Latest / Mechanical Engineering Made Simple / (#28) How Lean Manufacturing Cut Steel Mill Lead Time by 65% The Hybrid Pull System Revolution
Transcript
- 0:00Get ready to torque your nuts, harden your springs, and forge
- 0:03your mind into a bulletproof study guide.
- 0:10We are Mechanical engineering made simple.
- 0:13Welcome back design junkies to mechanical engineering made
- 0:15simple. So today we're doing a bit of an
- 0:17industrial demolition job. You could say we're tackling
- 0:21this well, this long held belief that lean manufacturing, the
- 0:26Toyota Production System magic only really works for nice clean
- 0:30discrete assembly lines. Yeah, like making cars or
- 0:33appliances. Things you can count easily.
- 0:35Exactly. But our mission today, we're
- 0:37taking those core lean ideas and throwing them right into the
- 0:40deep end. We're talking huge scale,
- 0:42continuous process industries, specifically steel
- 0:45manufacturing. Think massive furnaces, liquid
- 0:48metal stuff. That's fundamentally different
- 0:50from building an engine piece by piece.
- 0:52We're talking about taking muta waste elimination into
- 0:54environments where machines are gigantic, run nonstop, and you
- 0:57definitely can't just rearrange them over the weekend.
- 1:00And it's interesting, isn't it? Lean came from scarcity post WWI
- 1:03Japan. They had shortages of pretty
- 1:05much everything, capital, space, materials.
- 1:07Right. So the whole philosophy was
- 1:08built around using less. Less time, less inventory, less
- 1:12effort, but getting the same or even better output, higher
- 1:16quality, more variety. So the big question we're asking
- 1:19in this deep dive is can that same scarcity driven thinking
- 1:23really work when you're dealing with the sheer overwhelming
- 1:27scale and inflexibility of heavy industry like steel?
- 1:32That's the challenge. Let's dig in.
- 1:33OK, first let's quickly level set on the difference between
- 1:36these two worlds. Discrete manufacturing that's
- 1:38leans home turf. You make things you can count.
- 1:41Cars, phones, bolt. Individual units, yeah.
- 1:45Whereas continuous process industries, they make stuff you
- 1:47measure or meter oil, chemicals, cement.
- 1:51Or in our case, steel, liquid steel flowing.
- 1:52Right. Exactly.
- 1:53And historically, managers in these process industries,
- 1:56they've been pretty hesitant about lean tools.
- 1:58Why is that just the scale? Well, partly.
- 2:01You've got super high volume, but often very low product
- 2:04variety compared to discrete and the equipment, it's massive,
- 2:08fixed in place. You can't just create a cell
- 2:10like you would in a car plant when your blast furnace weighs
- 2:12thousands of tons. Right concepts like cellular
- 2:14manufacturing just seem impossible.
- 2:16They do. And then there are the setup
- 2:18times, the changeovers. They can be incredibly long and
- 2:22costly. That's a killer.
- 2:23I bet she can't just swap a die in 5 minutes.
- 2:26Not when changing over might mean shutting down a huge part
- 2:30of the continuous flow. We're talking potentially
- 2:32millions in lost production, maybe even risks to the
- 2:35equipment itself. So the traditional thinking is
- 2:39we need huge piles of inventory to buffer against these
- 2:42changeovers and potential downtime.
- 2:44OK, that makes sense from a risk perspective, but is that the
- 2:47whole story? Well, here's the key insight
- 2:49from the research. We looked at most of these
- 2:51so-called continuous processes. They're actually hybrids.
- 2:54Hybrids. How so?
- 2:56Think about that steel example. You have liquid steel, which is
- 2:59definitely continuous, flowing from the furnace through the
- 3:02cast. Very measured flow.
- 3:03But then what happens somewhere mid process, usually after
- 3:06casting, maybe some initial rolling, that liquid metal
- 3:09becomes solid. It gets cut into discrete
- 3:12countable units, slabs, coils, billets, whatever the form is.
- 3:17So there's a point where it becomes discrete.
- 3:19Exactly. It transitions from this non
- 3:21discrete flow to countable pieces and that specific point
- 3:25in the process, that transition, that's our opening, that's the
- 3:28toehold where we can start applying lean principles even if
- 3:32the very start of the process remains continuous.
- 3:34Interesting. So you don't try to force lean
- 3:37onto the blast furnace itself, but you find that discrete point
- 3:40downstream. Precisely, you leverage that
- 3:43hybrid nature. OK, so if we found our entry
- 3:46point, the next step in lean is always identifying the waste,
- 3:50right Muda? Absolutely.
- 3:52The goal is always eliminating anything that doesn't add value
- 3:55from the customers perspective. In heavy industry you see all
- 3:58the classic wastes, but some really stand out inventory
- 4:01obviously given what we just discussed.
- 4:03Those huge piles of coils or slabs just sitting there.
- 4:06Yeah. Overproduction often goes hand
- 4:08in hand with that inventory defects, which can be incredibly
- 4:12costly when you're dealing with massive batches and time related
- 4:16waste like those super long set up times we mentioned.
- 4:18So how do you find it all? It must be hidden in plain sight
- 4:21sometimes. The essential tool, really the
- 4:23starting point for any serious lean effort, is Value Stream
- 4:26mapping VM. Right, not just a simple flow
- 4:29chart. No, definitely not.
- 4:31VM tracks everything. Material flow, yes, but also
- 4:34information flow, the orders, the schedules.
- 4:36And critically, it tracks time. How long does each step take?
- 4:40How long does material wait between steps?
- 4:43How much inventory accumulates? It forces you to see the whole
- 4:45system, not just optimize one machine.
- 4:48Exactly. You visualize the entire value
- 4:50stream, from raw material to finished goods hitting the
- 4:53customer. And when the researchers applied
- 4:55VSM to the steel manufacturer ABS, the results were, well,
- 5:00pretty shocking. OK, let's hear it.
- 5:01What did the map reveal about their current state?
- 5:04For their annealed product line, the total production lead time
- 5:07start to finish was 46 days. 46 days, that's incredible.
- 5:11Over a month and a. Half.
- 5:13Yep. Now here's the kicker.
- 5:14They measured the actual value added time, the time the steel
- 5:17was actually being heated, rolled, cut, treat, you know,
- 5:20physically transformed. OK.
- 5:21How much is that? 5 days.
- 5:23Five days of actual work out of 46 days total lead time.
- 5:26Exactly. That means the value added time
- 5:29was only about 11, 7% of the total time the material spent in
- 5:32the system. So for 41 days, roughly 89% of
- 5:36the time that steel was just sitting.
- 5:39As inventory. As inventory waiting, waiting
- 5:42for the next process, waiting for a schedule change, waiting
- 5:45in a massive storage yard. And that right there exposed
- 5:49inventory as the single biggest source of waste and delay in
- 5:53their system. And that much inventory, it must
- 5:55mask us ton of other problems. Right, absolutely, it hides
- 5:58everything. Scheduling mistakes doesn't
- 6:00matter. Grab another coil from the pile.
- 6:02Quality issues from the caster. By the time you find the defect
- 6:05weeks later in the finishing mill, the conditions that caused
- 6:08it are long gone. Machine breakdowns just work
- 6:11through the buffer inventory. So reducing that inventory isn't
- 6:14just about saving space or capital.
- 6:16It's about forcing those underlying problems, the quality
- 6:19issues, the machine reliability, the scheduling hiccups out into
- 6:22the open where you have to fix them.
- 6:24That's the core principle. Inventory reduction reveals the
- 6:27rocks hidden beneath the water. OK so VSM shows a 46 day lead
- 6:31time mostly waiting. How do you redesign this using
- 6:35lean for the future state? Where do you start?
- 6:37You start by setting the pace you need to link production
- 6:40directly to customer demand. That means calculating the tact
- 6:44time. Tact time.
- 6:45The heartbeat of the system. Yeah, German word for rhythm.
- 6:47Exactly. It tells you how often you need
- 6:49to produce 1 unit, in this case a coil, to meet customer demand
- 6:52exactly. So for ABS, how did that
- 6:54calculation work? OK.
- 6:55The customer demand for this annealed product was 76,500 tons
- 6:59per month. You break that down, it's about
- 7:012550 tons a day, which translates to roughly 127 coils
- 7:07per day based on their average coil weight.
- 7:09A. 127 coils needed every single day, right?
- 7:11Then you look at the available work time.
- 7:13A standard day has 4440 minutes, 24 hours times 60 minutes.
- 7:18Got it. And the formula is.
- 7:19TAC time equals available work time per day divided by customer
- 7:23demand per day. So $1440 minutes divided by 127
- 7:27Ziller coils. Which comes out to approximately
- 7:29$11.00 and three 3 minutes per coil.
- 7:31So the target is 1 finished. Coil needs to roll off the line
- 7:36every $11.00 three, 3 minutes to keep up with demand.
- 7:39No more, no less. That's the rhythm the finishing
- 7:42end needs to March to. OK, but here's the tricky part
- 7:44again. The front end, the blast
- 7:47furnace, the caster, that's still continuous, right?
- 7:50It's pushing out steel constantly.
- 7:52How do you reconcile that push with this new $11.00 on three
- 7:56three minute pull rhythm at the finishing end?
- 7:59That's where the hybrid pull system design comes in.
- 8:01You acknowledge the front end has to push at least to some
- 8:03extent. You can't just turn a blast
- 8:05furnace on and off based on an 11 minute cycle.
- 8:07Definitely not. So you strategically decouple.
- 8:10You designate one single point in the downstream discrete
- 8:13process as the pacemaker. This is the only point that gets
- 8:16a formal schedule based on customer orders.
- 8:18And where was that for ABS? In their future state map, it
- 8:22was the temper mill. Basically the final processing
- 8:24step before shipping for this product.
- 8:26Everything upstream of the temper mill only produces to
- 8:29replenish what the temper mill consumes.
- 8:31So the temper mill pulls from the steps before it.
- 8:33Exactly. And those massive uncontrolled
- 8:36inventory piles we talked about? They get replaced by small
- 8:39controlled supermarkets. Like a grocery store shelf but
- 8:42for steel coils. Sort of, yeah.
- 8:44You have a limited defined amount of inventory, maybe a few
- 8:47hours or a day's worth, not 41 days worth held between key
- 8:51processes. When the downstream process,
- 8:54like the temper mill, withdraws a coil from its upstream
- 8:58supermarket, a signal, a Kanban, is sent back.
- 9:01Like an empty slot on the shelf signaling make one more.
- 9:04Precisely. The Kanban tells the upstream
- 9:06process, OK, I've used one now you can make one to replace it.
- 9:10It ensures you only produce what's actually needed when it's
- 9:13needed. It converts that push system
- 9:15into a pull system after the continuous part.
- 9:18But you still need some buffer between the continuous hot end
- 9:21and the first supermarket, right To absorb variations.
- 9:23Yes, you manage that buffer carefully.
- 9:25It's calculated, not just accumulated.
- 9:28And importantly, you also need to level the production Hajinka.
- 9:31Leveling meaning not making all of one type of coil on Monday,
- 9:36then all of another type on Tuesday.
- 9:38Exactly. If your customer needs, say,
- 9:40five types of coils this week, you don't run huge batches of
- 9:44type A, then type B, etcetera. That creates massive swings and
- 9:48makes changeovers a nightmare. Hijunca means smoothing out the
- 9:52production mix. So you'd make a little bit of
- 9:54each type more frequently. Right.
- 9:56They introduced the concept of pitch, a regular timed interval
- 9:59for releasing small batches of work into the system in the ABS
- 10:03future state. This was calculated to be around
- 10:05every $1.00, five, five hours. Every 90 minutes, a small mixed
- 10:09batch of coils needed by the pacemaker would be authorized
- 10:12for production upstream. So TAC time sets the overall
- 10:15speed, Cambian supermarkets control inventory flow, and
- 10:18Hijunca smooths out the mix. That sounds much more
- 10:21controlled. It is, but making the system
- 10:24work relies heavily on the physical processes being stable
- 10:27and reliable. You can't have a pull system
- 10:29operating on an 11 minute cycle if your machines are breaking
- 10:32down randomly for hours. Right, that smooth flow depends
- 10:35entirely on predictable uptime. Which brings us to the technical
- 10:39fixes needed. Absolutely.
- 10:40Tool number one has to be total productive maintenance or TPM.
- 10:44You have to attack equipment reliability head on.
- 10:47What was the problem at ABS? Just infrequent maintenance.
- 10:50Partly they had long scheduled shutdowns like maybe furnace
- 10:53reline every couple of months taking almost 1000 minutes.
- 10:56But the real killer was the unplanned downtime.
- 10:59The study mentioned the casters unplanned uptime followed an
- 11:02exponential distribution, specifically Expo ( 20,160
- 11:08dollars. close parenthesis minutes.
- 11:09Expo ( 20,106 dollars. Close parenthesis minutes.
- 11:15What does that mean in practice? It means on average it might run
- 11:18fine for about $20,160 minutes, which is roughly 14 days.
- 11:23But then it could fail unpredictably, and then downtime
- 11:26could last for several hours. That kind of variation just
- 11:28destroys a poll system. So TPM aims to prevent those
- 11:32failures. Yes, it shifts the focus from
- 11:34reactive fix it when it breaks or even just long interval
- 11:37preventative maintenance to proactive and predictive
- 11:39maintenance. It involves operators and daily
- 11:41checks, cleaning and lubrication.
- 11:43It means doing shorter, more frequent plan maintenance tasks
- 11:46to catch problems early. Maybe a four hour targeted
- 11:49maintenance every three weeks instead of that massive 10 hour
- 11:51shutdown every two months. The goal being maximizing OEE
- 11:55overall equipment effectiveness. Exactly.
- 11:58Reducing breakdowns, minimizing minor stops and speed losses,
- 12:01Making the machines reliable enough to support that tack
- 12:04time. OK, makes sense.
- 12:06What's tool #2? Set of production, often called
- 12:09SMA. Single minute exchange of dyes,
- 12:11though it applies to any changeover.
- 12:13Tackling those long change over times we talked about if you're
- 12:17running smaller level batches thanks to High Junka, you must
- 12:20be doing changeovers much more often.
- 12:22Way more often, if they take hours, the whole pull system
- 12:24collapses. SMA DS core idea is simple but
- 12:28powerful. Analyze every single step of a
- 12:31changeover. And figure out what you can do
- 12:33before the machine actually stops.
- 12:35Precisely. You separate internal setup
- 12:37tasks that absolutely must be done while the machine is
- 12:39stopped. Like actually swapping A roll
- 12:41from external setup tasks that can be done while the machine is
- 12:44still running. Like getting the next roll
- 12:46ready, preparing tools, preheating things.
- 12:49So find ways to convert internal time to external time.
- 12:53That's the game for the steel mill.
- 12:54They targeted things like the hot strip mill and the cold
- 12:57reduction mill, where work roles might be changed, say, 18 times
- 13:01a day. 18 times OK setup time is critical there.
- 13:04Absolutely. So polishing the next roll,
- 13:07getting the tooling ready, placing hoses, all that needs to
- 13:10become external work happening concurrently while the current
- 13:14coil is running. You fight for every minute saved
- 13:17on this frequent changeovers. Makes sense.
- 13:19Reliable machines, fast changeovers.
- 13:21What else? The foundation You can't forget
- 13:235S and visual system. I've S sort, straighten, shine
- 13:27or sweep, Standardize, sustain the housekeeping 1.
- 13:31It's way more than housekeeping. Especially in a heavy industry.
- 13:34There's often this culture of well, it's a steel mill.
- 13:36It's supposed to be dirty and cluttered. 5S directly combats
- 13:39that sorting, gets rid of junk straight, and organizes tools
- 13:42and parts shine keeps things clean, making abnormalities
- 13:46easier to spot. Like an oil leak on a clean
- 13:48floor versus a dirty. One exactly.
- 13:49Systematize and standardize. Make it stick.
- 13:52It frees up space and moves safety, boosts morale, and
- 13:55actually helps quality by making problems visible.
- 13:57And visual systems. What's an example there?
- 13:59Things like clear floor markings for inventory locations, or in
- 14:03the ABS case, they proposed a simple visual Kanban post near
- 14:07the shipping dock. Instead of relying purely on
- 14:10computer systems or paperwork which can have delays or errors,
- 14:14this post visually showed the status and position of coils
- 14:17ready for shipment. So a dock worker could instantly
- 14:20see, OK, this truck needs these three coils and they are
- 14:23physically right here in these marked spots and their status
- 14:26card is green. Right.
- 14:28It reduces errors like shipping the wrong coil or one that
- 14:31hasn't passed final inspection. Simple visual cues to prevent
- 14:35mistakes and keep things flowing.
- 14:37OK, so we have the hybrid pull system design supported by TPM
- 14:40for reliability, SMAD for quick changeovers, and 5S visual
- 14:44systems for foundation and air proofing.
- 14:47Did it work? What did the simulation show?
- 14:49The researchers modeled this whole future state system using
- 14:52simulation software arena I believe it was to predict the
- 14:55impact and the. Bottom line, the lead time.
- 14:57The results were pretty dramatic.
- 14:59The simulation showed that implementing the hybrid pull
- 15:01system along with the improvements from TPM and SMED
- 15:05reduced the average production lead time from the original $34
- 15:08and 2666 days they focused on in the detailed model.
- 15:11Wait, wasn't it 46 days initially?
- 15:13Ah. Good catch.
- 15:14The initial VSM showed 46 days across the entire process
- 15:18observed. The simulation model likely
- 15:20focused on a specific, slightly narrower part of that stream for
- 15:23detail analysis, which had a baseline of $34 and 266 days.
- 15:27Still a very long time. OK.
- 15:29So from 30 4.26 days down to. Down to 12.12 days.
- 15:34Wow. From over a month to under 2
- 15:36weeks, that's almost a 65% reduction.
- 15:38A massive improvement, yeah, nearly 2/3 of the lead time just
- 15:42that's. Huge.
- 15:43What does that do to? The value added percentage was a
- 15:44dismal 11%. Before it jumped significantly,
- 15:48the simulation showed the value added time as a percentage of
- 15:50total lead time increased to about 39%.
- 15:53Still room for improvement, sure, but a huge leap from 11%.
- 15:56Much less waiting, much more working.
- 15:58So it really proves the point, doesn't it?
- 16:01Even in these massive, supposedly inflexible continuous
- 16:04process industries, the core lean principles can be applied
- 16:08if you adapt them smartly. It shows the constraint often
- 16:12isn't the giant machinery itself, but the management
- 16:15system, the scheduling, the inventory policies, the
- 16:18maintenance approach, the lack of flow synchronization.
- 16:21That hybrid approach, finding that discrete point seems key.
- 16:25It's critical you have to find that interface between the
- 16:28continuous push and the potential for discrete pull, and
- 16:32manage it with tools like supermarkets and Kanban.
- 16:35It's a powerful demonstration that waste really is everywhere,
- 16:39Even baked into industries we think of is inherently
- 16:41inefficient due to scale. Continuous improvement is never
- 16:44really finished. Absolutely not.
- 16:46And the next logical step, the real frontier for this kind of
- 16:49thinking in heavy industry. Extending it beyond the plant
- 16:51walls. Exactly.
- 16:53Integrating the entire supply chain, looking for waste, not
- 16:56just inside the mill, but in the delivery of raw materials from
- 16:59suppliers and in the distribution network, getting
- 17:02finished goods to the final customer.
- 17:04That's where the next big gains are more likely hiding.
- 17:07Fascinating stuff, applying car factory thinking to melt shops
- 17:10and rolling mills and getting incredible results.
- 17:13Until the next equation design junkies, we are mechanical
- 17:16engineering made simple. Stay balanced, stay precise, and
- 17:19never stop building.