- 0:05Speaker 1: Where construction progress stands on four hundred million dollars Lake
- 0:09Speaker 1: Michigan water project for Kendall County communities. Written by Joey Weslow.
- 0:16Speaker 1: This article is being read by an automated voice brought
- 0:19Speaker 1: to you by Everlett. With a project as massive as
- 0:23Speaker 1: the near four hundred million dollars Lake Michigan water sourcing project,
- 0:27Speaker 1: stretching around thirty miles across Naperville, Oswego, Montgomery out to Yorkville,
- 0:32Speaker 1: it can be difficult to scope the work's full extent.
- 0:36Speaker 1: Yorkville City staff provided a closer look at the project,
- 0:39Speaker 1: including what construction has already been started and what work
- 0:43Speaker 1: residents of Kendall County can soon expect. The first water
- 0:47Speaker 1: down the pipeline is expected in the Yorkville area by
- 0:50Speaker 1: the summer of twenty twenty eight. Montgomery should receive water
- 0:54Speaker 1: by twenty thirty. The project is a joint venture between Yorkville, Oswego,
- 0:59Speaker 1: and Montgomery, hooking up to existing water mains near Naperville
- 1:03Speaker 1: owned by the DuPage Water Commission. The three Kendall County
- 1:06Speaker 1: communities are sharing costs as the region's population continues to grow.
- 1:11Speaker 1: The cities supported the project because the long used underground
- 1:15Speaker 1: aquifer was being depleted at an unsustainable rate. Yorkville is
- 1:20Speaker 1: currently eyeing a tab of two hundred and twenty four
- 1:22Speaker 1: point four million dollars for their contribution to the project.
- 1:25Speaker 1: Shovels already in the ground. Staff associated with the Waterlink
- 1:29Speaker 1: project provided construction and bidding updates through the end of March.
- 1:34Speaker 1: The updates provide a glimpse into the direction of the
- 1:37Speaker 1: multi year project. The total project is divided into twelve
- 1:41Speaker 1: different segments, each involving its own engineering and construction work bids.
- 1:46Speaker 1: The first segment begins on Book Road in Naperville, extending
- 1:50Speaker 1: south and then east toward Kendall County. Construction has already
- 1:54Speaker 1: begun on this first segment, with excavating tractors removing older
- 1:58Speaker 1: water mains and crews replacing them with wider pipes to
- 2:02Speaker 1: accommodate the larger water capacity flow. By the end of March,
- 2:06Speaker 1: crews had replaced one eight hundred and fifty feet of
- 2:09Speaker 1: water main. The total segment beneath Book Road needs sixteen
- 2:13Speaker 1: thy three hundred feet of pipe installation. This segment is
- 2:16Speaker 1: expected to be completed by the end of the year.
- 2:19Speaker 1: Elsewhere along the project, Tree Clearing has begun at two
- 2:22Speaker 1: other segments, including the mainline West segment, which is in
- 2:26Speaker 1: Kendall County, running parallel between Oswego and Montgomery. No heavy
- 2:30Speaker 1: construction has begun on any segments, primarily located in Kendall County.
- 2:36Speaker 1: Out of the twelve segments, contracts still need to be
- 2:38Speaker 1: awarded on four of them. A contract has been awarded
- 2:41Speaker 1: for the South Branch West segment, which connects Oswego to Yorkville.
- 2:46Speaker 1: The final leg connecting Yorkville to the rest of the project,
- 2:49Speaker 1: the Illinois Route seventy one segment, currently has a bid
- 2:53Speaker 1: package under development. Work along Collins Road and Route seventy
- 2:57Speaker 1: one will fully connect Yorkville to the Oswego waters. According
- 3:01Speaker 1: to Waterlink staff, the program schedule remains on track to
- 3:05Speaker 1: achieve the targeted community water delivery dates. The Illinois Department
- 3:10Speaker 1: of Natural Resources requires cities receiving the water to reduce
- 3:14Speaker 1: non revenue water loss below ten percent to receive the
- 3:18Speaker 1: water by twenty twenty eight. Yorkville has been aggressively replacing
- 3:22Speaker 1: older water mains across town and installing more accurate water
- 3:26Speaker 1: meters in homes and businesses throughout the city. The city's
- 3:30Speaker 1: older water mains have been prone to breaks and leaks.
- 3:33Speaker 1: The city most recently approved another five point six seven
- 3:36Speaker 1: million dollars in watermin replacements and accompanying roadwork. In early March,
- 3:42Speaker 1: Yorkville staff said they expect all water main work, new
- 3:45Speaker 1: water receiving stations, and installation of storage tanks to be
- 3:49Speaker 1: completed by twenty twenty seven. Construction is already underway on
- 3:53Speaker 1: the North receiving station, the Northwest water tank, the South
- 3:56Speaker 1: receiving station, the Illinois Route one six one water main,
- 4:00Speaker 1: and the Bluestem water main. How is Yorkville paying for it?
- 4:05Speaker 1: The waterworks began when bids for the first leg of
- 4:08Speaker 1: the project came in around about one hundred million dollars
- 4:11Speaker 1: higher than expected. The sticker shock had city officials concerned
- 4:15Speaker 1: about contracts for the rest of the project. To cover
- 4:18Speaker 1: the rising costs, the city reapplied for one hundred and
- 4:21Speaker 1: seventy million dollar loan from the US Environmental Protection Agency,
- 4:26Speaker 1: thirty million dollars higher than the city's initial Water Infrastructure
- 4:29Speaker 1: Finance and Innovation Act y if I a loan, the
- 4:32Speaker 1: remaining costs of the project are to be financed through
- 4:35Speaker 1: the city's bond issuance and loan proceeds to help offset
- 4:40Speaker 1: the costs, The city recently approved higher water rates for users.
- 4:44Speaker 1: Residents will face about twenty percent annual increases for at
- 4:47Speaker 1: least five years. City administrator bart Olsen previously said if
- 4:52Speaker 1: contracts are continuously higher than expected, the city might need
- 4:55Speaker 1: to revisit approving even higher water rate increases. However, after
- 5:00Speaker 1: the first sticker shock, the subsequent contracts came in under
- 5:03Speaker 1: or around estimates. The second segment came in at twenty
- 5:06Speaker 1: three million dollars, less than original estimates of forty million dollars.
- 5:11Speaker 1: Another bid came in around fifty five million dollars, with
- 5:14Speaker 1: initial estimates eighty three million dollars. Yorkville Mayor John Purcell
- 5:18Speaker 1: said the subsequent legs are easier. Construction and engineering complexities
- 5:22Speaker 1: and scheduling issues likely drove up the first bid. Folson
- 5:26Speaker 1: said once the final bids open, the city should know
- 5:28Speaker 1: around ninety nine percent of the project's official total costs.
- 5:32Speaker 1: The WiFi alone has a thirty five year payback from
- 5:35Speaker 1: the time of substantial completion, which will take it through
- 5:38Speaker 1: twenty sixty five. Yorkville must cover one hundred and forty
- 5:41Speaker 1: five percent of the Wiffia loone debt and the three
- 5:44Speaker 1: point five percent interest rate to meet the obligations of
- 5:46Speaker 1: the loan