Durant Road Students Temporarily Relocated | Durham News
Durant Road Elementary students started school in temporary digs at Abbotts Creek Elementary while critical structural repairs are underway—engineers found walls were built off-plan, now being reinforced with rebar, grout, and steel panels. Seventy-five percent of masonry work is complete, with a return date set for August 17. Despite some logistical hiccups—including a dad mistakenly taken to the wrong school—district officials say communication is being improved and families are kept updated as the school gets back to its original home safely. Listen in comfort:Get a discount on a Soli…