Latest / Contractor Business Builder Podcast / Stop Estimating Projects Like It’s 2005
Transcript
- 0:00The real reason you're not making the money you should,
- 0:03it's not the clients, it's not the economy, it is your
- 0:06estimating system and it's costing you big time.
- 0:09Stick with me because I'm about to walk you through a system
- 0:11that's helped GC's across the country turn bids into bank.
- 0:15Alright, so today we're going to be walking through the exact
- 0:19process to a complete estimating system that's going to increase
- 0:23your profits, help have a repeatable system that you can
- 0:26delegate, and I'm going to be going through what all the
- 0:29different components are. So there's three types of
- 0:31estimates and then there's a number of different ways to
- 0:34incorporate all of these into a streamlined system.
- 0:37So the three types of estimates are 1 is a ballpark estimate and
- 0:40we're diving into these in more detail about later.
- 0:43But essentially a ballpark is just a figure of scale of
- 0:46business projects going to cost 100,000 a million or 10 million,
- 0:50right? Like what you know, what's the,
- 0:51the ballpark that we're working with here.
- 0:53Then there's a rough budget. Rough budget is something where
- 0:56you've got line items you've working from just your standard
- 1:00based pricing, but it's thought quote it's it's you've done your
- 1:04takeoffs and it's a it's a pretty solid estimate, but it's
- 1:08not 100% drill down. And then finally we've got the
- 1:11detailed type of estimate that the, the detailed estimate is
- 1:14going to be 1 where you you've tendered the bids, you've gone
- 1:17through two suppliers that clients have gone through
- 1:19selections. It is very accurate and fined
- 1:22tuned estimate. Now if you're providing free
- 1:25estimates, you're going to want to know the difference between
- 1:27these three because if you are providing A detailed estimate
- 1:30for free, you are spending a lot of time and probably getting a
- 1:34lot of frustration going through all this work only to that have
- 1:37the client say no, it's too much or no, we're gonna go with
- 1:40someone else. So I'll be sharing with you the
- 1:41process of how we make sure that we use this 3 tiered estimating
- 1:45process to guide the client from one step to the next.
- 1:49Always be clear of where things are at with that client and help
- 1:52them kind of guide them into the sale and build that relationship
- 1:55over time. So that when it comes down to
- 1:57the representing the construction contract or
- 1:59proposal in front of them is really a no brainer option for
- 2:04them to move forward with you and your company.
- 2:06Now the whole estimating process, it really starts with
- 2:09the first consultation that you have with the client.
- 2:12This could be a consultation in their home.
- 2:14This is typically if you're doing large projects as a GC
- 2:17home builds, large remodels, whatever it may be, you're
- 2:20probably going to meet the client at their home so they can
- 2:22show you A, what their home is like right now and how they want
- 2:25to change it or B, go through the plans or the, the design of
- 2:31their their new project. So there is a whole process, the
- 2:34science behind this in order to get good information and set
- 2:38yourself up for success. So before getting to this home
- 2:41site meeting, you should have pre like qualifying questions so
- 2:45that you're not going to these home meetings and realizing
- 2:48later that this is not going to be a project that's going to
- 2:51work because the the client is not qualified.
- 2:54So just as a side note, they must be qualified before, you
- 2:58know, putting in the work. You always want to make sure
- 3:00that whatever stage of the process, there's a high chance
- 3:02that they're going to move forward with the next stage and
- 3:04and you guide them through that. So the first thing that you're
- 3:07going to do typically is a walk through.
- 3:09This could be a home walk through as far as you're going
- 3:12to walk around. They want their basement
- 3:13remodeled. They want their home remodeled.
- 3:16Let's see your house. Let's see what your plans are,
- 3:18whatever needs to get done. If you are a home builder,
- 3:22you're going to do like a walk through of their design plans if
- 3:25they have designs in place. If not, then you'll probably
- 3:28send them a questionnaire of what you know, what kind of
- 3:32house you looking for, two-story bungalow, whatever it may be,
- 3:35right? So you're going to do some sort
- 3:38of walk through and kind of clarify what they're looking for
- 3:42and how things are set up. Like I mentioned, you're going
- 3:45to have a discovery questionnaire.
- 3:46So a questionnaire is a really professional way to get a lot of
- 3:49information from a client. And you could go through this
- 3:51with them depending on the scale of the business or there's
- 3:55something that you could send them for them to do on their own
- 3:57time beforehand before the site meeting so that when you get to
- 4:01the meeting, you can kind of review it from them.
- 4:03OK, you're looking for 2500 square foot home and you, you
- 4:06want it facing this way and you want this many bedrooms and, and
- 4:09you know, you kind of walk through and just clarify and,
- 4:11and Give your opinion on everything from there.
- 4:14You're going to want to have some sort of like marketing
- 4:16material. It shouldn't be like we're
- 4:18sitting down to watch the family vacation pictures and you know,
- 4:23they're going to yawn their, their head off as they just
- 4:25don't care. But something quick, easy
- 4:28brochure or maybe a presentation on on your laptop or tablet or
- 4:32what have you, just a quick run through.
- 4:34This is our business. These are type of clients who
- 4:36work with, here's some of the completed projects that we've
- 4:38done before. This is, you know, our, our
- 4:40overall process of, of the estimating and the building and
- 4:44and whatever. Just to give them a big overview
- 4:46and kind of position your company as as professional as
- 4:49you've got to process as they're similar to all the other clients
- 4:53that you've worked with. And you work with clients like
- 4:55theirs and their location building this type of house or
- 4:58whatever it may be. So you want to be utilizing
- 5:01something like that. You always want to be
- 5:02positioning yourself as the expert in the conversation as
- 5:05well. So this isn't just menu type
- 5:07thing where you go to restaurants like I'll have the,
- 5:10you know, double pound beef burger or steak with side of
- 5:14potatoes and salad or whatever, right?
- 5:16You're not, this isn't like a list of OK, you want this check,
- 5:20you want this check. You need to be giving your
- 5:21advice of, well, you know, you're, you're looking for this
- 5:24size of the house. Maybe have you considered, you
- 5:27know, this or instead of having a basement suite, my granny
- 5:30suite, maybe 1 detached, you know, secondary dwelling unit or
- 5:34something like that, right? So Give your opinion if they're
- 5:37getting a kitchen remodel, but you know, what's your opinion as
- 5:40far as the best type of countertops or how to knock out
- 5:43a wall or or whatever, right? So you want to be positioning
- 5:47yourself as the expert in the conversation, not just taking
- 5:50down an order of things that they might want from here.
- 5:53This is where you will go into a ballpark budget.
- 5:56If you're not able to do this on the spot, you need to create,
- 6:00you should be able to create a some sort of spreadsheet very
- 6:02easily or use your project management software to create a,
- 6:05a very quick ballpark budget range for the client.
- 6:08So they really early on you can have that budget conversation
- 6:11with the qualifying questionnaire that you've had
- 6:14with the client. You should already have some
- 6:16sort of an indication of like if they are in the right, you know,
- 6:20area as far as like ballpark. So you know, what is their
- 6:25budget? Is it usually a range of
- 6:27whatever may be, so if they're looking for a new home and
- 6:30looking for one around 500 to 700,000 or they looking for one
- 6:33from like 1 to one and a half million.
- 6:35So in the qualifying questionnaire, you will have
- 6:38like these big kind of brackets and categories.
- 6:41And then the ballpark budget is something a little bit more
- 6:43refined, typically working off square foot square footage of
- 6:48pricing. So if you're looking to get a
- 6:50new home and you know that they want something a little bit
- 6:53higher end on the luxury, you could, you could let them know,
- 6:56hey, based off of the square footage you, you said and the
- 6:59location, you're probably looking at somewhere between 800
- 7:02to, to $1,000,000 or you know, 1.2 to $1.4 million for this,
- 7:07this new home build they're, they're looking at.
- 7:09So you should be able to get that out very early.
- 7:11And if they're like, wow, that's like way over our budget.
- 7:14We were looking for something around 600,000.
- 7:17Then it's kind of like back to the drawing board a little bit.
- 7:19OK, you said you want 2500 square feet.
- 7:22Are you comfortable with going down to maybe 2000 square feet
- 7:26or maybe having, you know, unfinished garage or basement
- 7:30or, or not doing, you know, so much like very minimal
- 7:32landscaping or, you know, cutting back on certain things
- 7:35now so you can still get the home that you want, but maybe
- 7:39have room for upgrading later on or or whatever, right.
- 7:42So getting that out of the way early on, of course, because as
- 7:46much as you want to keep this sale alive, you don't want to
- 7:49walk into and doing a bunch of estimating or designing for
- 7:53something that's just not feasible.
- 7:55And you know that you're not even in ballpark range.
- 7:58It's just a bad experience for you because you're going to be
- 8:00doing this work for them, bad experience for them because you
- 8:04don't want that huge sticker shock when you come back and,
- 8:07and, and they're not even close to, to what their budget is.
- 8:10So that that's how you use the ballpark budget.
- 8:12It's quick numbers back to the napkin kind of stuff.
- 8:14You can create a spreadsheet very easily to kind of highlight
- 8:18the the big points in a project or create like a ballpark
- 8:20template for whatever typical type of projects you do.
- 8:24From there for this process, you're going to collect this
- 8:27information from them. Your admin person or whoever is
- 8:31kind of in the back, back into your business.
- 8:33There is going to create a client folder for this this
- 8:37client and they're going to present a preconstruction
- 8:40service agreement and this home site visit.
- 8:43Your whole kind of purpose of it is to guide the client into a
- 8:48PCs agreement. So pre construction service
- 8:51agreement, you've kind of gone over what they they want, you've
- 8:55presented your company, you've you've put yourself as the
- 8:57expert. Now you have to let them know,
- 8:59OK, next step for us, we can do a more detailed budget for you.
- 9:04We can get you into a design with our designer.
- 9:06If you don't have a designer, you know, you can just partner
- 9:10with the designer or what have you.
- 9:11But you need to be looking, even if you're not like a design
- 9:13build company, you need to be partnered with design so that
- 9:17you can integrate that and solve that problem.
- 9:19The first problem for the client is they don't know how much it's
- 9:22going to cost. They don't know what you know
- 9:26how to do construction, they don't know anything about
- 9:28design. They're kind of lost.
- 9:30So you need to present the whole package of we're not just the
- 9:33builder to contact after you've got everything designed, we're
- 9:36going to help you with this design process.
- 9:39Part of that is getting PCs assigned.
- 9:41So that's the kind of first sale.
- 9:43If you want a guide on how to get a PC SA in place and how to
- 9:47present that, check out the links in the description below.
- 9:51In the description, I've got a link you can get our free
- 9:54planner. It's, it's a guide for CSA of
- 9:56how to put one together, how to structure it, how to create that
- 9:59offer and, and what it, what it will look like essentially.
- 10:04So go pick up that resource, click the link in the
- 10:06description below. All right, So what is in a PCs a
- 10:10package, you are going to include these typical things,
- 10:13architecture and interior design.
- 10:15So whether they have architectural, you know,
- 10:18wherever they're at in the design process.
- 10:20If they if they don't have anything in place, then you need
- 10:22to get them in touch with your architect, your interior
- 10:25designer, But you'll only do that after the design of PCs a,
- 10:29because you want to make sure that you are their builder of
- 10:31choice, that they're going with you for the PCs A, you know,
- 10:35preconstruction and everything like that.
- 10:36So architectural interior design is going to be included.
- 10:39They're going to include a budget, you're going to include
- 10:41scheduling, you're going to reserve them a spot in your
- 10:44pipeline. So you have to build this value
- 10:46to them where it's like, wow, this builder is super put
- 10:49together. This PC SA makes total sense and
- 10:53we need to do this right away. Create some urgency and you do
- 10:56that with the reserved pipeline spot.
- 10:59So with the with that it's like, you know if without this PSA, we
- 11:04can't get in your pipeline, we're scheduling projects out
- 11:07and we want to make sure that we can get to your project, you
- 11:09know on time and that we can flow everything very nicely with
- 11:13the scheduling. So with this CSA, we will
- 11:16reserve your spot and our production pipeline.
- 11:18You need to be able to sell this at the end of the day, and this
- 11:21is an easier sale than the full proposal.
- 11:23This may seem new to you if you haven't done this before and it
- 11:26may seem like, oh, that's gonna be hard to kind of get them to
- 11:29into an agreement when we're not even like ready to build yet or
- 11:33what have you. The truth is getting them into a
- 11:36CSA that is maybe a couple $1000 to maybe ten $20,000 sale,
- 11:42right? So it's a lot easier to sell
- 11:43them on. Hey, all you've got to be, you
- 11:46know, putting into this is we're going to do value add design.
- 11:50You're going to know all this stuff, how much it's going to
- 11:53cost. We're going to put you in touch
- 11:54with our expert designers who we've worked with many times and
- 11:58all we need from you is a retainer, you know, 2005, $1000,
- 12:03whatever it may be. So you're only selling maybe a
- 12:055000 or $10,000 product. Maybe the full PCs, if you're
- 12:09doing like a home build, maybe that's going to cost them 1520
- 12:12grand and you'll let them know that ahead of time.
- 12:14But you're only going to be charging for services rendered.
- 12:18Typically speaking, if you wanted to have more of a
- 12:20package, if you do like a certain level of remodels and
- 12:23it's like $2500, we give you plans, we give you, you know, we
- 12:26do the permits, whatever else, it's you know, you, you
- 12:30structure this how it makes sense for your business, but
- 12:32you're presenting this as a package for them to purchase.
- 12:35It's kind of low level as far as like they're not agreeing to go
- 12:39ahead with $800,000 of of home build.
- 12:42They're only agreeing to go ahead with like ten $20,000.
- 12:46And during this design process, if the feasibility is not
- 12:49correct or something out of line, they can walk away at any
- 12:51time. They're not held too long term
- 12:53contract. They're not, they're not held to
- 12:55doing the construction with you. You're simply going through this
- 12:58whole design process. So they have everything in place
- 13:00and then they can make a decision as far as which builder
- 13:03they want to go ahead with. Of course, after working with
- 13:06you, if you've done everything correctly and you've kind of
- 13:09built that budget for them, there should be no opposition
- 13:11for you to then just move into the construction contract and,
- 13:14and either builder of choice. So like I mentioned, you can do
- 13:17a retainer or flat fee, you know, cost plus pricing, however
- 13:20you want to structure that, right?
- 13:22So now we're going to get into the actual estimating.
- 13:24And can you see how like a lot of builders or remodelers, they
- 13:27skip kind of those first two steps of nailing down the
- 13:31process of like the walkthrough as well as the PCs.
- 13:35A without those two components, it makes all the rest of this,
- 13:39you're just a commodity at that point.
- 13:40If you're just providing a free budget or estimate for them and
- 13:44then hoping they go ahead the project, you are just in line
- 13:48with every other builder out there or anybody else that they
- 13:51can get ahold of and call for free estimate and they're going
- 13:53to be shopping around. They still may do that to some
- 13:55degree, but it's less likely. And you're also positioning
- 13:58yourself as an in demand builder with a process who solves a
- 14:02bigger problem than the other guys who are just doing the
- 14:04building part of it. You're also solving the design.
- 14:07Even though you are not a design company, You're going to pass it
- 14:10off to one of the your your partners in another company that
- 14:13does design, but you are structured that way to be able
- 14:16to help my client from, you know, the first step to the last
- 14:19step. So the next phase of the
- 14:22estimating process is the rough budgeting.
- 14:24Now, depending on how many leads come in and how your process
- 14:29works and how well you are kind of at the sale of the pre
- 14:32construction agreement, you may provide a free rough budget to
- 14:36them. And this is going to be worked
- 14:37from a template. It's going to have a lot of
- 14:40standard kind of base level pricing that you can offer as a
- 14:43free budget to them or or you could work it into your yes.
- 14:47It's totally up to you how you structure that.
- 14:50If you are providing the rough budget for three, you've kind of
- 14:52go above and beyond. Again, if you're trying to
- 14:54compete with other contractors or things like that, then that
- 14:58may be an option by kind of giving more incentive up front
- 15:02to to continue to work with you or providing more value from the
- 15:06clients perspective before you're asking for that PCs A now
- 15:10for rough budgeting, you're going to need a project
- 15:12management and take off software.
- 15:13The three that I like to use is job tread build, exact contract
- 15:19form and those are my top 3/4 residential general contractors.
- 15:24If you are a commercial contractor, then things like
- 15:27Procore is the big, big name and the popular one out there.
- 15:30There are other ones as well. Jeff Build I believe is another
- 15:33good one and but you'll need a good solid project management
- 15:38software that has the takeoff software either built into it or
- 15:41a separate software for takeoff software.
- 15:44There is Bluebeam was probably my top pick and then there's
- 15:47also Square, which is pretty straightforward plan.
- 15:50Swift, another great one plans looked really solid as well.
- 15:53So you need to get your proper software stack in place.
- 15:56You want to then set up a big estimating template.
- 16:00So your template should be pretty much as big as you can
- 16:03make it because it's a lot easier deleting things out of an
- 16:05estimate than it is to to add them in.
- 16:08So if you are a home builder, you want to have a, a pretty
- 16:11robust home build estimate and then you can just take things
- 16:14out like, you know, if they're not having a swimming pool or if
- 16:17they're not having a detached garage or, or whatever, you can
- 16:20just delete those those sections out of there fairly easily.
- 16:23Of course, you could have different, you know, like have a
- 16:26really big template and then have like maybe some paired down
- 16:29templates for like more basic type builder and stuff like
- 16:32that. But at the very least I have one
- 16:34big good estimating template to work from.
- 16:37And then ideally have additional ones as you build all your
- 16:41systems cost codes and price database.
- 16:43This is sort of the next step to get cost codes in place.
- 16:46So you can do job costing very important as well as just keep
- 16:49things categorized and, and, and more organized.
- 16:52The price database, there's a lot of resources and a lot of
- 16:56these project management softwares have that like live
- 16:59pricing built in either from suppliers or from like an Rs
- 17:02means or one bill, I believe is is another one through some of
- 17:06these other databases. So those are good for materials
- 17:10typically, but not so good necessarily for labour costing
- 17:14and and specifics like pricing that for you and your business
- 17:18in your area. So you're going to want to build
- 17:19out your your database and you may be really experienced and
- 17:23kind of know the pricing and know the whatever codes and
- 17:25stuff like this. But the reason you want to build
- 17:27all this out in a systemized way is because the whole purpose of
- 17:31this is that you're going to pass this off to somebody else
- 17:33eventually in your business. If you're still doing all the
- 17:35estimating, you're going to want to hire an estimator or have a
- 17:38project manager who can take estimating system and run with
- 17:40it and, and get this off your plate, you know, as soon as
- 17:44possible and, and focus on more high level stuff besides just
- 17:48estimating, which is probably, you know, fresh air for for you.
- 17:51But that's why you want to take the time to make this estimating
- 17:55process really good. For rough budgeting, you're just
- 17:57going to use allowances. So $10 per square foot for tile
- 18:01or 5 or 15 or whatever 8. But with the rough budgeting,
- 18:05you want to keep the pricing very minimal because this first
- 18:09kind of budget you're going to provide for the clients, you've
- 18:12done a ballpark, but that's really just a range to sort of
- 18:14see if they're in ballpark. The rough budget, you wanna keep
- 18:18it low because you don't want to scare off the client.
- 18:20You don't wanna come in super high, especially if they're
- 18:22gonna get competing bids where it's like, well, your, you said
- 18:261.2 and this other contractor saying they can do it for
- 18:291,000,000. So we're kind of leading towards
- 18:31them and we're not sure if we can move forward.
- 18:33If if you're saying it's 1.2, even knowing very well that that
- 18:37other builder that's quoting 1,000,000 is probably out to
- 18:40lunch and it's probably gonna end up costing 1.2 or more.
- 18:43And the end, even though you're more correct, you still want to,
- 18:47you know, you want to be reasonable, but you want to let
- 18:49them know like this is kind of base materials.
- 18:51This is what we can build this house for.
- 18:54You know, we can come in at 1.1 million or million, but this is
- 18:58sort of your baseline. If if you have, you know, want
- 19:01more high end finishes or you make changes to this or you
- 19:05know, we want more expensive kind of fixtures and stuff like
- 19:08that, this price will can potentially go up overtime as we
- 19:12finalize the design and the selections, we want to start
- 19:15kind of lower. And then you can always add to
- 19:17that price. If they're like, you know, we're
- 19:19OK with 1,000,000 and then they can see how their decisions are
- 19:22driving that price. You will probably end up at 1.2
- 19:25by the time you get down to the detailed design, but at least
- 19:28the client understands that it's their decisions that have
- 19:31influenced the price. And if they want to lower price,
- 19:33they have to, you know, accommodate with lower
- 19:37selections or different designer or what have you.
- 19:39So you and you want to be very clear in your estimate.
- 19:42This isn't allowance. One thing that a lot of builders
- 19:46and especially newer ones forget is you want to make sure you
- 19:49have project management time in your estimate and it should be
- 19:53very clear. I like to have it right in there
- 19:56so the client can see it. Some people are like, I don't
- 19:58want to have management time because other builders don't and
- 20:00their clients going to wonder why they're getting charged for
- 20:03this. Your markup or your margin,
- 20:06however you want to call it there, there is a difference.
- 20:08But that markup that you put on top of everything should not
- 20:11cover the project management, even if you don't have a project
- 20:14manager, because. One day, hopefully soon, you're
- 20:17going to hire a project manager and you're going to need to pay
- 20:19them whatever it is for to run the project.
- 20:21You know, that could be 20304050 more $1000 to manage a project
- 20:27for you. You need to have that in your
- 20:30estimate. And the way to do this is how
- 20:31many hours per day does it take you to manage the project?
- 20:33Talking with the client, calling the trades, doing site meetings,
- 20:37meeting inspectors, doing your own quality checks, all this
- 20:40kind of stuff, right? So is that a one hour, 2 hours,
- 20:433 hours a day to manage a project?
- 20:45Make sure you build that into your estimate and then your
- 20:49margins as far as your overhead. So things like your your
- 20:54overhead should be built into your project too.
- 20:56Because if your markup is 15% and you have a 12% overhead for
- 21:01your company, you are going to be barely, you're going to be
- 21:05losing money essentially because the overhead is a margin,
- 21:10whereas the markup is on top of the price and there there's a
- 21:12difference. So if you're, if you have let's
- 21:15say you're running at 15% overhead, that is considerable
- 21:19to a 50% margin. If you mark up your estimate
- 21:2215%, your margin is more like I believe 12% or something like
- 21:27that. So there, there's a difference
- 21:29between those numbers and you, you probably need to be in the
- 21:3220% markup range to hit a margin of 15%.
- 21:36So really you should be marking up like 25% because you need
- 21:39some contingency in there as well as some profit at the end
- 21:42of the day. So make sure you're you're
- 21:44accounting for that and you've got some contingency or
- 21:46miscellaneous. I like to put a little bit of
- 21:47miscellaneous neighbor, miscellaneous materials, things
- 21:50like that, because as you know, there's always things that go
- 21:53unaccounted for, little things that pop up in in a build and
- 21:58you don't want to be out of out of pocket for that stuff.
- 22:01Also, you want to be able to smooth it out if maybe something
- 22:05comes up. That's a little bit of a Gray
- 22:06area that technically you could do a change order for the
- 22:08client, but it's only like 1000 bucks a year or a couple 100
- 22:11bucks here. And it's like you've got that
- 22:13missed budget to take care of it without, you know, doing a whole
- 22:17bunch of different change orders for the client.
- 22:18So after you completed that, the rough budget and provide that to
- 22:21the client, now they have a good idea and you've got past any
- 22:24sticker shock, any, you know, changes or things they may be
- 22:27asking for, you'll now move into the detailed budgeting.
- 22:30By the time you get to the detailed budgeting, this is
- 22:32where you're definitely need a pre construction service
- 22:34agreement in place so that you're getting paid for your
- 22:36time being put it in. It'll take you hours to go
- 22:39through selections, changes, whatever else that may go into
- 22:44the detailed budgeting process. So first thing will be tendering
- 22:48bid requests. So you're going to be sending
- 22:49out the request to your subcontractors and they should
- 22:54be templated. Should either template or
- 22:56documents or using your project management software have
- 22:58templated wording that gets sent out so that every subtrade is
- 23:03knowing is getting the same information.
- 23:05But also that you have standards of practice so that when you
- 23:09send it to maybe somebody new, they know this is the level of
- 23:12quality that you want. This is the way that they should
- 23:15be doing their project. Are they including materials or
- 23:17not including the materials, All those kind of things.
- 23:20So everyone is giving you bids on the same information and
- 23:25you're not getting all this, you know, stuff all over the place.
- 23:28As as far as selecting bids with subcontractors, if you get the
- 23:33standard sort of like 3 bids, you definitely want to be going
- 23:38kind of mid range. The reason you don't want to go
- 23:40with really low bids is that if that contractor for some reason
- 23:44can't do the project or something happens with that
- 23:47contractor, you've now submitted a price to your client that
- 23:51includes that low bid. But now you need to maybe hire
- 23:54someone else. It's gonna cost more and now all
- 23:56your margins are gone essentially.
- 23:58Or possibly you're losing money depending on how much of AA
- 24:01range of pricing that there is. So you typically want to choose
- 24:07somewhere around the middle bit or at least not have the bottom
- 24:10pricing. Even if you plan to go with the,
- 24:13the cheaper, you know, bid that you get, you want to make sure
- 24:16that you've you've added additional markup or on top of
- 24:20that so that if you do go with a different contractor, you have
- 24:23that room and not just having to go with that, that, you know,
- 24:26bottom price, then you're going to get supplier pricing.
- 24:29This is going to be based off selection.
- 24:32So the clients are going to go through the design process.
- 24:34They're going to say you know we want this kind of siding, we
- 24:37want this type of decking, we want this type of flooring,
- 24:40whatever it is, and you're going to need to get pricing from your
- 24:43supplier so you can build that into your estimate and get very
- 24:45specific with the costs of of the project selections as well.
- 24:50This is typically going to go through the designer by you will
- 24:54probably have some involvement with selections from pricing
- 24:59standpoint as well as as well as like reaching out to suppliers.
- 25:02Like like I mentioned earlier, upgrades are always great.
- 25:04So I like to have sort of a checklist that you provide to
- 25:08clients of upgrades that they make.
- 25:09Consider this could be things like soundproofing walls, maybe
- 25:13in floor heating, astronomical timers where lighting outside,
- 25:17maybe it's like landscape stuff. So whatever may be have a list
- 25:21of things because this this can greatly increase the the
- 25:25satisfaction or the experience of the completed project when
- 25:29clients do get these upgrades. But it's something that they may
- 25:32not have thought about or they may not, you know, initially
- 25:35want, because it's like they're not sure about pricing, but come
- 25:38later on when they're, you know, getting this and that and this,
- 25:40they may want to upgrade stuff in their project, which is good
- 25:42for everybody. Site testing and permitting.
- 25:44So during this detailed budgeting stage, you, the design
- 25:48should be at a place where you can send it out for permitting.
- 25:51And then also you want to do any site testing.
- 25:53So if it's, you know, like if you need to do any testing for
- 25:56geological or maybe asbestos or whatever may be, you want to get
- 26:01that done during this phase so that you know what it's going to
- 26:04cost if, if there are issues that come up.
- 26:06And then also, you always want to double check your accuracy.
- 26:09So ideally you're going to have somebody else look at your
- 26:13budget for you. So you'll have gone through the
- 26:15estimate. You know everything.
- 26:16It's always good to get a second set of eyes.
- 26:18This could be a project manager, could be senior person or
- 26:21estimator, your company or whatever it may be.
- 26:24Get a second set of eyes on the estimate because there's
- 26:27probably things that they forgot or you forgot or whoever put it
- 26:30together. It's very common that you just
- 26:33don't see it because you, you're in the, you're in the weeds, if
- 26:35you will. Someone new and fresh would be
- 26:37like, Hey, we should word this differently.
- 26:38Are you sure about this? That number looks out of place
- 26:41and what have you to double check the accuracy.
- 26:43Now we're going to move on to the proposal.
- 26:45So you've, you've done all the, the legwork, the design is done,
- 26:49the final detailed budget is, is done.
- 26:52Now you need to be able to propose and sell the actual
- 26:55construction contract and move it into the, the real, you know,
- 26:59nuts and bolts of, of what, what we do as builders to, to
- 27:02actually build the project. So some things you want to keep
- 27:05in mind for your proposal and the process is you definitely
- 27:08want to have some sort of cover letter that showcases your
- 27:11company shouldn't just be, you know, a list of of your your
- 27:15estimate that you send to the client.
- 27:16Have something more for the cover letter letter.
- 27:19As far as you know, a little bit of marketing stuff, a little bit
- 27:23of, you know, thanks for asking us to bid on the project.
- 27:26This is the final, you know, budget that we've come up with,
- 27:29whatever it may be, but it should be more give it that
- 27:32Polish professional look. You always want to be doing the
- 27:34proposal in a live meeting. Do not just e-mail an estimate
- 27:38over to a client and then hopefully hear back from them
- 27:41because that's a good way for them to ghost you or for them
- 27:43just to take forever to get back to you, right?
- 27:46As well As for them to say like, oh, we're not going to move
- 27:49ahead of it. We're going to go with someone
- 27:50else or this is a bad time or whatever, right?
- 27:53Getting an e-mail like that, you have no idea what's happening or
- 27:56why they chose not to move forward with the project,
- 27:58typically speaking. So live meeting you're much
- 28:01better off to be able to walk through your estimate of like
- 28:04these are all the line items. This is the cost of this and
- 28:07that. If you know, if you have
- 28:08detailed costing in there and you can get their live feedback
- 28:12of, you know, if they say it's all this is, you know, too high
- 28:15of a price or we're not sure about this or that, you can walk
- 28:19through it, you can talk with them, you can get, get some
- 28:22feedback from them on the estimate and, and which way
- 28:25they're going. And you're in a much better
- 28:27position to then sell the construction contract and move
- 28:29forward with them. If you can do it in a live
- 28:31meeting. Multiline pricing.
- 28:33I know there's this boat, two sides of the coin as far as like
- 28:36we just give one final price. Your project is going to cost,
- 28:40you know, 2200 thousand dollars or $500,000.
- 28:44Or do we do line item by line item with, you know, all the
- 28:47costs in there? It's kind of up to you.
- 28:50For me, I, I prefer more open book style of pricing and I find
- 28:54that the customer is going to appreciate that more and have
- 28:57more trust. Of course, this does open the
- 29:00book for them to kind of dive into things and, and start
- 29:03asking about specific pricing. But if you've done your due
- 29:05diligence, you have like present yourself in a professional
- 29:08manner, I find you'll attract clients and you'll be able to
- 29:11work with clients who are less concerned about individual small
- 29:14pricing and more about the project and the experience.
- 29:17And yeah, they may still have pricing concerns, but they're
- 29:20not going to want to dive into every little thing, right?
- 29:22But it does build a lot of trust when you can at least have the
- 29:25big sections of your estimate priced out individually instead
- 29:29of just one solid price at the bottom.
- 29:32You always want to include the plans and the schedules with
- 29:34your budget. So you shouldn't just have an
- 29:37estimate by itself and send that off or just show that, right?
- 29:40You want to have the plans and the schedule so that they
- 29:43realize that this is a full project.
- 29:45This isn't just a numbers thing. There's a schedule, there's
- 29:48there's plans to design. It all comes together and you as
- 29:51the builder are there and the one stop shop facilitator that
- 29:55can see the the entire picture and help guide them to that
- 29:58final product of the beautiful home or office space or remodel,
- 30:03whatever is is that you know they're looking to get done on
- 30:07your proposal. Make sure you include your
- 30:08qualifications and any warranty. So are, you know, your builders
- 30:12license if you're part of any Chambers of Commerce, if you've
- 30:15won any awards or whatever it may be warranty.
- 30:19Not all the nitty gritty, but like you have a one year
- 30:21warranty on workmanship, five years on on foundation or
- 30:25roofing or or whatever, right? So just a couple of line items
- 30:29that you include a warranty. This is how long.
- 30:31These are the kind of the big individual things that that do
- 30:34get a warranty to give them more trust and and just make the
- 30:39decision easier for them. And then finally, you're going
- 30:41to want to have inclusions and exclusions.
- 30:44So what is included is permanent costs included is whatever it
- 30:49may be. You want to be very clear, like
- 30:51you know, all materials, what is not a what, what is not included
- 30:55in this, What is excluded, You know, that could be city
- 30:58upgrades if they need new sewer or water or electrical, you
- 31:02know, any kind of stuff from the city, whatever it may be.
- 31:05We've got, of course, all this stuff templated and built out.
- 31:09If you're interested in in getting like this high level
- 31:13systems and everything all documented and build out for
- 31:16you, reach out to us is what we do.
- 31:18We help contractors get really polished, really refined with
- 31:21all their systems that have a great process that's high
- 31:24converting and brings in the right type of clients.
- 31:27But this is what you're going to want to include on your
- 31:30proposal. All right, So at this stage,
- 31:32you've essentially moved from getting a new lead to the whole
- 31:36process of going through the budgeting from rough to to
- 31:41detail to PCs agreement to moving them into construction.
- 31:44Now I'm going to be sharing with you big mistakes you want to
- 31:46void to make sure that you're not getting hung up or losing
- 31:50money on a project as you go through that whole process that
- 31:53I just showed you. So one thing which I mentioned
- 31:56kind of earlier is overestimating the rough budget.
- 31:58So you don't wanna go over estimating on a rough budget and
- 32:01you will tell the client this is a rough budget.
- 32:03This is our best kind of scenario at this point as we go
- 32:07through this elections, the design, the, you know, getting
- 32:11suppliers quotes and getting quotes from our sub trades and
- 32:13everything. The, the budget will fluctuate
- 32:17up and down and could, you know, change 510% possibly,
- 32:21potentially even more depending on on how things go and, and
- 32:24choices you make and all this kind of stuff.
- 32:26So we want to make sure that that initial rough budget is
- 32:29fairly low, very basic, and you want to communicate that as far
- 32:32as expectations go, like this is our basic budget.
- 32:35This is the price as of now. It'll, you know, can fluctuate
- 32:38up and down, but overtime, typically as we get more prices,
- 32:42this, this could potentially go up.
- 32:44So we want to do that because you can scare people off very
- 32:46easily and then it puts you back in that competition of like
- 32:50pricing, pricing wars instead of being, you know, getting the CSA
- 32:53and being their preferred builder to design and and budget
- 32:56their project with waiting to system, systemize and delegate.
- 33:01So this is a huge mistake. You need to build a system
- 33:04around this right now, today, tomorrow, this week, as soon as
- 33:08possible. Again, if you need help with it,
- 33:09reach out to us. You need to build a system so
- 33:11you can delegate it because you will hit the ceiling.
- 33:14You can't manage projects, do estimating, do marketing,
- 33:18budgeting, talking with clients, checking financials, all this
- 33:21stuff. As a business owner, you will
- 33:23never grow. Maybe you can build 123 homes a
- 33:26year or do a few larger projects or what have you.
- 33:28But you need to build a system around this first, to help
- 33:31yourself to to be able to do your job better if if you're
- 33:34still feeling all these roles in your business.
- 33:37But second, so you think you can start to delegate it.
- 33:39And the sooner you get a system in place, the sooner you can
- 33:42start to improve it to a point where you can easily hand this
- 33:44off to somebody else and delegate it to implement on your
- 33:47behalf. Winging labour, another quick
- 33:49way to lose money. You may be really good at like
- 33:53knowing like, OK, this kitchen remodel is gonna take, you know,
- 33:56the carpenters, whatever, 20 hours to install cabinets or 10
- 34:01hours to, to, to whatever. Do the, the demo or whatever may
- 34:06be. Really think it through because
- 34:07it's very easy to wing labour and then often go over because
- 34:11you forgot something or didn't think it through.
- 34:13I like to do a mental picture in my head of like, OK, guys got to
- 34:16show up with site. They've got to unpack all their
- 34:19stuff. They've got to, you know, figure
- 34:20out the plans, they've got to start getting into stuff.
- 34:23They gotta put up their their site protection, whatever it may
- 34:26be, right? So you're going to lose a few
- 34:28hours there. Then it's like they've got to,
- 34:29you know, pull out the cabinets, take the packaging off, set it
- 34:33up, check the walls, level, whatever, right.
- 34:35So just kind of walk through and figure out how, how long is this
- 34:39going to take? And if you need to ask someone
- 34:42who's there and doing the job. If you've got carpenters or
- 34:45foreman or project manager, they may be better suited to know how
- 34:49long something's gonna take because they're not as invested
- 34:52in the business and they don't have your mindset of like, get
- 34:56shit done as soon as and quick as possible.
- 34:58And how you maybe did it 10 years ago or 20 years ago when
- 35:01when guys could fly through it. It's a different world now.
- 35:04You have different employees. Stuff happens at a different
- 35:07pace, right? So getting someone who's closer
- 35:09to the front lines to just get a double check on, on labour time
- 35:13or cost may be very helpful and will keep you from winging it
- 35:17and losing money. So no small project pricing.
- 35:20You should have kind of tiers of projects and a small project to
- 35:24you is, you know, could vary by the company.
- 35:27It could be 20,000, it could be 200,000, it could be 2 million,
- 35:30whatever that small project kind of folded, you need to be
- 35:34charging more for the project based off that threshold.
- 35:38So if you are a home builder and your typical home build is
- 35:41$1,000,000, if you get a project or build that's less than let's
- 35:45say $700,000, maybe that's a small project and you need to
- 35:49increase your, your markup by potentially, you know, 5% or or
- 35:54whatever it may be. Because small projects still
- 35:57have a certain amount of overhead and just management no
- 36:00matter what size of the project. And you also want to be more
- 36:04competitive on the larger typical projects than you do on
- 36:07the smaller projects just to kind of help you stay clear of
- 36:13having being that small project builder, builder take it on too
- 36:16many small projects, being busy with that and not being able to
- 36:19have room for larger projects that that come along.
- 36:22So definitely adjust your markup pricing based off the size of
- 36:26the project. If it's a really big project
- 36:28they really want to get, maybe you can thin your margins a
- 36:30little bit, but don't go overboard.
- 36:32You should have kind of your base pricing that you're
- 36:34profitable at. And then if you have like a
- 36:36small project threshold, anything below that at an extra
- 36:395%, we didn't percent to the markup.
- 36:42No secondary review. So I mentioned that as far as
- 36:44double checking it, you should be double checking yourself, but
- 36:47also make sure you have someone else in the company or that you
- 36:51trust to double check and review the estimate together.
- 36:54Quick 10 minutes review is all you really need for someone else
- 36:57just to get a second set of eyes on it.
- 36:58Make sure nothing's forgot or your pricing is an outlook.
- 37:01No risk assessment, very poor. I'm a, I'm a culprit of this.
- 37:05I, I like, I'm an optimist. I like to think that things will
- 37:08go well and everything's great. But when in reality, shit comes
- 37:11up and then things hit the fan and you definitely need to be
- 37:15thinking forward of what are the risks on this project?
- 37:19You know, is it the clients? Is it the location?
- 37:22Is it that maybe we haven't done this type of build before?
- 37:25Maybe we haven't used this material before?
- 37:28Whatever it could be, right? So if if you identify a risks
- 37:31like excavation is always risky, you never know what you're going
- 37:34to find under under the soil and things like that.
- 37:37So what are the big risks here? And have you mitigated that in
- 37:40your estimate If something comes up either with an exclusion
- 37:44signifying, I like to put it right in the line item allowance
- 37:48or risk, like just in full capitals risk, whatever it may
- 37:54be. And you don't want to overuse
- 37:56this where you scare off the client.
- 37:57But at the same time, if you can identify risks in the, in the
- 38:00client's project and no other builder, if they aren't getting
- 38:03competing bids has brought up that risk, You look like the
- 38:07expert and the you, they'll feel more comfortable going ahead
- 38:10with you because you've identified it and you brought it
- 38:12to their attention that, hey, professional opinion, this is a
- 38:15potential risk on your project. And you know, instead of having
- 38:18that conversation later when it comes up, we've identified it
- 38:21now. And then finally, outdated
- 38:23pricing, especially on larger projects or home builds, if
- 38:27you've got a lengthy process of design and then planning and
- 38:31permitting, and they may not be able to start right away.
- 38:34The pricing that you give them now will be different from a
- 38:39year from now when maybe they're ready to move ahead with the
- 38:42project or six months or what have you.
- 38:44And if you're basing your pricing on the project you last
- 38:46year and now you're, you're, you're, you're projecting ahead,
- 38:49the pricing, you know, in six months or one year from now when
- 38:52they start to build, that's going to be vastly different.
- 38:56And you could be out 1015% depending on fluctuations and
- 38:59price. So you have to be able to be
- 39:01aware of that and not be a using outdated pricing, but also be
- 39:06thinking of the future of like is there potential in the
- 39:09pricing could rise? What is typical?
- 39:12How much do I expected to rise because I can quickly eat into
- 39:14your profits if you are pricing on outdated pricing.
- 39:19So now you've got a complete estimating system.
- 39:21As mentioned before, check out the links in the description
- 39:24below. There is a free piece PCs a
- 39:28preconstruction agreement guide to help you build out a
- 39:31preconstruction agreement offer for your company, as well as
- 39:34some free estimating templates to do with the the home
- 39:37walkthroughs and and just building out your your line item
- 39:40estimating templates. So tons of value there.
- 39:42Go click through the links and get those for yourself.
- 39:44I'll see you on the next video.