs that you create extra downtime
- 11:25and extra exposure for workers in hazardous areas.
- 11:28Under‑maintenance is the flip side-stretching intervals until equipment
- 11:32fails and you're back in firefighting mode.
- 11:32You manage those trade‑offs
- 11:37by looking at your data.
- 11:38If you're spending a lot of time opening equipment up and not finding
- 11:41issues, maybe you can move some tasks to condition‑based triggers.
- 11:45If poor data quality is undermining decisions,
- 11:48you simplify the logging and train people on why accurate records matterSo
- 11:53to recap some practical next steps: pick one critical line and document
- 11:57its asset list and failure modes.
- 11:59Create three basic PM tasks for the top asset-inspection,
- 12:04lubrication, and a simple cleaning checklist.
- 12:07Log every PM and failure for thirty days,
- 12:11calculate MTBF, and hold a short reliability and safety huddle to decide
- 12:16the next move.
- 12:16Do that, and you're already using your PM program as a real
- 12:21reliability tool-not just a box‑ticking exercise.
- 12:24Over time, you'll see better food safety,
- 12:27better worker safety, higher OEE,
- 12:30and a lot less chaos in maintenance.
- 12:30And in our next episode,
- 12:34we're going to connect the dots to the system that holds all of this
- 12:37together: the CMMS.
- 12:40We'll talk about how to use your maintenance system to schedule,
- 12:44execute, and continuously improve your PM program instead of just storing
- 12:49data no one looks at.
- 12:49Laura, thanks for the conversation today.
- 12:49Thank you,
- 12:54James.
- 12:55And thanks to everyone listening.
- 12:55This has been Reliability Maintenance.
- 12:58Keep your people safe, your product safe,
- 13:01and we'll talk to you next time when we dive into CMMS and making your
- 13:05PM program really work.