- 0:01Hello and welcome to the APM podcast.
- 0:03APM is a childhood body for the project profession.
- 0:06My name is Mike Heinen, online, editor for apm's, project
- 0:09journal, and your host. And our topic today is contracts
- 0:12and collaboration contracts. Create legally binding,
- 0:15obligations between the parties involved in a project, they
- 0:19describe the nature of those obligations and the actions that
- 0:21can be taken, if they are not met as such, the contract is a
- 0:24foundational document, whose content will come to define the
- 0:27project and how the work unfolds.
- 0:30It is there to provide certainty and protection to the parties,
- 0:33but there may be an opportunity for contracts to be used to
- 0:35create ongoing collaborative relationships, rather than
- 0:38simply defining strict requirements, and being regarded
- 0:41as a tool to give parties leverage, in the event of
- 0:43acrimonious circumstances to find out a bit more about how
- 0:47project professionals can enhance their knowledge of
- 0:49contracts and get more from their relationships.
- 0:51With contractors, I sought the input of a couple of experts.
- 0:55First up, I interviewed Sarah shooter, Sarah is an independent
- 0:59solicitor Advocate consultant and trainer whose company
- 1:02shooter Consulting limited as a niche practice in project,
- 1:05management and law. She's also running a webinar
- 1:09series for apm's contracts and procurements Sig entitled basic
- 1:12contract law for project managers.
- 1:14You can find a link to the first installment in the episode
- 1:16description. Hi Sarah.
- 1:24Thanks for joining us to begin with, please.
- 1:27Could you introduce yourself and give a bit of background to your
- 1:29role and your experience with contracts.
- 1:33Yes, of course. Thanks my gets really, really
- 1:35exciting to be here on this, AP and podcast, thank you for the
- 1:38invitation. So I'm an independent solicitor
- 1:42Advocate. I work for myself.
- 1:44My little company, choose, a Consulting limited.
- 1:48We've been going for about seven and a half years.
- 1:50Now, I specialize in construction, engineering and
- 1:55infrastructure, projects, including technology projects,
- 1:59and I'm working on projects of All Sorts, but mostly Within
- 2:03those sectors at the moment. If I look around my desk, I've
- 2:07got a couple of any C3, contracts and subcontracts.
- 2:11I've got a Professional Services engagement for project manager
- 2:15and a supervisor to look at for one of my clients I've got my
- 2:19collaborative workspace, open for a webinar that I'm sort of
- 2:25emceeing in September, on alternative dispute, resolution
- 2:29and I've got a nondisclosure agreement for Consulting.
- 2:32Engineer who I want to help him to get through and to nail a
- 2:36deal down. So there's lots going on.
- 2:39For sure, at the moment and summer season is no excuse.
- 2:41I've also got a pile of accounts in front of me because at this
- 2:45time of year, when my kids are off holiday and work, come
- 2:48naturally quietens down and deadlines elongates a little bit
- 2:53through projects, then I try and get some of the infrastructure
- 2:56as I call it to my own company done as well.
- 2:58And that includes things like the accounts, updating our
- 3:01template. It's getting some new training
- 3:04workshops ready for September. So yeah, we've got quite a lot
- 3:08on. We're juggling lot, but never
- 3:10complain. And always keep trucking.
- 3:13We're talking today about contracts for project
- 3:16professionals. So I want to start off with a
- 3:18very simple question, what are contracts?
- 3:20And why are they important in a project context?
- 3:23That's a really great place to start.
- 3:25A contract, is really an arrangement, a deal.
- 3:30It is the means by which you Regulate, an arrangement between
- 3:35two or more parties, generally speaking contracts, all over the
- 3:40world are what we call bilateral.
- 3:42So there between two people or two organizations, or one of
- 3:45each you can of course get multi-party contracts as well as
- 3:49the partnering variety of the alliance in variety and
- 3:52contracts come in all different shapes and sizes.
- 3:54So right at the very basic end you've got what we call a simple
- 3:59contract which is works and services for money.
- 4:02Me and right at the other end of the spectrum, you've got super
- 4:06complicated network of project contracts, which might have side
- 4:10agreements, which might have third party involvement, which
- 4:13might have all sorts of stuff to do with stakeholders and funding
- 4:17agencies and local public bodies and that sort of thing, but
- 4:22whatever size and shape of contact you've got, however,
- 4:24complex or simple. It is the hugely important in a
- 4:28project context because they regulate the relationship
- 4:31between the Teas. And therefore the parties
- 4:34understand what it is that is being done or delivered or
- 4:40procured whatever the correct verb is that hat, that attaches
- 4:43to, that contract for an amount of money. you've described how
- 4:48contracts appear on a spectrum from simple to complex, but are
- 4:52their components that are to be found in all contracts
- 4:55irrespective of their level of complexity, Yeah, there are
- 4:59actually and in order to have a contract in law, you have to
- 5:02have these components. So it's not that their
- 5:05components of a typical contract of such, but actually that if
- 5:08you want to have a contract in the eyes of the law, then you
- 5:11need to have these components. Now anybody who has listened to
- 5:15the APM, webinar series that I'm doing for the second time, we'll
- 5:22have heard in episode 1, what those components are now.
- 5:25If you haven't heard that, let me Let me in let you in on that
- 5:30on that secret. You need to have five components
- 5:32of a contract. The first is that you need to
- 5:35have an offer so that is an offer from one party to the
- 5:40other. To either do work.
- 5:43If it's coming from the seller or to go out to the market and
- 5:47ask for work. If you're the buyer of works or
- 5:49Services then you need to have the opposite, which is what we
- 5:52call acceptance. So it's an acceptance by the
- 5:55buyer of the sellers works or services.
- 5:58Or it's an acceptance by the seller to what the buyer is
- 6:02wanting to to buy. Now, in order to mesh that
- 6:05together you need something called consideration which is
- 6:08normally money when we're talking projects but it maybe
- 6:11money's worth, it doesn't have to be cash as such but it must
- 6:15be something which is unidentifiable swap between the
- 6:18parties. For those works and services
- 6:21that are being done. We also need an intention.
- 6:26We call it an intention to to create legal relations.
- 6:30And in essence, if you have a written contract, that will be
- 6:33taken for granted because you will have signatures to the
- 6:35contract. If you've got an exchange of
- 6:37emails that can perform a similar function with much more
- 6:41informal oral contracts, that's a bit more tricky because you
- 6:44haven't got any written evidence to show what that is.
- 6:47But if the parties agree it, and they can exchange a note on it,
- 6:51then again, that will more or less servers as the correct
- 6:54component for that and then we need something called Acity now
- 6:58capacity in commercial contracts is all about an authorized
- 7:03signatory. A person who has the authority
- 7:06on behalf of the organization to enter into the contract and if
- 7:11you are an individual, then you have authority on behalf of
- 7:13yourself so capacity, tends not to be too difficult in
- 7:17commercial contracts either. So there you have it.
- 7:20Five elements for a contract in law.
- 7:24Why is it important for project professionals to have a good
- 7:26grasp of contracts and not to regard them as just something
- 7:29for the legal department to deal with?
- 7:32Yeah, that's a really good question and it is so important
- 7:34for project professionals to have a good grasp.
- 7:37The first is that for themselves and for their organization to
- 7:41understand what are the works. All the services that they
- 7:44themselves are delivering for their client.
- 7:47What are those promises that they have made or probably have
- 7:51been made on their behalf? And then they are delivering
- 7:53Going for their organization. So you've got to understand that
- 7:57in order to deliver firstly, what you're supposed to be
- 8:00delivering but also to then, think about how to do it.
- 8:03Effectively efficiently. And of course profitably the
- 8:07other angle for project professionals, depends on the
- 8:09role and for certain project professionals you're going to
- 8:14need to have a better understanding of other contracts
- 8:17in the network of the project. For example, if you are
- 8:21appointed as a contract 200 JCT contract or your appointed as
- 8:27the NEC capitalized project manager, you're going to need to
- 8:31understand what it is that the contractors delivering for the
- 8:34client because you're there as the contract administrator,
- 8:37you're there as the person who is going to be looking at the
- 8:41work that's been done, that's going to be certifying what
- 8:44money is going to be paid over and perhaps making judgment
- 8:48calls and decisions about Works which haven't been done very
- 8:51well. All services which haven't been
- 8:53completely Added and therefore you don't want to certify that
- 8:55money ought to be paid. So you know, the commercial
- 8:59details of those other contracts can be blacked out can be
- 9:02redacted, but you do as a project professional who is
- 9:05dealing with being if you like an agent between the parties,
- 9:09you're going to need to understand what the scope of
- 9:11that other contract is and perhaps other contracts around
- 9:14the outside as well. What details within a contract
- 9:19should project professionals? Pay special attention to Okay,
- 9:24so the first thing that they need to pay attention to is the
- 9:27scope that's going to be the scope of Works themselves or the
- 9:30scope of services that are going to be delivered.
- 9:32And again, both within their own contract.
- 9:35But also with any contracts, which they are helping to
- 9:38administer through their Professional Services, they're
- 9:42going to need to also look at payment terms, because if you're
- 9:45a certify, you need to know what payment to be certifying.
- 9:49When, to be doing it, how frequently to be doing it and
- 9:53perhaps, Might even be details in the contract such as the
- 9:56format to use or template documents or a system that you
- 10:00need to have access to in order to be able to do that
- 10:03certification process for other project professionals as well.
- 10:07In particular for project managers, it's a really good
- 10:10idea to have a special look at the contract processes.
- 10:16Now there'll be tons of different processes but you can
- 10:20focus in on things like problem solving.
- 10:23Ooh, okay. What happens if a dispute
- 10:25arises? What is the process that the
- 10:27parties are going to use? How long is it going to take
- 10:30should any third parties be involved other important
- 10:33processes for project managers or things like a completion
- 10:37process? What does completion mean?
- 10:40How is it certified who needs to come and inspect?
- 10:43Are there any commissioning tests should videos and
- 10:46photographs be kept excetera, Etc.
- 10:48So the contract will have lots of detail in it.
- 10:51About various processes that project.
- 10:53Smells need to pay attention to and project managers in
- 10:56particular need to pay attention to those ones.
- 10:59And I suppose, if I think about it that the other process to pay
- 11:02attention to would be the dealing of any risk, which
- 11:05arises those are quite well established in many forms of
- 11:09standard contract. But again, there's something to
- 11:11pay attention to, there will be time scales to work to.
- 11:15There will be paperwork that needs to be exchanged and go
- 11:18backwards and forwards and then maybe assessments that need to
- 11:22be done as well by the project manager.
- 11:24So, I mean, you know, you could say could project professional,
- 11:27good pay attention to every contract term but but one never
- 11:31has time to do all of those things.
- 11:32So, for a project manager, those would be the three.
- 11:35I would concentrate on risk management, completion and
- 11:39money. And I suppose the fourth one
- 11:41which is a good one to have up your sleeve would be problem,
- 11:44solving and dispute resolution. Can you tell us a bit about
- 11:47Express and implied terms in the contract and what to watch out
- 11:51for? Yes, of course.
- 11:54It's pretty simple, actually Express.
- 11:57Terms are those which are expressed which have been
- 12:00written down, which have been agreed between the parties,
- 12:05whether orally or in writing. So an Express term is something
- 12:09that you can see and an implied term is the opposite.
- 12:13An implied term is silent. It's invisible.
- 12:17It may be something which are the parties have agreed but
- 12:19haven't written down. It may be something which they
- 12:22haven't. Gust at all, in which case there
- 12:26are scenarios where the law and this is done through a court or
- 12:29through an adjudicator, will step in and literally imply a
- 12:33term into a contract such that the contract will be interpreted
- 12:38using that employed term. So implied, terms can be quite
- 12:43useful. They can also be a bit scary
- 12:46because, of course, they are invisible, and that makes them
- 12:48in certain so people like Xpress terms, because you can see them
- 12:51in front of you. And because there, You can
- 12:53understand the regulation of the relationship between the
- 12:56parties. But implied terms, they can be
- 12:59positive, they can be negative. So, positive, implied term would
- 13:03be act reasonably and - implied term would be, don't commit
- 13:09fraud in your application for payment, you know, things like
- 13:12that, which people say, yeah. Okay, fair enough.
- 13:14I understand those, I don't need to write them down.
- 13:17They sound perfectly sensible and, you know, and that's
- 13:20absolutely fine. But there are other employed
- 13:23term. Terms which always come back to
- 13:25the threshold of reasonableness in law.
- 13:27So if you want to do something, which isn't going to be measured
- 13:30or benchmarked against the test of reasonableness, then you want
- 13:34to make it Xpress. For example, the work must be
- 13:38completed within three months, okay?
- 13:42In the absence of giving that Express term in the contract
- 13:45written down or agreed orally, the court would imply, or the
- 13:48law would imply an implied term which would be the works.
- 13:52Must be finished within a Reasonable time.
- 13:54And the reasonable time would be considered of all the
- 13:57circumstances in which that work is being done.
- 14:00Including resource availability, time of year, whether there are
- 14:06any subcontractors involved have complicated, etc, etc.
- 14:09So if you want to do something and have the certainty about it,
- 14:12the best way to do that is to include the statement as an
- 14:16Express term. What are some of the risks
- 14:19associated with poor practice around contracts?
- 14:22Now what could happen? Example, if a project
- 14:24professional doesn't give due care and attention to the terms
- 14:27of a contract. That's it.
- 14:29That's a great question. It's something that I often come
- 14:33across through, lack of Education, really and training
- 14:37of project managers. And this is what I something
- 14:39like this podcast is such a great opportunity to get that
- 14:42message out there for project managers.
- 14:45There's lots of risks and they and it comes back to to actually
- 14:49the question about having a good grasp of contracts.
- 14:52The first is that you need to project managers need to be
- 14:57aware of Their Own. Tracked.
- 14:59So if you don't deliver your own Services properly that can put
- 15:02you in breach of your own contract or your organization's
- 15:05contract more likely and that could be also professional
- 15:09negligence and that's, you know, hideous for all sorts of
- 15:12reasons, you know, on a wider sort of project level.
- 15:17If a project manager isn't playing their part then that the
- 15:22the agency role. If you like the certifier role,
- 15:25the independent assessor role that they Play that they broke a
- 15:30between that the client and the contractor is is is poorly
- 15:35regulated and is liable to be very fragile or able to be
- 15:39vulnerable to disputes. And basically, nobody really
- 15:42knows what they're doing. So then everybody is doing what
- 15:44they always do and they and they know solidly within their own
- 15:47technical expertise what they're doing, but they miss the nuances
- 15:50and the subtleties of the contract which are the bits that
- 15:53regulate where money flows? How time works?
- 15:57Who needs to do what when What is, you know, what is triggered
- 16:01by one party when somebody else does does a particular action?
- 16:06So the risks are that the project unravels not in a
- 16:09technical sense because technical people know their
- 16:12stuff and they will get to the end of the project, but it
- 16:14unravels in a governance side it unravels in a in a maturity side
- 16:20and it unravels in the sense of a relationship side because we
- 16:24don't have that tightness that regulator contract process which
- 16:28will Here and guide people step-by-step to the end.
- 16:33How can project professionals take a more active or proactive
- 16:36role in the Contracting process to help mitigate some potential
- 16:39risks? Yeah.
- 16:41I absolutely Advocate all of that and trying to give my
- 16:45project manager. Clients, a voice and encouraging
- 16:48those in-house project managers within Contracting functions to
- 16:53try and be a bit more vocal pre-contract in procurement in.
- 16:58In stage because they are the ones and this is literal.
- 17:03In some cases, get handed the contract and told to go off and
- 17:06get on with it. You know, our job is done and
- 17:10hands are washed and pre contract and procurement folks,
- 17:13get on with their next. Prospect the project manager.
- 17:16Meanwhile, is given something which they've never seen before.
- 17:20They haven't had any input into let alone be able to perhaps
- 17:24even influence how the terms of the the of the contractor put
- 17:29together. I was actually looking at one
- 17:31last week. This is a really good example.
- 17:34Actually, a project manager for an NEC subcontract.
- 17:39The sub contract was negotiated and the standard term reads that
- 17:43a particular action has to happen within 3 weeks.
- 17:47Now, the subcontractor has had that term reduced from three
- 17:53weeks down to two weeks and the Tractor, which is the
- 17:59subcontractors client has had that term increased from three
- 18:02weeks to four weeks. So suddenly people who before
- 18:07have to do in the vanilla form, do something within 3 weeks have
- 18:10either got less time than they thought.
- 18:12Or as a bonus, I got more time than they thought and the
- 18:16project manager on dealing with that, the subcontractor has only
- 18:18very recently been alerted to the fact that they now have two
- 18:22weeks to do something rather than three weeks.
- 18:25And it's those kind of things where project Jurors could
- 18:29really useful e, both be informed but also be consulted
- 18:34on, you know, you have to apply the real life to this stuff.
- 18:37What does it mean for that project manager to have only 2
- 18:42weeks to complete? Whatever the action is rather
- 18:44than three weeks is it possible? Is it okay, great?
- 18:48If it is but if it isn't always puts the organization at risk,
- 18:52or with more resource has to be pulled together in order to have
- 18:57the completion. Evidently in capably, within a
- 19:00two-week period rather than a three-week period, Then the
- 19:02project manager is going to have to be very agile.
- 19:04Is going to have to book to Pivot themselves in order to be
- 19:08able to do that. And of course, if they don't
- 19:09know that exist, how can they possibly plan to deliver the
- 19:13services that they that they need to deliver?
- 19:17In your experience to contracts. Tend to be viewed negatively.
- 19:20I is something that's only referred to, in an adversarial
- 19:22situation. Where are they regarded
- 19:24positively as the foundation for a good business relationship?
- 19:28Well, that of course is exactly how they should be saying.
- 19:30I mean the contract is it is what it is, in the sense that it
- 19:35is, the the document, hopefully, it's a document that makes life
- 19:38a lot easier. The document, by which the
- 19:41relationship is regulated, and I come back to this all the time
- 19:44because I think that is how it should be viewed.
- 19:46And certainly views differ, as to the usefulness of contracts
- 19:52and whether they are viewed positively or negatively and I
- 19:56guess, depending on any given situation depending on which
- 19:59side if you like, and there's a, there's an issue with sides as
- 20:02well. You could say that, you know,
- 20:06one term is positive for one party and negative for another
- 20:09or one process is helpful to one party.
- 20:11But, you know, unhelpful and burdensome to another so it does
- 20:14largely depend on the pair of eyes that is At it.
- 20:17But I try to get my clients to look at contracts as the
- 20:21regulating mechanism as the set of processes and tools that they
- 20:27have that have been agreed. And in some cases that their
- 20:30organizations have paid a lot of money for to have negotiated on
- 20:34their behalf. Not always, of course, a lot of
- 20:37it's done in house, but but you know, sometimes there is an
- 20:41investment piece. So what's the point of having
- 20:43made that investment whether it's time?
- 20:45Money, external. Internal people have needed to
- 20:49come together to put into shape this contract into being, to
- 20:53sign it, to send it through various gateways and governance
- 20:56and legal and everything else only for everybody to ignore it
- 20:59and do what they always do. So, in that sense, when you talk
- 21:03about the, the risks, about poor practice, and why it's useful,
- 21:08and helpful to project managers to really kind of stand up and
- 21:11say, look, I need to see this contract, I want to have a part
- 21:14in the negotiation of it. I want to be consulted.
- 21:17Because I'm going to be the one who's delivering there.
- 21:19Sits my neck on the Block. Then all of those things come
- 21:23together to say, well, we should be viewing contracts in a
- 21:26positive way. They aren't, they aren't there
- 21:29just to be dusted off when things go wrong.
- 21:31Because if, when things have gone wrong it's too late was
- 21:35actually the contract is there to help you and to steer you
- 21:38through all of the tools and processes and to help you to
- 21:42anticipate and have foresight about things, which could go
- 21:45wrong or which might go Go on or which look like they might be
- 21:48going wrong in which case there's stuff in the contract
- 21:51that's going to help you to bring it back on track, whether
- 21:54it's by risk management, or early warning, processes or
- 21:58flagging up notices and you know, pulling it, pulling an a
- 22:03an Emergency meeting together, that sort of thing.
- 22:05The contract will have that kind of thing in it.
- 22:08Within projects decisions often have to be made very rapidly.
- 22:12What is the implication when a quick decision creates working
- 22:15Arrangements that aren't covered by an existing contract?
- 22:18I think this happens very often and I think it's all credit to
- 22:23project managers micro decision-making and ability to
- 22:28Pivot that they can do these things confidently.
- 22:31And in most cases, fairly capably, there are risks, of
- 22:34course attached to creating working Arrangements outside of
- 22:38the On track, not least that you might do a heap of work and not
- 22:41get paid for it, which I suppose is that another sort of big dose
- 22:46of the real life bit of delivering contracts.
- 22:51The question around project manager, Authority is an
- 22:54interesting one because if the project manager is given
- 22:57sufficient authority to create these kind of working
- 22:59arrangements and we get the term of payment Etc sorted then
- 23:04actually, that can work very, very well and it can, it can
- 23:07push through things. He's speedily that might
- 23:09otherwise be slowed down by some, you know, torturous
- 23:13governance process or have to go through a bunch of stakeholders
- 23:16or whatever it happens to be, of course, depending on the size of
- 23:20the contract, and the amount of stakeholders that one has to
- 23:23talk to you about this stuff but those informal arrangements are
- 23:27in some cases necessary. And so the project manager being
- 23:32both capable in a contract fashion but also technically
- 23:35capable in terms of his or her. These can often work through
- 23:40those kind of working Arrangements in a very in a very
- 23:44sort of agile and practical fashion.
- 23:48The worry of course is the bit that you've done work that you
- 23:51don't get paid for and there's no easy way around that
- 23:56sometimes decisions have to be done.
- 23:57Sometimes that has to be the priority in the moment and the
- 24:01other stuff, the commercial side, if you like the financial
- 24:04side has to be dealt with after the event.
- 24:07It is a risk. But depending on the the, you
- 24:10know, the project at stake and what the pivotal decision that
- 24:12needs to be made is that might be the right decision in the
- 24:15moment and of course project managers need to be supported if
- 24:19they've been given you no authority to to move the project
- 24:24along as they see fit. So just to end with that like to
- 24:27ask you to tell us a bit more about the upcoming installments
- 24:30in the webinar series, you're running for the APM contracts
- 24:33and procurement Sig. I will, I'm really excited about
- 24:35this because we first ran this on Teen.
- 24:40I was I've known John broom for many years.
- 24:45John Bruno has is very well known in the APM and has been
- 24:49the chair of contracts and procurement Sig fought for many
- 24:51years. And John invited me.
- 24:53I think back in 2016 or 2017 to be thinking about this, this
- 25:00contract and project manager space.
- 25:01And it's been, it's an area that I've worked on, for many, many
- 25:04years. So I was really interested to
- 25:06help out. We first ran the serial He's in
- 25:082018, we had a bit of a break and then Corona has happened and
- 25:13everybody's been in a bit of a tailspin, of course, but we're
- 25:16back for 20 21 and it's new and refreshed.
- 25:19It's a three parter where we already had part number one in
- 25:25June. And that can be picked up by APM
- 25:28members. It's stored in the, in the apm's
- 25:31Library, part two is September and part three is in November in
- 25:37part 2. We're going to Focusing on how
- 25:39you build a contract and what project managers can use freely,
- 25:43add to that process. It's going to pick up on things
- 25:45like those examples of the the time scales for actions that I
- 25:49talked about earlier and part three is going to be some stuff
- 25:54on problem solving. And what happens?
- 25:56How can project managers help out when when things go wrong or
- 25:59they're threatening to go wrong? So we're talking about nipping
- 26:02problems in the bud and, and really getting the project
- 26:06manager to use all the abilities and, and all the contract
- 26:10knowledge that they will have by the end of the series, to put
- 26:13them in a good position to then, you know, go off them
- 26:17confidently and capably into the contract.
- 26:19Sunset. To find out a bit more about
- 26:24contracts in action. I spoke with Richard Cairns
- 26:26director of Korean Browns London project and program management.
- 26:29Team working in the Pharmaceuticals and Life
- 26:32Sciences sector. Richard is a fellow of a p.m.
- 26:34and a Committee Member of the program management Sig.
- 26:37We spoke about contracts including any C4 and how the
- 26:40pandemic might be influencing best practice around contracts.
- 26:47Thanks for joining us, Richard. So begin with please.
- 26:49Could you introduce yourself and give a bit of background to your
- 26:52current role? Yeah, hello everyone.
- 26:54So I'm Richard Cairns I'm a director at Korean Brown and I'm
- 26:57responsible for the London and Southeast pharmaceutical and
- 27:00life science project management team.
- 27:03So I've got nearly 40 members of Staff in my team and we provide
- 27:07projects program design Management Services as well as
- 27:11projects and planning schedule management a bit of Bim
- 27:14Management Services as well. And then document management
- 27:17projects happen and supports it's a various public and
- 27:20private sector clients The team were working with some quite
- 27:24large and complex and interesting projects at the
- 27:27moment and one of them even had a visit from Boris Johnson last
- 27:30year although we do lots of Not. So Glamorous, work for our
- 27:34clients as well. I've specialized in in
- 27:38pharmaceutical and life science program and project delivery
- 27:41open last kind of five years. But I haven't always worked in
- 27:44that sector. I've also worked in education,
- 27:47Healthcare government, and a bit of new build residential and
- 27:51regeneration as well. The last kind of 20 years and
- 27:55each of these sectors has their preferred unusual contract
- 27:59choices and project delivery preferences as well.
- 28:03You mentioned there are a couple of different sectors you've
- 28:05worked across. So like to ask you with in
- 28:08Farmer and Life Sciences, what Contracting disciplines does
- 28:11that sector use that perhaps distinguishes it from for
- 28:14example the public sector work that you've done in the past.
- 28:17Yeah really really good question.
- 28:20I suppose. Especially the team currently,
- 28:24you know, they're delivering pharmaceutical and life science,
- 28:27construction projects, and they vary in size and complexities.
- 28:32They work on lots of different types of projects, kind of 200
- 28:34million, plus new, build vaccine, manufacturing, and
- 28:38pandemic response, facilities, right down to konev refurbishing
- 28:42containment, Laboratories upgrading, or replacing kind of
- 28:45a Statewide infrastructure Building Services projects as
- 28:48well. I supposed, you know, most
- 28:51professional bodies Produce their own kind of standard forms
- 28:55of construction, contracts, and Engineering contracts as well.
- 28:59The most popular kind of standard forms are going to be
- 29:02the joint contrast tribunal the J, CT, which publishes Suite of
- 29:07Standard, Building contracts, and related contracts as well,
- 29:11such as collateral warranties, sub contracts as well.
- 29:15Another really popular ones new engineering contract any see
- 29:18which was originally kind of published in the early 90s after
- 29:22the landfill, Of construction Excellence report and the latest
- 29:26edition of our sin e C4 which was published quite recently
- 29:29more, you know, 2017. There's others as well.
- 29:33So, it's also the association for consultant Architects, quite
- 29:37often abbreviated to Aca and that's got the project partner
- 29:41in contract which is PPC 2000, which is kind of first,
- 29:45published it in the 2000 year, but it's been revised in 2008.
- 29:50And again in 2013 and the ACA statement was it was the
- 29:55original one, the first standard partment contract as well.
- 29:58So the types of contracts used in the team vary from.
- 30:01Come on. Sighs type scale, procurement
- 30:04and complexity of each of the projects that they're working
- 30:06on. And also, if they're in a public
- 30:08sector, private sector as well. You know, generally, we use cone
- 30:12of je, CT design, and build or Standard Building contracts
- 30:16without quantities there. They're more used in the private
- 30:20sector and then any see any C3 and any C4 and more used in the
- 30:25in the public sector. But it, you know, isn't a hard
- 30:27and fast Rule and both sectors and we can and do them.
- 30:31Do you? Both forms of contractors.
- 30:33Well, we've also got a few projects being delivered under
- 30:36the institution of chemical engineer so I can be contracts
- 30:39as well. What are some of these strengths
- 30:43or unique characteristics of the ik me contracts?
- 30:47I can be so that this this type of contrast.
- 30:50Drafted as a performance-based contract for the design and
- 30:53construction process plan really the other outputs, you know, and
- 30:57and output based projects. So it specifically addresses
- 31:00liabilities and And testing regimes appropriate for
- 31:04performance of plant. Really good example of that.
- 31:07We're using an ARCA me contract to deliver a new building
- 31:10simulator project. One of our, one of our clients
- 31:12are the moment is working wellness.
- 31:15It's exactly right for that type of project.
- 31:18Really, you know, I'd probably say, you know, generally most
- 31:22common use for my Contracting, the team at the moment, it's the
- 31:25only see for engineering and Construction contract which is
- 31:28abbreviated to ECC. And that's really The, the
- 31:32contracted choice for the public sector but that's kind of
- 31:35focused on the type of work that we're doing with a lot of
- 31:38government bodies of moment as far as specifics go.
- 31:41So kind of the NEC for PCC contract is got nine core
- 31:47Clauses. You know, these are split
- 31:48between like one is General to contractors responsibility three
- 31:53time for Quality Management. Five payment goes down, you
- 31:58know, six compensation events, 7 title 8.
- 32:02Listen Insurance streets at 29, termination.
- 32:05You've also got kind of options with NEC as well.
- 32:08And it goes from option, A down to option.
- 32:10F. These option A is kind of the
- 32:13price contract, activity schedule.
- 32:16Option b is price contract with bills of quantities, see Target
- 32:20contract with activity, schedules, and d-type contract
- 32:25with bills of quantities, a cost-reimbursable contrast and F
- 32:29management contract. You know, you choose the right
- 32:33option based on a client's kind of time, cost quality, and
- 32:36procure and Route objectives. Their project really.
- 32:40So would you say that customizability and flexibility
- 32:42are some of the key strengths of any C4?
- 32:46Yeah, you're definitely. Yeah, I mean, most of the, but I
- 32:49suppose the most commonly used options that are in the team use
- 32:52that, hey, which is kind of price contract, activity,
- 32:54schedule and Andy, which is kind of cost-reimbursable.
- 32:58So, they're kind of opposite opposite ends of the spectrum,
- 33:01really, for kind of fully designed or not, and you're
- 33:04doing a Time reimbursable type Arrangement.
- 33:07The NEC is split into three different types of Clauses.
- 33:11So, X Clauses, a kind of used for Can be optional clause in
- 33:16the contract that kind of standard Clauses in the contract
- 33:20W Clause is the use for dispute resolution.
- 33:23And I supposed to know your point on flexibility.
- 33:26You know, any see gives you the option to use said causes for
- 33:29additional Clauses in the contract and we can talk a bit
- 33:32later about how they can be used to kind of achieve client
- 33:37specific objectives in certain areas as well.
- 33:41You've plugged recently for a p.m. about the construction play
- 33:43book. Published by the government,
- 33:45tells us a bit about what the Playbook is, and why?
- 33:47It's valuable for the project profession.
- 33:50Yeah, that's right. Yeah we wrote A Blog for the APM
- 33:53in June this year. It was the construction Playbook
- 33:57and how sustainable Contracting is guiding the government's
- 33:59recovery plans. So I'm a Committee Member for
- 34:03the APM program management sick and I try to provide kind of
- 34:06thought leadership on appropriate subject, matter
- 34:08topics. And, you know, encourage
- 34:10collaboration a bit of knowledge, sharing transfer.
- 34:14And I really enjoy that part of my role for the a p.m.
- 34:17So I get involved in a in webinars and writing thought
- 34:19leadership. Schools.
- 34:21I've got a follow-up block it in August, on the construction
- 34:25Playbook as well and it's going to focus on Modern methods of
- 34:28construction. So or MMC so I've got a busy few
- 34:32weeks ahead but specifically answering your question the
- 34:35construction Playbook as opposed as part of the government's
- 34:38strategy to build our way to a better economy.
- 34:41You know, they've committed to delivering construction
- 34:43engineering projects and programs.
- 34:45You know what you build schools, hospitals prisons and major
- 34:49instrument. Infrastructure Works to support
- 34:51the economic recovery from the pandemic and delivering
- 34:55excellent public sets of works. We are crucial part, the
- 34:57government's recovery plan. I think they've committed
- 35:00something like 37 billion pounds worth of public sector contracts
- 35:04to go to the market over the next year.
- 35:06So, you know, we're talking big numbers really to help to help
- 35:11me that aim that the cabinet office is produced the
- 35:14construction Playbook. You know it's abbreviated down
- 35:18to the Playbook is what is commonly known?
- 35:20Apps and that provides kind of government guidance on sourcing
- 35:25and Contracting Public Works projects and programs really The
- 35:29Playbook supports the government's Ambitions and plans
- 35:32to transform the public sector estate and infrastructure
- 35:35networks. Kind of going through over the
- 35:38next decade and Beyond really supporting their aims to kind of
- 35:41build build back better faster. And Greener, you know,
- 35:44sustainability is a real key key to it as well.
- 35:48It focuses on kind of The process of programs and managed
- 35:51correctly with the optimum, kind of purple best contractual
- 35:55strategy and solution from the outset of really whether the
- 35:59scope is delivery of a school, a hospital and major
- 36:03infrastructure project, the principles of the Playbook of
- 36:05really the same state detail the approach for assessing kind of
- 36:09procuring and managing Public Public Works, and projects and
- 36:13programs, really. So it's really about best
- 36:16practice and how it applies across the board.
- 36:19Yeah, yeah definitely. Yeah.
- 36:21I mean one of the one of the key principles is creating an
- 36:24effective kind of Contracting environment.
- 36:26So, you know, that's one of the one of the 14 key policies of
- 36:31the Playbook and its aim to ensure that contrast is
- 36:34structured to support an exchange of data.
- 36:38No Drive collaboration is a really big theme.
- 36:41Improved value manage risk with a drive for kind of continuous
- 36:45Improvement as well. But as if there's another real
- 36:48Theme coming from the Playbook which the government wants to
- 36:51still focus on outcomes to create long-term value kind of
- 36:56all through successful project delivery.
- 36:58So they want this to create a contrasting landscape that
- 37:00delivers Converse a sustainable resilient and effective
- 37:04relationship between Contracting parties and a supply chain.
- 37:07They just they don't want one off contrasted with long-term.
- 37:11Collaborative, relationships, being Bill going forward, which
- 37:13is great. I think for the industry
- 37:15thinking a bit more about collaboration.
- 37:17How can contracts be? Used to foster a more
- 37:20collaborative way of doing projects.
- 37:23Yeah, cut contracts. And there are spoke wording
- 37:26causes and requirements can be used to implement kind of many
- 37:29specific clients or project requirements including kind of
- 37:34promoting and encouraging collaborative working and
- 37:36practices kept going back. You know the 1994 constructing
- 37:42the team commonly known as the lamp from reports.
- 37:45That the starting point for most, you know, most recent
- 37:48change changing agenda in the UK construction industry.
- 37:52The why? Fred growth of partnering and
- 37:55subsequent kind of collaborative working, can all be kind of
- 37:57traced back, right? You know, right away back to
- 38:00that 1994. All Anthem report, really the
- 38:04NEC particularly, you know, approaches and the way
- 38:07approaches the management managing of contracts.
- 38:10It was really endorsed him in the lamp and Report, you know?
- 38:14And which was kind of the government's review of
- 38:17procurement and contractual arrangements and UK construction
- 38:19industry at that time. So going back nearly kind of
- 38:23What 20 years, but the use of any she contrast with Play-Doh a
- 38:28key key in helping part in the industry to kind of do things
- 38:32differently and better with collaboration kind of right at
- 38:35the heart of this, you know, in my view as well.
- 38:38The four pillars of success are all kind of embodied in the NEC
- 38:42contract and those are kind of you know, one working together
- 38:46to stack together, you know, 3 adding value.
- 38:50And then for Innovation they're all the key principles of I'm
- 38:54fully embodied into the NEC country.
- 38:56I really and they should all be embodied into kind of most
- 38:59contracts in contracted approaches and processes really
- 39:02in my view. How do you think the change in
- 39:04working conditions brought about because of the pandemic has
- 39:07impacted the way we need to think about Contracting
- 39:10practices? Yeah, another another really
- 39:12good question, really, so I'm very currents as well.
- 39:16So one of the one of the changes in working condition of
- 39:18practices that I've personally experienced in a pandemic is
- 39:21obviously remote working and remote.
- 39:23Idiot delivery. You know, we're all kind of
- 39:25working from home, a lot of use of kind of virtual kind of
- 39:29meeting software, you know, Ms. Teams is a great example,
- 39:33really? I don't think I'm unique here
- 39:36and probably the whole country of you saying something similar,
- 39:38but I suppose there's a working example.
- 39:42Last year I was working on a, on a project, using a development
- 39:45management agreements, which stated a requirement for
- 39:49contractual notice under under that kind of contract or
- 39:53agreement. It's be shoed in hard copy
- 39:55recorded correspondence, delivery with wet signatures and
- 39:59you know obviously working remotely in a pandemic and kind
- 40:02of mitigating spread and kind of this.
- 40:07The spread of the virus that just wasn't practical or
- 40:09appropriate for those type of working conditions in the
- 40:12pandemic, really? I suppose it's worth noting as
- 40:16well. That NEC for the new the new
- 40:19contract or newish contract. That came out in 2017.
- 40:23Mmm. Braces.
- 40:23All these kind of digital changes that are happening in
- 40:26the construction industry especially around communication
- 40:29and, and been really, which are essential in this ever-changing
- 40:34world. Particularly the moment, you
- 40:35know, in the pandemic or, or coming out of the pandemic, I
- 40:38think we've changed over the last 18 months and and
- 40:42certainly, for the better really another highly current topic.
- 40:45Of course, is sustainability. What are some of the ways in
- 40:49your experience of addressing sustainability concerns through
- 40:52contracts? Yeah, especially if a client has
- 40:56a particular sustainability ambition or Target that they
- 41:00want to achieve through a project on way to do this.
- 41:04It could be through the use of, I'll use any see again as a
- 41:08specific example, but you know, could use a specific Z Clause,
- 41:12we talked a bit about that earlier, didn't we?
- 41:14You know, as an additional Clause to the contract under the
- 41:17NEC engineering and Construction contract?
- 41:21You know, it could be worded to include A specific
- 41:24sustainability or carbon reduction Target as a key
- 41:27performance indicator or or kpi as a contract requirement.
- 41:32And, you know, there's a number of reasons that could drive
- 41:36this. You know, a local Authority
- 41:37planning condition of building regulation part L requirements
- 41:41or a Brie am Target or aspiration.
- 41:45There's also carbon reduction kind of aspirations aimed a
- 41:49supposed minimizing environmental environmental
- 41:51impact of your business cutting Waist and acts extravagance as
- 41:56well and kind of generate just minimizing your carbon
- 41:59footprint, really? It's very, very current and
- 42:02topical at the moment. The UK government recently
- 42:04stated it is NetZero strategy targets set by the climate
- 42:09change Act of 2008 and at least expose 100 percent reduction in
- 42:15UK greenhouse gas emissions by 2050 compared to those two kind
- 42:18of 1990 levels. So contracts, then requirements
- 42:22play Key Parts in Meeting those requirements really, you know,
- 42:27as well as sustainability they could be used in other areas as
- 42:30well and, you know, we're seeing this a lot, you know, myself and
- 42:34the team. You know, this is coming through
- 42:35a lot in after areas, where kind of public static clients using
- 42:39said Clause is to implement social value or corporate and
- 42:43social responsibility aspirations through the
- 42:46procurement effect construction projects.
- 42:48And this this is all filtering down into the supply chain.
- 42:50Are there any specific or unique?
- 42:53Meek considerations around sustainability for building
- 42:55projects within farmer and life sciences.
- 42:59Yeah, I think I think I wouldn't say there's anything
- 43:01particularly unique about farmer and Life Sciences very much like
- 43:05for like a cross construction industry.
- 43:07But farmer and life science unit, depending on what the
- 43:09project is, it could be Rd, you know, research and development
- 43:13facility or kind of a cgmp Time. Manufacturing facility.
- 43:19Everybody controlled environments and complex kind of
- 43:23complex buildings and places really and sometimes achieving
- 43:27those those The sustainability targets can be more complicated
- 43:32than a than a say a new-build block of flats which is
- 43:36obviously less complex, you know.
- 43:37But but I wouldn't say there's anything particularly specific
- 43:41about the farmer and laughs insectary only that it's a much
- 43:45more complicated environment, so Implement highly serviced as
- 43:50well. So you know, it's a bit more
- 43:53complicated I suppose in summary in your view how can contracts
- 43:57help drive a culture on a Act, for example, and agile culture.
- 44:02Yeah. Yeah.
- 44:02I mean contrast can certainly help Drive project culture and I
- 44:06suppose it all comes back to to ensuring that you select the
- 44:10right procurement and contrast strategy that meets your own
- 44:13specific requirements. Really, you know what meeting
- 44:16the clients objectives and business case and user
- 44:20requirements brief are essential really.
- 44:24We've talked a lot about any see in this podcast and I think it's
- 44:28a fantastic sweetie of contracts, but it does have its
- 44:31crew. Systems which are mainly focused
- 44:33around those being heavily administrative, you know, with
- 44:37with inflexible kind of process-driven contractual
- 44:40requirements, I don't think there's any one size fits all
- 44:44type of protein in the construction playbook.
- 44:47For example, states, that the standard contract should be
- 44:50should be chosen and the following sweets and it
- 44:53specifically mentions any c 3 or 4 JC 2016 in and PPC 2000.
- 45:00So it gives you a range of Stood options contractual Arrangements
- 45:04can be can be usually added to in some kind of model contracts
- 45:08to help deal with projects and clients specific requirements or
- 45:11risk so which are not covered in the main contract term.
- 45:15So, if you've got a kind of actual working requirement,
- 45:17these can be easily inserted and dealt with through a contract
- 45:20Amendment wording. Or a said clause, for example,
- 45:23under any c, so you can easily Implement those if needed
- 45:27finally reflecting on the headline-grabbing vaccine
- 45:30rollout program from the Okay, government, which is broadly
- 45:34been deemed a huge success. Are there any lessons on the
- 45:37contracts and procurement side that we can take from that
- 45:39program and use going forwards? Yeah, I mean first of all kind
- 45:44of in answer to that I think you know I think I think the
- 45:47government has done a fantastic job in the vaccine rollout
- 45:50program, it's something that country can really be proud of
- 45:53over the last Connor, 12 months. I think, you know, when compared
- 45:56to other nations we've really excelled in what we've done on
- 46:00that program. So, you know how soft to
- 46:03everyone that was involved in it.
- 46:04Really, I personally wasn't involved in the government's
- 46:09vaccine rollout program, but I did did have some pre-contract
- 46:13involvement in the design and construction of the new build
- 46:16vaccine manufacturing and pandemic response facility.
- 46:19It was a really great project to work on but I think looking back
- 46:24you did need to be very thick-skinned the times whilst
- 46:26working on it, but I'm really proud of the role that I played
- 46:30or small part that I played in it.
- 46:31The frames, you know, it's an absolutely great project to be
- 46:34involved in one of the lessons that I've learned and took for
- 46:38my involvement in the project is ironically for this podcast is
- 46:42that there's definitely a time and a place not to be overly
- 46:45contractual and there's definitely a need to be a bit
- 46:48pragmatic, you know, particularly, you know, when
- 46:51working with such an important projects, you definitely need to
- 46:54make sure that you take the time to select the right procurement
- 46:57and contract strategy as part of a project initiation, you know,
- 47:00right at the beginning. Of a project if you don't get
- 47:03that right. You know, it could really the
- 47:05wheels could really come off on a project really special.
- 47:09What other Lessons Learned can we take from the last 18 months?
- 47:13Really? I think flexibility and
- 47:16innovation in Project delivery. And contrast strategy has proved
- 47:20to be really crucial, you know, in the response to kind of these
- 47:23exceptional kind of nature of the pandemic and the challenges
- 47:27that we faced over the last kind of year or 18 months for A
- 47:33rapidly evolving kind of projects and contract
- 47:37requirements, iets complex changing stakeholder groups, you
- 47:41know, fluid Financial control, will you know, maybe there isn't
- 47:45so much driver to on cost, you know, you just need to get it
- 47:49done. Just to kind of save lives,
- 47:51really high levels of kind of external public scrutiny, as
- 47:55well, with kind of made it necessary to kind of innovate
- 47:58and adapt through every aspect of the kind of contract strategy
- 48:02process, really? It's been achieved in a number
- 48:07of ways, doesn't it throughout kind of the project and program
- 48:11life cycle over the kind of lost 80 mums?
- 48:13You know, flexible procurements key design and construction
- 48:17Solutions need to be highly kind of strategic in your sourcing as
- 48:22well. You know, aimed at maximizing
- 48:24buying advantage in responding quickly to risks in supply
- 48:28chain, disruption, brexit certainly hasn't helped That
- 48:31regard, but, you know, we've got through it.
- 48:34I think moving forward, you know, stakeholders should
- 48:36continue to kind of employee flexible kind of innovative
- 48:40procurement solution approach really.
- 48:42And that will allow us to adjust.
- 48:44And, and flex to me, you know, growing needs going forward as
- 48:48part of the pandemic response or kind of, if needed in a
- 48:53telephone, a second or third wave now, but, you know, if we
- 48:56need to upscale vaccine manufacturer, we will need to be
- 48:58flexible. Really What my personal
- 49:02reflection of working through the pandemic really is, you
- 49:05know, I think we've learned a lot and enormous amount over the
- 49:08last 18 months. No against enormous odds.
- 49:11You know we could we can still deliver from a contractual
- 49:14perspective and you know what we have seen this really you know,
- 49:18impossible or unattainable in 2019, we've shown throughout
- 49:22kind of 2020 and through into 2021, you know, it's now
- 49:26possible. So, you know, just keep
- 49:29collaborating be flexible and apply.
- 49:31And if it's you've approached I think we can step up and meet
- 49:35any new challenge that 2021 and Beyond throws.
- 49:37It's just really. Thanks to Sarah and Richard for
- 49:44their contributions to this episode.
- 49:46I'd like to wrap up by summarizing some of the things
- 49:48that we've learned firstly contracts.
- 49:50A hugely important in a project context because they regulate
- 49:53the relationship between the parties and enable them to
- 49:55understand what work is being done to live it up cured.
- 49:59They set out in clear terms the scope timescales and processes
- 50:02for disputes and risk mitigation as Sara explained.
- 50:05And awareness of contract is important for project managers
- 50:08because if they don't deliver Services properly, it could be
- 50:11in breach of contract. And relationships and governance
- 50:13could begin to unravel. Richard meanwhile explained how
- 50:17contracts can help Drive project culture during you select the
- 50:20right procurement and strategy to meet your own specific
- 50:22requirements, along with the clients objectives and business
- 50:25case, it's also worth remembering.
- 50:27The contracts aren't just there to be dusted off when things go
- 50:30wrong because of the huge Investments of time and money
- 50:33that go into contracts. They should instead be viewed in
- 50:35a positive way, there is an opportunity for project
- 50:38professionals to stand up and make their voices heard.
- 50:41They need to see the contract, have a part in its negotiation
- 50:44or at least be consulted. They are the ones who have to
- 50:47deliver and take ultimate responsibility for the outcomes.
- 50:51We also heard about the role of contracts in sustainability.
- 50:53Now inserting specific Clauses, can Implement social value or
- 50:57corporate social responsibility aspirations through, for
- 50:59example, procurement of a construction project.
- 51:03And finally have the pandemic has taught us collaboration,
- 51:06flexibility and Innovation and project.
- 51:08Delivery and contract strategy are crucial and faced with
- 51:11rapidly evolving situations. With complex changing,
- 51:14stakeholder groups, check the episode description for links to
- 51:17Sarah's webinar series and Richards latest blogs for a p.m.
- 51:20Em. Get in touch with your feedback
- 51:22and suggestions at a p.m. podcast at think publishing
- 51:25.co.uk. This podcast has been brought to
- 51:28you by APM the charts body for the project profession.
- 51:32For more information on a p.m. visit, a p.m.
- 51:35Dot org.uk. Em.
- 51:21Get in touch with your feedback and suggestions at a p.m.
- 51:24podcast at think publishing .co.uk.
- 51:27This podcast has been brought to you by APM the charts body for
- 51:30the project profession. For more information on a p.m.
- 51:34visit, a p.m. Dot org.uk.