- 0:04SPEAKER_01: Hi, I'm Santi Ruiz, and you're listening to Statecraft.
- 0:07SPEAKER_01: Specifically,
- 0:09you're listening to me interview Stephanie Pollock in what's
- 0:12one of my favorite
- 0:12SPEAKER_01: conversations I've ever recorded on Statecraft.
- 0:15SPEAKER_01: And I'll tell you why.
- 0:17SPEAKER_01: For one, I had a blast.
- 0:18SPEAKER_01: Stephanie's funny, and she's got a killer Boston accent.
- 0:21SPEAKER_01: For another,
- 0:22SPEAKER_01: she explains some of the ideas I care about incredibly well,
- 0:25SPEAKER_01: like how well-intentioned regulations turn bad,
- 0:28SPEAKER_01: how political pressures make simple things hard to pull off,
- 0:32SPEAKER_01: why building in the real world is so hard,
- 0:34SPEAKER_01: She taught me a huge amount about building transit in this conversation,
- 0:38SPEAKER_01: and she's a great storyteller.
- 0:40SPEAKER_01: Some context.
- 0:41Stephanie was the deputy administrator of the Federal Highway
- 0:44Administration for
- 0:45SPEAKER_01: the first half of the Biden admin.
- 0:47Before that,
- 0:48she served as the secretary of the Massachusetts Department of Transportation.
- 0:52She was secretary when she had to step in and salvage the Green
- 0:55Line Extension,
- 0:56SPEAKER_01: a Boston transit project that went horribly wrong.
- 0:59SPEAKER_01: And a while before that,
- 1:00SPEAKER_01: before she was in the business of building things,
- 1:03she was an environmental activist who sued the Massachusetts
- 1:06Department of
- 1:06SPEAKER_01: Transportation for building things.
- 1:08SPEAKER_01: We'll get into that evolution in her career here.
- 1:11This conversation is one of a series of conversations over the
- 1:13coming months about transit,
- 1:15SPEAKER_01: why it's gotten so hard to build,
- 1:17SPEAKER_01: who fights over it,
- 1:18SPEAKER_01: and what it takes to build something people love and use.
- 1:22SPEAKER_01: As a reminder,
- 1:23the transcript for this full conversation and for many others
- 1:27is available at www.statecraft.pub.
- 1:31SPEAKER_01: That's statecraft.pub.
- 1:34SPEAKER_01: I'll shut up now and let Stephanie talk.
- 1:36SPEAKER_01: All right.
- 1:36SPEAKER_01: Stephanie Pollack, thank you for joining.
- 1:38SPEAKER_01: Let me start with this.
- 1:39SPEAKER_01: What do most people not understand about federal transit?
- 1:44I think most people don't understand that the way transit
- 1:49agencies get money from
- 1:50SPEAKER_00: the feds is very different than the way highways get money from the fed.
- 1:55And that fundamentally changes the ability of transit agencies
- 1:58when they want to
- 1:59SPEAKER_00: deliver a megaproject.
- 2:00SPEAKER_00: Highways get money that's allocated year after year after year.
- 2:04SPEAKER_00: They know years in advance how much money so they can plan.
- 2:07And most state transportation or highway departments are in the
- 2:10building things business.
- 2:11SPEAKER_00: Most transit agencies are in the running transit business.
- 2:14SPEAKER_00: And then every so often when they want to do a big project,
- 2:17they actually have to go through a really laborious process
- 2:20that's run by the
- 2:21SPEAKER_00: Federal Transit Administration and basically get a grant.
- 2:25Can you explain how much of what transit agencies do is
- 2:28maintenance versus the
- 2:30SPEAKER_01: amount of maintenance that state highway work involves?
- 2:33SPEAKER_00: Yeah, it's a great question.
- 2:35SPEAKER_00: State highways are probably 90-10 building things and operating things,
- 2:40and transit agencies are probably 90-10 operating things and
- 2:44maintaining them and
- 2:45SPEAKER_00: making sure that they pull off the commute every day,
- 2:47SPEAKER_00: and 10% doing real capital work.
- 2:50Because if you think about the way most people would judge
- 2:53their local transit agency,
- 2:55SPEAKER_00: it's based on the morning commute or the afternoon commute.
- 2:57SPEAKER_00: Like how good did it work?
- 2:59SPEAKER_00: Did the train show up?
- 3:00SPEAKER_00: Did it break down?
- 3:02SPEAKER_00: Did it take the time it usually takes or doesn't?
- 3:04So transit agencies are their DNA as being operators and
- 3:08highway agencies,
- 3:09SPEAKER_00: their DNA as being constructors.
- 3:11SPEAKER_01: And is that mostly on the highway side,
- 3:14just down to the fact that it doesn't take that much
- 3:16maintenance to keep a highway running?
- 3:18SPEAKER_01: Is that kind of a naive or unformed way of thinking about it?
- 3:20SPEAKER_00: No, it's actually probably how a lot of highway people think of it.
- 3:24SPEAKER_00: It's not that it doesn't take work to maintain a highway, right?
- 3:26SPEAKER_00: There's potholes to be filled and guardrails to be repaired.
- 3:29And if you're in Massachusetts and northern states,
- 3:32there's snow to be plowed.
- 3:34SPEAKER_00: But I don't think it's how people think about it.
- 3:36SPEAKER_00: Like if you think about your drive,
- 3:38SPEAKER_00: you're not necessarily saying, oh, traffic was terrible today.
- 3:41SPEAKER_00: That's the state transportation department's fault.
- 3:43But if you think about it,
- 3:44that transit commute,
- 3:45it's like,
- 3:46oh my God,
- 3:46it was awful today.
- 3:48SPEAKER_00: That is the transit agency's fault.
- 3:50So there is operations and the truth is highway folks could
- 3:54learn a lot from
- 3:55SPEAKER_00: transit folks about operations,
- 3:57SPEAKER_00: right?
- 3:58SPEAKER_00: But it's not mostly operations.
- 3:59SPEAKER_00: It's far and away building and also
- 4:01The history of the federal government and their relationship to
- 4:05state highway
- 4:06agencies is they enlisted state highway agencies in the 50s and
- 4:1060s and 70s to
- 4:11SPEAKER_00: build out the interstate highway system,
- 4:13SPEAKER_00: right?
- 4:14SPEAKER_00: People think of the interstate system as federal,
- 4:17SPEAKER_00: and it is because it's federally funded,
- 4:19SPEAKER_00: but it's actually built and owned by the states.
- 4:23So they were born to build,
- 4:26whereas transit agencies were born to provide service.
- 4:31Will you treat me like I'm five here and basically explain how
- 4:35do state highway
- 4:36SPEAKER_01: agencies get money from the federal government?
- 4:38SPEAKER_01: And then how do state and local transit agencies get money?
- 4:41Just walk me through the actual mechanics of I've got something
- 4:44I want to build.
- 4:45SPEAKER_01: I asked the feds for money.
- 4:46SPEAKER_01: How does that work?
- 4:47SPEAKER_00: So basically, state highway agencies don't ask for money.
- 4:51SPEAKER_00: They just get it.
- 4:53SPEAKER_00: It's called formula funding or apportionment.
- 4:56But what it basically means is every five or six years,
- 4:59Congress passes a big bill.
- 5:01SPEAKER_00: They did it last in 2021.
- 5:04And they lay out for five or six years into the future how much
- 5:07money each state is
- 5:08SPEAKER_00: going to get,
- 5:09SPEAKER_00: mostly for roads and bridges.
- 5:11And then you know you have that money,
- 5:13which means if you're trying to plan...
- 5:16SPEAKER_00: Right.
- 5:16SPEAKER_00: A series of big projects to fix roads and bridges.
- 5:20SPEAKER_00: You don't just know what you're getting this year.
- 5:23You know what you're getting next year and the year after and
- 5:24the year after.
- 5:25And you know that since the 1970s,
- 5:28every five or six years,
- 5:30Congress re-ups the system.
- 5:32SPEAKER_00: So you can even plan that.
- 5:35You know,
- 5:35the current end of the federal highway bill is September of 2026.
- 5:39SPEAKER_00: But all over the country, states are planning projects for 2027 and 2028.
- 5:44SPEAKER_00: Not legally.
- 5:46SPEAKER_00: They don't legally have that money.
- 5:48SPEAKER_00: But practically speaking, they do.
- 5:51SPEAKER_00: And it just, it makes a big difference.
- 5:53SPEAKER_00: Whereas transit agencies do get some money by what,
- 5:57SPEAKER_00: by formula,
- 5:58SPEAKER_00: they get a certain amount,
- 5:59SPEAKER_00: but it's really to do maintenance.
- 6:01SPEAKER_00: It's not for big projects.
- 6:02SPEAKER_00: If they want to do a big project,
- 6:04they have to apply for the money and go through a multi-year
- 6:07process before they
- 6:09SPEAKER_00: know they're getting the money.
- 6:10SPEAKER_00: And then when they do that,
- 6:11they get money for one project and they have to come back for
- 6:13the next project they
- 6:14SPEAKER_00: want to do.
- 6:16Can states use that formula funding for big projects legally,
- 6:20or is it just not enough capital?
- 6:21SPEAKER_00: It's a great question.
- 6:22SPEAKER_00: So the biggest transit systems,
- 6:25SPEAKER_00: the ones many people think about when they think about transit,
- 6:28SPEAKER_00: New York and Chicago and Philadelphia and Boston and San Francisco,
- 6:32SPEAKER_00: no.
- 6:33SPEAKER_00: Smaller systems that mostly run buses don't.
- 6:36SPEAKER_00: do have flexibility under federal law.
- 6:39SPEAKER_00: They can move the money between operating the system,
- 6:42SPEAKER_00: maintaining the system,
- 6:43SPEAKER_00: and doing capital work.
- 6:45SPEAKER_00: But the bigger systems,
- 6:46SPEAKER_00: by and large,
- 6:47SPEAKER_00: the federal government sees its role as supporting their maintenance,
- 6:51SPEAKER_00: but not big capital projects.
- 6:54SPEAKER_01: You've had a really interesting career,
- 6:56SPEAKER_01: Stephanie,
- 6:56SPEAKER_01: and I'll just flag a couple key points here for listeners.
- 6:59You were an environmental advocate for something called the
- 7:02Conservation Law
- 7:03SPEAKER_01: Foundation in Massachusetts.
- 7:05SPEAKER_01: You sued the MBTA over price increases.
- 7:08SPEAKER_01: You were in court with state and local transit agencies.
- 7:11SPEAKER_01: Later,
- 7:12SPEAKER_01: you end up on the other side of those kinds of fights in the cabinet of
- 7:16SPEAKER_01: Massachusetts Governor Baker at the State Department of Transportation.
- 7:19SPEAKER_01: You're involved in building out state and local transit.
- 7:22SPEAKER_01: And then you end up not so much in the transit side,
- 7:24SPEAKER_01: but at the federal level,
- 7:26SPEAKER_01: the Federal Transit Administration working on federal highways.
- 7:29SPEAKER_01: We were talking before this conversation.
- 7:31You sent me over a bunch of Boston Globe articles and other
- 7:34reading about projects
- 7:35SPEAKER_01: you'd worked on,
- 7:36SPEAKER_01: like the Green Line extension.
- 7:37SPEAKER_01: And
- 7:37One of the things that your critics say in those articles is
- 7:40something like,
- 7:41SPEAKER_01: Stephanie was critical of these projects at one point,
- 7:43SPEAKER_01: now she's on the other side,
- 7:44SPEAKER_01: or she wanted more funding for them at one point,
- 7:47SPEAKER_01: and now she's saying,
- 7:48SPEAKER_01: we don't have that money.
- 7:49How do you think about the through line of your career on these
- 7:52different kinds of
- 7:52SPEAKER_01: transit projects?
- 7:54SPEAKER_00: So I would say there's one through line that hasn't changed,
- 7:57SPEAKER_00: and that's the importance of transit,
- 8:00SPEAKER_00: not just as a mode of transportation,
- 8:02but as the glue that holds a region and its economy together
- 8:06and that creates
- 8:08access for people for whom a car is not an affordable or
- 8:12realistic way of getting around.
- 8:14That's why you sue the MBTA when they try to raise fares and
- 8:17you're worried that
- 8:17SPEAKER_00: they're going to make transit unaffordable,
- 8:19SPEAKER_00: right?
- 8:19Or that's why you sue when this Commonwealth of Massachusetts
- 8:22is going to build a
- 8:23giant highway project and you're worried they're going to
- 8:25neglect investment on the
- 8:27SPEAKER_00: transit side of the house,
- 8:28SPEAKER_00: right?
- 8:28SPEAKER_00: So that is the through line,
- 8:31SPEAKER_00: is the centrality of transit,
- 8:32SPEAKER_00: at least for big metropolitan areas like Boston,
- 8:35SPEAKER_00: not just to the transportation system,
- 8:38SPEAKER_00: but to people and communities and the economy.
- 8:41I think the difference is over the different roles that I've
- 8:44played in my career.
- 8:45SPEAKER_00: I've learned a lot more.
- 8:47And I think there was a certain amount of naivete early in my
- 8:52career about,
- 8:53SPEAKER_00: well,
- 8:54SPEAKER_00: if they sign a legal document and say they're going to build a project,
- 8:58SPEAKER_00: then they're
- 8:59legally obligated to build the project and the money part is
- 9:03not my problem.
- 9:04SPEAKER_00: The money part is their problem.
- 9:05SPEAKER_00: They made the promise.
- 9:07And the more I came to understand the intricacies of the
- 9:12financing system at the
- 9:13SPEAKER_00: state and federal level,
- 9:15SPEAKER_00: the more I understood that the game is actually the money.
- 9:18Like it doesn't mean anything to say we're going to run a
- 9:21world-class transit
- 9:22SPEAKER_00: system or we're going to build this project by this year.
- 9:26SPEAKER_00: None of that is true if you haven't figured out what you're building,
- 9:29SPEAKER_00: how you're going to build it,
- 9:30SPEAKER_00: and most importantly,
- 9:32SPEAKER_00: how you're going to pay for it.
- 9:34Give me an example of that intellectual change or that move
- 9:38from naivete to getting
- 9:40SPEAKER_01: it on the money side.
- 9:40SPEAKER_01: What's a case study in your life where that realization hit you?
- 9:44When the big dig was being planned in Boston and there were all
- 9:48these concerns that
- 9:49it was going to sort of suck up all the money and there wasn't
- 9:51going to be money
- 9:52SPEAKER_00: for transit,
- 9:53SPEAKER_00: the thought was,
- 9:55SPEAKER_00: well,
- 9:56SPEAKER_00: there's two different transportation entities in Massachusetts.
- 9:59SPEAKER_00: There's the state transportation department,
- 10:01SPEAKER_00: formerly the highway department,
- 10:03SPEAKER_00: and there's the MBTA.
- 10:05SPEAKER_00: And we were very clear that we didn't want the MBTA to be
- 10:10SPEAKER_00: Right.
- 10:11For transit that was being built as part of this bigger Eastern
- 10:16Massachusetts enterprise.
- 10:17SPEAKER_00: The big dig wasn't a project.
- 10:18SPEAKER_00: It was a series of,
- 10:20SPEAKER_00: to us in the environmental world and in the community,
- 10:22it was a series of projects and the transit projects were just
- 10:25as important as the
- 10:26SPEAKER_00: highway line.
- 10:26SPEAKER_00: And so the thought was,
- 10:27SPEAKER_00: you know,
- 10:28SPEAKER_00: it was a transit project,
- 10:29but it was the Commonwealth of Massachusetts that was going to
- 10:32be responsible.
- 10:32And it somehow wasn't going to affect the T's budget to build
- 10:35and operate these projects.
- 10:37SPEAKER_00: That is so not true.
- 10:39SPEAKER_00: Right.
- 10:40SPEAKER_01: Why?
- 10:40Well,
- 10:41for one thing,
- 10:42it's always the T's responsibility to operate the project.
- 10:45SPEAKER_00: And like when we when I was secretary,
- 10:48SPEAKER_00: we actually took a look at what it does to the operating budget.
- 10:51SPEAKER_00: Right.
- 10:52SPEAKER_00: Or I'll give you another example.
- 10:53SPEAKER_00: So the Green Line extension,
- 10:55SPEAKER_00: it made the Green Line,
- 10:56SPEAKER_00: which is already a pretty long transit line,
- 10:59SPEAKER_00: almost five miles longer.
- 11:00So if you try to operate a much longer transit line with the
- 11:04same number of trains,
- 11:06it's going to take way longer for a train to get from the
- 11:08beginning to the end.
- 11:09SPEAKER_00: And you're actually going to have less service, right?
- 11:11SPEAKER_00: Like you're going to wait the platform longer for the next train.
- 11:14SPEAKER_00: So you have to buy trains.
- 11:15SPEAKER_00: I didn't know that when we were first,
- 11:18SPEAKER_00: like I just,
- 11:19SPEAKER_00: I was thinking about the extension as its tracks,
- 11:21SPEAKER_00: its signals,
- 11:22SPEAKER_00: its platforms,
- 11:23SPEAKER_00: right?
- 11:24SPEAKER_00: Well, you have to buy trains.
- 11:25Oh,
- 11:25well,
- 11:25so they had to buy 24 new trains and that was almost $200 million.
- 11:29SPEAKER_00: In addition, now you own 24 new trains.
- 11:32SPEAKER_00: We're going to take care of those trains.
- 11:34SPEAKER_00: There's all these FTA requirements.
- 11:35SPEAKER_00: They have to be inspected.
- 11:36SPEAKER_00: They have to get upgrades.
- 11:38SPEAKER_00: They don't have enough space at their existing maintenance facility.
- 11:41SPEAKER_00: They have a certain size fleet.
- 11:42SPEAKER_00: They have a certain number of train cars.
- 11:44SPEAKER_00: So now you have to build a new maintenance project.
- 11:47SPEAKER_00: U.S.
- 11:47SPEAKER_00: transit agencies are often...
- 11:49criticized for spending so much more money than European
- 11:53transit agencies or Asian
- 11:54SPEAKER_00: transit agencies.
- 11:55But I think one of the problems is that the way the system
- 11:58works in this country,
- 11:59the conversation about things like how big should the fleet be
- 12:03and how are you
- 12:03SPEAKER_00: going to maintain it is driven by a project.
- 12:06The conversation about the Green Line in Boston got driven by
- 12:08the Green Line extension,
- 12:09and the cost of the Green Line extension includes 24 new cars
- 12:13and a brand new
- 12:13SPEAKER_00: maintenance facility.
- 12:14SPEAKER_00: Hundreds of millions of dollars.
- 12:16SPEAKER_00: Well,
- 12:16SPEAKER_00: if you take the cost of the project and divide by the number of miles,
- 12:19SPEAKER_00: right,
- 12:19SPEAKER_00: you're going to have a really high cost per mile.
- 12:22But hundreds of millions of that cost aren't to extend the
- 12:25system by 4.7 miles.
- 12:27They're to buy trains and build a maintenance facility that in
- 12:29a different system
- 12:30SPEAKER_00: is in a different part of the budget.
- 12:32SPEAKER_00: The problem for transit in the U.S.
- 12:34SPEAKER_00: is there is no different part of the budget.
- 12:37SPEAKER_01: That's a great clarification.
- 12:39SPEAKER_01: Will you double back and let's just go chronologically for a second.
- 12:42SPEAKER_01: Explain to me like I'm from Arizona and have never heard of the big dig.
- 12:46SPEAKER_01: What was the big dig?
- 12:48SPEAKER_01: And then we'll get to the green line extension.
- 12:49SPEAKER_01: I think both of these are worthwhile to talk about.
- 12:52So the big dig was the nickname given to a project that was
- 12:57proposed by Michael
- 12:58Dukakis when he was governor of Massachusetts in the 1980s to
- 13:02take an elevated road
- 13:04that ran through the middle of downtown Boston and really cut
- 13:08the city off from
- 13:09SPEAKER_00: Boston Harbor and bury it underground,
- 13:11SPEAKER_00: both to make traffic flow better.
- 13:14SPEAKER_00: but also as an urban planning endeavor, right?
- 13:17To have this beautiful surface in the city of Boston where you
- 13:21could stroll right
- 13:22over to the edge of the Boston Harbor without walking
- 13:26underneath this horrible,
- 13:28SPEAKER_00: always congested,
- 13:29SPEAKER_00: elevated highway viatac.
- 13:31SPEAKER_00: It was formally called the Central Artery Tunnel Project,
- 13:33SPEAKER_00: but it became known as the Big Dig,
- 13:36probably infamous because then Congressman Barney Frank at one
- 13:39point said that he
- 13:40had come to the conclusion that it would be easier to raise the
- 13:44city than lower the
- 13:45SPEAKER_00: central artery.
- 13:47SPEAKER_01: And the Big Dig was originally estimated around $2 billion.
- 13:51SPEAKER_01: What did it come in at when all is said and done?
- 13:54SPEAKER_00: $12 billion, but that's if you don't count the cost of financing it.
- 13:58SPEAKER_00: Because for some odd reason,
- 13:59we don't include interest on the bonds that get issued to pay
- 14:03for these projects
- 14:04SPEAKER_00: and their project costs,
- 14:05SPEAKER_00: but at least $12 billion instead of $2 billion.
- 14:08SPEAKER_00: And so the big dig was important to the city.
- 14:11It was important because almost every transportation
- 14:14professional in greater Boston,
- 14:16SPEAKER_00: including some of the ones who later worked on the Green Line Extension,
- 14:19SPEAKER_00: cut their teeth on the big dig because it employed
- 14:21everybody and it was important because it got a national
- 14:24profile because it ran so
- 14:26far over budget and over time that there were congressional
- 14:30hearings and there was
- 14:31a decision to basically i told you at the beginning there's
- 14:33always money for
- 14:34highways the big dig was the exception they actually cut the
- 14:37money off and said no
- 14:38SPEAKER_00: state has to pay for this this is ridiculous
- 14:41SPEAKER_01: We'll get into a couple of different case studies of cost overruns,
- 14:45SPEAKER_01: and they're not all the same.
- 14:46SPEAKER_01: I mean,
- 14:46SPEAKER_01: the Big Dig is very different from a transit extension,
- 14:48SPEAKER_01: is different from other kinds of projects.
- 14:50But real quickly,
- 14:51I mean,
- 14:51what went into the incredible cost overruns for the Big Dig?
- 14:55SPEAKER_01: How should I, as a layman, think about those at least 6x overruns?
- 15:00SPEAKER_01: And that's the low end, right?
- 15:02SPEAKER_00: So I would say it's worth thinking about three different things.
- 15:05SPEAKER_00: It's only a cost overrun if the cost you thought was real.
- 15:10So the first thing is there was never a $2 billion central
- 15:13artery tunnel project
- 15:14SPEAKER_00: and there was never a $600 million green line extension.
- 15:17SPEAKER_00: When people build projects,
- 15:19SPEAKER_00: the cost estimates at the beginning are based on almost no information.
- 15:24And the incentive that any supporter of the project has is
- 15:28going to be to lowball
- 15:28SPEAKER_00: the cost,
- 15:29SPEAKER_00: right?
- 15:29Because if you tell people $12 billion at the beginning,
- 15:32the answer could be no.
- 15:33SPEAKER_00: But if you say for only $2 billion,
- 15:35SPEAKER_00: you can transform the city of Boston and make traffic go away,
- 15:38SPEAKER_00: then you have a conversation.
- 15:39SPEAKER_00: Some people would say it's deliberate.
- 15:41SPEAKER_00: Some people would say it's what economists call optimism bias, right?
- 15:45SPEAKER_00: People are just like, oh, yeah, we can do it.
- 15:47But I think the first thing I would say is almost any time you
- 15:50hear about a project
- 15:51SPEAKER_00: that has doubled,
- 15:52SPEAKER_00: tripled,
- 15:52SPEAKER_00: quadrupled,
- 15:53SPEAKER_00: quintupled,
- 15:53it actually there was never a time it was going to be built for
- 15:56that price.
- 15:57SPEAKER_00: That price was a fantasy.
- 15:59SPEAKER_00: So that's the first thing to think about.
- 16:01SPEAKER_01: Just on my end,
- 16:02SPEAKER_01: professionally,
- 16:03SPEAKER_01: in my editorial work,
- 16:04SPEAKER_01: we talk about the planning fallacy all the time,
- 16:06SPEAKER_01: that you always underestimate the amount of time it's going to take you,
- 16:09SPEAKER_01: the author,
- 16:09SPEAKER_01: to finish a certain piece of work.
- 16:10So it sounds like there's just a similar kind of fundamental
- 16:13human thing going on here.
- 16:14SPEAKER_00: There absolutely is.
- 16:15So that's the first thing that tends to push all large scale
- 16:19infrastructure
- 16:20SPEAKER_00: projects way over their initial budget.
- 16:23SPEAKER_00: The second thing is what planners and engineers would call mission creed.
- 16:28SPEAKER_00: Once you get some momentum on a project,
- 16:30whether it's the Big Dig or the Green Line Extension or the
- 16:34Second Avenue Subway in
- 16:35SPEAKER_00: New York,
- 16:35SPEAKER_00: people sort of see this money train and they're like,
- 16:39SPEAKER_00: oh,
- 16:39SPEAKER_00: doing that,
- 16:40can you do these other things that like are in the general
- 16:43geographic vicinity that
- 16:45SPEAKER_00: we've never been able to find money,
- 16:47SPEAKER_00: right?
- 16:47SPEAKER_00: So let's attach different pieces to the project.
- 16:50SPEAKER_00: Let's fix a bunch of the river roads.
- 16:53SPEAKER_00: Let's fix a bunch of other bridges.
- 16:55SPEAKER_00: Let's build a bunch of parks.
- 16:56SPEAKER_00: Let's build a bicycle and pedestrian path next to
- 16:59SPEAKER_00: it.
- 16:59And so the initial estimate is actually for a project that
- 17:03bears only a passing
- 17:05SPEAKER_00: resemblance to the project that gets built.
- 17:07The project that gets built tends to be bigger,
- 17:10more complicated,
- 17:11and have more elements.
- 17:12SPEAKER_00: And the more things you add to the project, the cost goes up.
- 17:16SPEAKER_00: That original $2 billion didn't include certain things, right?
- 17:18SPEAKER_00: Same for the green line.
- 17:19SPEAKER_00: So that's the second thing.
- 17:21The project that you build doesn't really look like the first
- 17:24project that you estimate.
- 17:26SPEAKER_00: Then the last thing,
- 17:27SPEAKER_00: and I think that this is a huge problem,
- 17:29SPEAKER_00: not just in transit,
- 17:30SPEAKER_00: but in infrastructure delivery in this country,
- 17:32SPEAKER_00: is we build projects really,
- 17:35SPEAKER_00: really,
- 17:35SPEAKER_00: really slowly,
- 17:37SPEAKER_00: right?
- 17:37SPEAKER_00: So when the big dig was being permitted, it was 1990 and 1991.
- 17:43And that was the first time there was a conversation and the
- 17:46Commonwealth said,
- 17:47SPEAKER_00: you should build the Green Line extension.
- 17:49SPEAKER_00: And folks said, okay, we should have a deadline for you to do that.
- 17:53SPEAKER_00: And the deadline is going to be 2011.
- 17:55SPEAKER_00: We're talking about 21 years.
- 17:58SPEAKER_00: We're setting a deadline.
- 18:00SPEAKER_00: We're planning to take forever to build that project.
- 18:04SPEAKER_00: Same thing with the big dig.
- 18:05SPEAKER_00: Well, time is money when you construct projects.
- 18:08SPEAKER_00: And this is particularly true when you start a project
- 18:11and you don't know how you're going to pay for it because you
- 18:14don't put out one big
- 18:15SPEAKER_00: contract to build the project.
- 18:17SPEAKER_00: You actually put out a contract for the money you have.
- 18:21SPEAKER_00: It's a $2 billion contract.
- 18:22SPEAKER_00: I only have $600 million this year.
- 18:25SPEAKER_00: I'll put a $600 million contract out.
- 18:27SPEAKER_00: We'll start to do some preliminary work.
- 18:29And then at the end of that contract,
- 18:31I'm going to go procure a new contract.
- 18:33SPEAKER_00: I'm going to maybe hire a different company, depending on who bids.
- 18:36The first company is going to be paid to take down all the
- 18:39stuff that they're no longer using.
- 18:40The new company is going to be paid to what's called mobilize,
- 18:43put up new stuff.
- 18:44SPEAKER_00: And so
- 18:45Building projects in this sort of series over a long time
- 18:49because we don't have
- 18:50enough money at the beginning to end is really toxic to
- 18:54delivering projects on budget.
- 18:56But it's kind of how we've gotten in the habit of building
- 18:58things in this country
- 18:59over the last decades because we rarely actually have all the
- 19:02money for a project
- 19:03SPEAKER_00: when we get started.
- 19:05SPEAKER_01: I have so many questions to follow up here.
- 19:07SPEAKER_01: Right off the bat, how does inflation play into all of this?
- 19:10SPEAKER_01: Because it's not just that you're waiting on new rounds of money,
- 19:13but the actual money that you have is the real value of that is
- 19:16being eaten away
- 19:17SPEAKER_01: over time.
- 19:18SPEAKER_00: So the interesting thing,
- 19:20SPEAKER_00: it's hard to remember now,
- 19:21SPEAKER_00: but before COVID,
- 19:23SPEAKER_00: we had a four-decade run of very low inflation in this country,
- 19:28SPEAKER_00: right?
- 19:29During the heart of the growth in the federally funded
- 19:33infrastructure program,
- 19:34SPEAKER_00: both the interstates and then the programs to build transit,
- 19:37SPEAKER_00: which is the 80s,
- 19:38SPEAKER_00: the 90s,
- 19:39SPEAKER_00: the 2000s,
- 19:40SPEAKER_00: post-Jimmy Carter stagflation,
- 19:42SPEAKER_00: we don't have a lot of inflation,
- 19:44SPEAKER_00: right?
- 19:45SPEAKER_00: People don't actually think that much about the time value of drive.
- 19:50They don't say,
- 19:51oh,
- 19:51well,
- 19:51if you spend 10 years instead of five years building it,
- 19:54right?
- 19:55SPEAKER_00: But now,
- 19:56SPEAKER_00: because of COVID,
- 19:57SPEAKER_00: because of inflation,
- 19:59SPEAKER_00: because of a lot of other reasons,
- 20:01SPEAKER_00: I mean,
- 20:01SPEAKER_00: at its peak,
- 20:03the tracking measure that the Federal Highway Administration
- 20:07used to measure
- 20:08construction cost inflation on the highway side was growing at
- 20:122% per month.
- 20:14So that meant if you delayed a project five months for a
- 20:18community process or a
- 20:19SPEAKER_00: permit or procurement,
- 20:21SPEAKER_00: you just increased the cost of the project 10%.
- 20:24SPEAKER_00: Now you don't have enough money for the project.
- 20:25SPEAKER_00: So then you go and you find more money for the project,
- 20:28SPEAKER_00: which takes you months,
- 20:29SPEAKER_00: during which time the cost of the project goes up.
- 20:32SPEAKER_00: So in an atmosphere of one or 2% per month,
- 20:36SPEAKER_00: construction cost inflation,
- 20:38SPEAKER_00: you can't build projects the way you built them when there wasn't any,
- 20:42SPEAKER_00: except we still do.
- 20:43SPEAKER_01: That's incredible.
- 20:44SPEAKER_01: With a big dig,
- 20:45SPEAKER_01: when you had structurally lower inflation,
- 20:48what are the factors there that lead to the target date being
- 20:5220 years out from
- 20:54SPEAKER_01: when you kick off?
- 20:54SPEAKER_01: Well,
- 20:55SPEAKER_01: before you answer that,
- 20:56SPEAKER_01: I'll say on Statecraft,
- 20:56we talk a lot about permitting and that big burden to projects
- 21:00that puts timelines out.
- 21:01SPEAKER_01: But as I'm sure you're going to say,
- 21:02SPEAKER_01: there's other factors that are not permitting,
- 21:04things that we don't pay as much attention to on this podcast
- 21:07that play a big role.
- 21:08So I would say that it's helpful if you think about four Ps and
- 21:13one of them is permitting.
- 21:14SPEAKER_00: It is not a bad thing to spend a long time planning.
- 21:17There's an argument that's been made by many people that more
- 21:20time planning and
- 21:21SPEAKER_00: then once you get started,
- 21:23SPEAKER_00: go fast.
- 21:23SPEAKER_00: So plan long and then build fast.
- 21:26SPEAKER_00: It could be a real thing, but we can plan forever.
- 21:28And this is particularly true,
- 21:30again,
- 21:30for projects for which we don't have enough money.
- 21:32SPEAKER_00: Because if you're an elected official or a supporter of that project,
- 21:36you create some sense of momentum by having planning meetings
- 21:40and issuing documents
- 21:41SPEAKER_00: and doing PowerPoints and maybe having little events.
- 21:47SPEAKER_00: There's a different project in Massachusetts called South Coast Rail.
- 21:50SPEAKER_00: And when we did a groundbreaking for it,
- 21:51SPEAKER_00: when I was the secretary,
- 21:53SPEAKER_00: the state senator who represented the district said,
- 21:55SPEAKER_00: this is my fifth groundbreaking for this project.
- 21:58Because previous governors had found some money and done a
- 22:01little piece of work and
- 22:02SPEAKER_00: held a groundbreaking.
- 22:04SPEAKER_00: So planning takes us a long time on purpose.
- 22:07SPEAKER_00: Permitting is real.
- 22:10SPEAKER_01: And if I can't get,
- 22:12SPEAKER_01: say,
- 22:12SPEAKER_01: the state legislature to pony up enough money in a given year,
- 22:16SPEAKER_01: all I can really do is planning,
- 22:17SPEAKER_01: right?
- 22:17SPEAKER_01: That's the only thing that fits the scope.
- 22:20SPEAKER_01: I can't really truly start the project, but I can do more planning.
- 22:24SPEAKER_00: Right.
- 22:25SPEAKER_00: Because because planning and permitting,
- 22:27SPEAKER_00: you know,
- 22:28SPEAKER_00: is as frustrating as they can be and is lengthy.
- 22:31SPEAKER_00: In the end, they're going to be 10, 15, 20 percent of your project cost.
- 22:34SPEAKER_00: Most of your project cost is going to be building it.
- 22:37SPEAKER_00: Right.
- 22:37SPEAKER_00: If you have short money, it's a great thing to do.
- 22:39SPEAKER_00: So planning and then planning is followed by permitting,
- 22:42which unquestionably takes too long and is too complicated in
- 22:47this country.
- 22:47SPEAKER_00: And then planning and permitting, the third P is public engagement.
- 22:52SPEAKER_00: And on the one hand,
- 22:53all of us agree that certainly it is critically important that
- 22:57the people who,
- 22:57SPEAKER_00: both the people who are going to use a piece of infrastructure,
- 23:00but also the people who are going to be affected by a piece of
- 23:02infrastructure
- 23:03SPEAKER_00: because it goes through their neighborhood.
- 23:06SPEAKER_00: The problem with those three Ps,
- 23:07SPEAKER_00: planning,
- 23:07SPEAKER_00: permitting,
- 23:08SPEAKER_00: and public engagement is being gone forever,
- 23:11SPEAKER_00: right?
- 23:12SPEAKER_00: You've heard people call it the vitocracy.
- 23:14SPEAKER_00: And what I say is the processes are a real problem, okay?
- 23:17SPEAKER_00: But the truth is at the end of the day, the actual problem is, is that
- 23:22SPEAKER_00: No one is willing to make a decision and find the money.
- 23:24So until someone is willing to make a decision,
- 23:27either yes,
- 23:27we're building it or no,
- 23:28we're not.
- 23:29SPEAKER_00: And I can tell you how we're going to pay for it.
- 23:31SPEAKER_00: Then planning and permitting and public engagement go on and on,
- 23:34SPEAKER_00: not just for years,
- 23:35SPEAKER_00: but in some cases for decades.
- 23:37SPEAKER_00: And then when people look backwards,
- 23:38SPEAKER_00: they say,
- 23:39SPEAKER_00: oh,
- 23:39SPEAKER_00: the planning,
- 23:40SPEAKER_00: permitting and public engagement is why it took decades.
- 23:44As opposed to the unwillingness to make a go no go decision and
- 23:48the lack of money
- 23:49SPEAKER_00: is why it took decades.
- 23:50SPEAKER_00: And during those decades,
- 23:52SPEAKER_00: we did a lot of planning,
- 23:54SPEAKER_00: permitting and public engagement to keep the project alive.
- 23:57SPEAKER_01: That's an interesting point that while you're waiting,
- 24:00SPEAKER_01: the political will,
- 24:01these processes can just drag out forever because what else are
- 24:04you going to do?
- 24:05SPEAKER_00: And to some, and I want to be clear, there's value, right?
- 24:09SPEAKER_00: Like they are advancing the product.
- 24:10SPEAKER_00: You're learning things.
- 24:11SPEAKER_00: You're figuring out how to build things.
- 24:13SPEAKER_00: Sometimes if you're creative, you find little pieces of money.
- 24:16SPEAKER_00: And so you fix some utilities that are in the way,
- 24:19or you fix a bridge that's going to need to carry train tracks
- 24:23and heavy trains,
- 24:24SPEAKER_00: or you fix a place where the road and train tracks meet,
- 24:27SPEAKER_00: which is called a crossing.
- 24:29SPEAKER_00: and you're going to have to have a bunch of grade crossings fixed.
- 24:32SPEAKER_00: So if you can do five a year,
- 24:34SPEAKER_00: every year for five years,
- 24:36SPEAKER_00: then 25 grade crossings are done,
- 24:38SPEAKER_00: and then they don't have to be part of the project.
- 24:39SPEAKER_00: So I don't want people to think that the entire planning,
- 24:43SPEAKER_00: permitting,
- 24:44SPEAKER_00: public engagement time is a waste.
- 24:46SPEAKER_00: It's not.
- 24:47SPEAKER_00: But I would say that amount of value it adds to a project is
- 24:51is small relative to like what you could get if you had a more
- 24:56succinct process.
- 24:58SPEAKER_00: And when we talk about the Greenline extension,
- 25:00I can talk a little bit about how you could actually get
- 25:03through a compressed version.
- 25:04And then I just also want to mention the fourth P is procurement,
- 25:07which is absurd.
- 25:09SPEAKER_00: and not something that a lot of people think about.
- 25:12But procurement is the legal process by which you hire the
- 25:16people who are going to
- 25:17SPEAKER_00: build your project.
- 25:18SPEAKER_00: And it's really important to get it right.
- 25:21SPEAKER_00: And so that's another one where it adds time to the process,
- 25:25SPEAKER_00: but it actually adds value to the process.
- 25:28If you have the right team and the right contract structured
- 25:31the right way,
- 25:32SPEAKER_00: the odds that you can deliver the project are good.
- 25:34SPEAKER_00: And if you get procurement wrong,
- 25:36SPEAKER_00: You know,
- 25:36you're basically starting off in the wrong place and you
- 25:40haven't even begun
- 25:40SPEAKER_00: building the project.
- 25:42SPEAKER_01: Talk me through the big dig in a little more detail.
- 25:44How did each of those piece play into the big dig and the
- 25:47amount of time it took time and money?
- 25:49so planning took a while in part because in the end the big dig
- 25:54actually was a
- 25:55combination well at first it was a combination of two road
- 25:58projects that were
- 25:59separate right one was to bury this elevated highway through
- 26:02the center of boston
- 26:04but a second one was to build a third tunnel under boston
- 26:08harbor to connect logan
- 26:10SPEAKER_00: airport to metropolitan boston
- 26:13Logan Airport was built actually on an island out in the middle
- 26:16of Boston Harbor.
- 26:17SPEAKER_00: And then as it grew, it filled in a bunch of islands.
- 26:20SPEAKER_00: And so access to the airport was a huge transportation,
- 26:23SPEAKER_00: but an even bigger economic development limited issue.
- 26:26SPEAKER_00: So there was sort of a project that was about the tunnel.
- 26:29SPEAKER_00: And then there was a project that was about the artery.
- 26:32And the decision was made by Governor Dukakis and his
- 26:34transportation secretary,
- 26:35SPEAKER_00: Fred Salvucci,
- 26:36SPEAKER_00: to put those two together.
- 26:37And that's probably what created enough benefits and political
- 26:41momentum to get it done.
- 26:42SPEAKER_00: But as you can imagine,
- 26:43a planning process that starts with two pretty big projects and
- 26:47then combines them
- 26:47SPEAKER_00: into one gigantic process takes a long time.
- 26:51SPEAKER_01: Okay.
- 26:51SPEAKER_01: So that's planning.
- 26:52SPEAKER_00: So a lot of people talk about something called NEPA,
- 26:55SPEAKER_00: or the National Environmental Policy Act,
- 26:57SPEAKER_00: as permitting.
- 26:58SPEAKER_00: And it is important.
- 26:59SPEAKER_01: I talk a lot about NEPA.
- 27:00SPEAKER_00: I've done probably more NEPA.
- 27:02SPEAKER_00: Like I've written comments.
- 27:03SPEAKER_00: I've sued people under NEPA.
- 27:05I've signed records of decision in my role as federal highway
- 27:08administrator under NEPA.
- 27:09SPEAKER_00: And it's really important, but it's actually not permitting, right?
- 27:13SPEAKER_00: And one of the problems with permitting,
- 27:15actually one of the problems with all of these processes we're
- 27:17talking about is
- 27:18SPEAKER_00: that they are sequential instead of concurrent.
- 27:22SPEAKER_00: We do them one after another instead of at the same time.
- 27:25SPEAKER_00: If you think about it,
- 27:27There is no reason you couldn't do planning and public
- 27:29engagement and permitting
- 27:31SPEAKER_00: kind of at the same time.
- 27:32And you could spend four years on each of them and you could be
- 27:35done in four years.
- 27:37Or you could spend four years on each of them sequentially and
- 27:40it could take you 12 years,
- 27:41SPEAKER_00: right?
- 27:42SPEAKER_00: Permitting is very non-sequential in the United States.
- 27:46SPEAKER_00: NEPA was designed.
- 27:48SPEAKER_00: It's a very short law.
- 27:49SPEAKER_01: It's five pages, I think.
- 27:51SPEAKER_00: Yeah, it's like five pages.
- 27:52SPEAKER_00: Like we talk about laws now that are a thousand pages long, right?
- 27:55So it's like amazing that we had a five page law and that it's
- 27:58made such a difference.
- 27:59SPEAKER_00: But the idea of NEPA was you should gather a lot of information,
- 28:03give the public a shot to look at that information and use that
- 28:07information to
- 28:08SPEAKER_00: better define your project,
- 28:09to identify what is usually referred to as the locally
- 28:12preferred alternative.
- 28:13And then having finished that sort of information gathering
- 28:17part of the process,
- 28:18SPEAKER_00: then you move into actual permits.
- 28:20SPEAKER_00: You need a permit, you know, to move utilities.
- 28:22SPEAKER_00: You need a permit to fill in part of a river.
- 28:24SPEAKER_00: You need a permit to build on part of a park.
- 28:26And some of those are federal permits and some of those are
- 28:29state permits and some
- 28:31SPEAKER_00: of those are local,
- 28:32SPEAKER_00: right?
- 28:33SPEAKER_00: Just because it's a federal project.
- 28:34And so that's the thing is like finishing NEPA is the starting
- 28:37gun for the rest of permitting.
- 28:40SPEAKER_00: People think it's the finish line.
- 28:41SPEAKER_00: It's not.
- 28:42SPEAKER_00: It's the starting line.
- 28:43SPEAKER_00: And so NEBA itself,
- 28:45I think last time I looked before the most recent set of
- 28:49process reforms made by
- 28:50Congress was taking six to eight years for big carry projects
- 28:53like the Central
- 28:54SPEAKER_00: Artery Project and the Green Line Extension.
- 28:57SPEAKER_00: But when that's done, all you have is a giant factual record.
- 29:01SPEAKER_00: You don't actually have a single permit.
- 29:04SPEAKER_01: I want to ask this carefully,
- 29:05but how has your view on the ability to litigate under NEPA and
- 29:09then state and
- 29:10local permitting requirements changed since you went from the
- 29:13litigating side to
- 29:14SPEAKER_01: the state side?
- 29:16The fact that you can litigate under NEPA is essential if your
- 29:21concern is that
- 29:22SPEAKER_00: agencies will not do their job and that they need to be held accountable.
- 29:26And so if you hand them a process and let them screw up the
- 29:29process and then they
- 29:30SPEAKER_00: can still move on and permit and procure and build the project,
- 29:33SPEAKER_00: that's a terrible thing.
- 29:35SPEAKER_00: But once you subject that decision at the end of NEPA to litigation,
- 29:41SPEAKER_00: it's not just the lawsuit part takes.
- 29:43It changes everyone's behavior throughout the entire process
- 29:47because everybody is
- 29:48SPEAKER_00: thinking about the lawsuit.
- 29:49The NEPA process at this point is about minimizing the risk of
- 29:53a lawsuit or
- 29:55covering your butt if there's actually a lawsuit or creating
- 29:57the factual record.
- 29:59SPEAKER_00: And so what I have said,
- 30:00and I'm a big supporter of intelligent deproceduralization and
- 30:05process reform,
- 30:06but if you reform the process and you make it a really quick
- 30:09and dirty process and
- 30:10it's short and it doesn't have thousands of pages and all that
- 30:12kind of stuff,
- 30:13SPEAKER_00: and you can still litigate the result of that process,
- 30:17SPEAKER_00: I'm not sure that it just doesn't turn into the next NEPA,
- 30:20SPEAKER_00: like whatever you call it.
- 30:21SPEAKER_00: So that litigation decision is really critical.
- 30:23But if you don't allow litigation,
- 30:25then what you're saying is,
- 30:26well,
- 30:27what is the accountability?
- 30:28SPEAKER_00: We're having this conversation right in April of 2025.
- 30:32SPEAKER_00: It's hard to have a conversation right now and say,
- 30:35we're comfortable not having the courts have any role in
- 30:38holding government
- 30:39SPEAKER_00: agencies accountable for the actions they take.
- 30:41SPEAKER_00: Like right now,
- 30:42SPEAKER_00: it feels like in some areas,
- 30:44there isn't anyone but the courts who has a chance of holding
- 30:47certain federal
- 30:47SPEAKER_00: agencies accountable for certain things they're doing,
- 30:49SPEAKER_00: not just infrastructure.
- 30:50SPEAKER_00: So it's not an easy call.
- 30:52It absolutely completely shapes the process that there is
- 30:56litigation at the end.
- 30:57SPEAKER_00: But if you take it away, what does that mean?
- 31:00SPEAKER_01: You're making a bunch of my points for me on this conversation.
- 31:03What my colleagues at the Institute for Progress would say on a
- 31:05lot of this,
- 31:06they would totally agree with you that the ability to litigate
- 31:09is a bigger problem
- 31:10SPEAKER_01: than the specific requirements on agencies in NEPA.
- 31:14SPEAKER_01: But you can also litigate under other substantive requirements,
- 31:17SPEAKER_01: that the feds not dump sludge in the water,
- 31:20SPEAKER_01: right?
- 31:20SPEAKER_01: And NEPA isn't one of those requirements.
- 31:22SPEAKER_01: It's a requirement about process.
- 31:24Do you think environmental advocates in an ideal world would
- 31:27spend time litigating
- 31:28those kinds of substantive requirements and not have as much
- 31:32surface to litigate
- 31:33SPEAKER_01: under NEPA,
- 31:33SPEAKER_01: the process requirements?
- 31:34So I know that you did a podcast with Nick Bagley about Coast Chevron,
- 31:40right?
- 31:41SPEAKER_00: I was literally a law clerk at the D.C.
- 31:43SPEAKER_00: Circuit and a young lawyer when this is happening.
- 31:45SPEAKER_00: So NEPA passes in 1970.
- 31:46SPEAKER_00: The original Chevron decision is 1985.
- 31:49SPEAKER_00: So in the early years of NEPA,
- 31:51we don't know what the legal standard is under which a
- 31:54permitting decision by a
- 31:55SPEAKER_00: federal agency will be reviewed.
- 31:57Like,
- 31:57we don't know how much deference the courts are going to give
- 32:00to the permitting agency.
- 32:01SPEAKER_00: So we want belts and suspenders, right?
- 32:03SPEAKER_00: We want multiple bites of the apple.
- 32:05SPEAKER_00: We want to litigate under NEPA.
- 32:07SPEAKER_00: And then we want to litigate the permits, right?
- 32:10You could put together a system in which NEPA is just the
- 32:14foundation and then you
- 32:15SPEAKER_00: do the permits and those can get litigated.
- 32:17But I do think many of the advocates who are concerned about
- 32:22accountability by the
- 32:23agencies and adherence to environmental laws in a post-Chevron
- 32:27world are going to
- 32:28be really skeptical of that approach because they're worried
- 32:32that all the permits
- 32:33SPEAKER_00: will just be upheld.
- 32:34SPEAKER_00: Got it.
- 32:35I want to say something else about NEPA that I think we didn't
- 32:38know when it was
- 32:38SPEAKER_00: passed or even in the 80s.
- 32:40I speak as someone who literally wrote their third year paper
- 32:43for law school about NEPA.
- 32:44SPEAKER_00: So I've been thinking about this a long time.
- 32:46So in the world of people like Jen Palka and people who are
- 32:51thinking about,
- 32:52SPEAKER_00: you know,
- 32:52SPEAKER_00: abundance and stuff,
- 32:53SPEAKER_00: right?
- 32:54SPEAKER_00: We don't like waterfall decision making, right?
- 32:56SPEAKER_00: We like test and learn decision making.
- 32:58SPEAKER_00: We like the government to be able to sort of do a little bit,
- 33:01SPEAKER_00: learn something and then do a little bit more.
- 33:03SPEAKER_00: So NEPA is the ultimate waterfall, right?
- 33:06SPEAKER_00: Permitting is the ultimate waterfall.
- 33:07You literally have to do this whole multi-year process before
- 33:11you can do anything.
- 33:13And what that assumes is that the way you build big projects
- 33:16like the Big Dig or
- 33:17the Green Line Extension is that you literally know everything
- 33:21about the project
- 33:22SPEAKER_00: when you're doing NEPA.
- 33:23to the point where you can calculate exactly how many square
- 33:28feet of wetlands
- 33:29SPEAKER_00: you're going to impact or exactly how many square feet of parkland.
- 33:32SPEAKER_00: But every time you change the project,
- 33:36SPEAKER_00: let's say you change it because you discovered environmental impact,
- 33:39Or because your public engagement convinces you that you want
- 33:43to go this way
- 33:44SPEAKER_00: instead of that way.
- 33:45Every time you change it,
- 33:46it cascades and it changes all of the impacts,
- 33:50right?
- 33:50So if you just set aside like what NEPA is and you just asked
- 33:54yourself what a
- 33:55SPEAKER_00: rational process would look like,
- 33:57SPEAKER_00: right?
- 33:57SPEAKER_00: Right.
- 33:58SPEAKER_00: It would actually be iterative.
- 34:00SPEAKER_00: It wouldn't be waterfall, right?
- 34:02SPEAKER_00: You'd like start with a project.
- 34:03SPEAKER_00: You'd engage the public.
- 34:04SPEAKER_00: You'd start to look at the environmental impacts.
- 34:06SPEAKER_00: You'd start to think about the permitting requirements.
- 34:09SPEAKER_00: Then you'd make changes to the project,
- 34:10SPEAKER_00: which would in turn change your permitting,
- 34:13SPEAKER_00: change your impacts,
- 34:14SPEAKER_00: right?
- 34:15But that's okay because you're making those changes because the
- 34:17process actually
- 34:18SPEAKER_00: made you change things.
- 34:20SPEAKER_00: And this is where the P of procurement comes in.
- 34:22until two decades ago the way we built infrastructure there was
- 34:27one way you
- 34:28procured a team to build it for you it was called design bid
- 34:32build and what that
- 34:34meant is the agency who owned the road or the bridge or the
- 34:37transit they would
- 34:38design every asset doesn't matter how long they took that took
- 34:41them 25 years they
- 34:42would design it so specifically that it could then be permitted
- 34:45and go through nepa
- 34:46SPEAKER_00: and then they would write a procurement
- 34:48that said build exactly this this way and they'd find out what
- 34:52it costs by the way
- 34:53that would be the first time they actually knew what it really
- 34:55costs because now
- 34:56you have a real company telling you that you build it and then
- 34:59they would go out
- 35:00and they would build that exact project except of course they
- 35:02wouldn't because as
- 35:03soon as you started building it you'd bump into something you
- 35:05didn't know was there
- 35:06so in a design bid build world right you can do permitting and
- 35:10public engagement
- 35:10SPEAKER_00: and NEPA and everything else and you get to this 100% design but
- 35:14So one of the things that I think we've learned and that a lot
- 35:17of places in the
- 35:18SPEAKER_00: world have learned is that's a really stupid way to build a project,
- 35:21SPEAKER_00: right?
- 35:21That a better way to build the project is to actually engage
- 35:25the team that's going
- 35:26to help you build it earlier in the process and sort of do
- 35:29designing and public
- 35:30engagement and permitting iteratively and kind of design and
- 35:33maybe build the first
- 35:34SPEAKER_00: piece of it,
- 35:34SPEAKER_00: design and then build another piece of it,
- 35:37push off some other part that has a really complicated
- 35:39engineering problem and let
- 35:40SPEAKER_00: people work on it.
- 35:42SPEAKER_00: Well, in that world, how do you do waterfall permitting at all?
- 35:45You never get to the point where you know exactly how many
- 35:48square feet of wetlands
- 35:49SPEAKER_00: you impact until you've finished building.
- 35:52So all of this permit and public engagement and planning
- 35:55process actually grows out
- 35:59SPEAKER_00: of the assumption that at the end of the day,
- 36:01SPEAKER_00: when you're ready to finally build,
- 36:03SPEAKER_00: you're going to do this waterfall thing where you're
- 36:07SPEAKER_00: You're going to hand it to the industry and you're going to say,
- 36:09SPEAKER_00: okay,
- 36:09SPEAKER_00: industry,
- 36:10SPEAKER_00: tell me what it's going to cost me to build it.
- 36:12SPEAKER_00: But in fact, the best infrastructure projects being built in the U.S.
- 36:16and around the world right now are not being built,
- 36:19design,
- 36:19bid,
- 36:19build anymore.
- 36:21SPEAKER_00: But nobody has really taken that step backwards and said,
- 36:24SPEAKER_00: okay,
- 36:24SPEAKER_00: but in a world where we're actually,
- 36:26SPEAKER_00: even if we don't use these words...
- 36:28Trying to go from waterfall process to test and learn processes
- 36:33to incremental
- 36:34SPEAKER_00: processes to iterative processes,
- 36:36all of which I think all of us now have come to understand
- 36:39really are better for
- 36:40SPEAKER_00: delivering things.
- 36:42SPEAKER_00: Well,
- 36:42SPEAKER_00: now you have to ask,
- 36:43SPEAKER_00: OK,
- 36:43so then how should that change how we permit things and do
- 36:46public engagement and
- 36:47SPEAKER_00: plan things?
- 36:48If the thing that you're doing is not like a thing that at a
- 36:51moment in time is done,
- 36:52but is a thing that is iteratively being planned and designed
- 36:55and permitted and
- 36:56SPEAKER_00: thought about and engaged with the public right up until the date.
- 37:00Move us forward in time to the Green Line extension in which
- 37:04you're no longer
- 37:05SPEAKER_01: litigating these projects from the outside.
- 37:06SPEAKER_01: You're responsible for executing these projects.
- 37:09And again,
- 37:10imagine I'm from Arizona,
- 37:11got no special knowledge of Boston geography.
- 37:13SPEAKER_01: What is the Green Line extension?
- 37:14SPEAKER_01: And at what point do you come in to that whole project?
- 37:18SPEAKER_00: So the Green Line is a light rail line in Boston.
- 37:22SPEAKER_00: It's a subway line part of the time.
- 37:24SPEAKER_00: It's underground.
- 37:24And part of the time,
- 37:25it's a trolley that literally runs down the middle of streets.
- 37:28SPEAKER_00: And it ends just north of the Charles River.
- 37:31SPEAKER_00: So Boston is separated from the city of Cambridge by the Charles River.
- 37:34So the Green Line goes over the Charles River and has a couple
- 37:37stops and then it ends.
- 37:38SPEAKER_00: And it ends just before a city called Somerville, Massachusetts.
- 37:42To understand why the Green Line Extension matters so much,
- 37:44you have to understand Somerville.
- 37:45SPEAKER_00: So Somerville is a four square mile city with 80,000 residents.
- 37:51SPEAKER_00: It is one of the densest places in the Northeast United States.
- 37:54And it is almost certainly the densest place in the Northeast
- 37:56United States that
- 37:57SPEAKER_00: has no transit except buses.
- 37:59SPEAKER_00: And they have been trying to get transit forever.
- 38:02SPEAKER_00: And the idea of the Green Line extension,
- 38:04SPEAKER_00: and this is true for a lot of infrastructure projects,
- 38:06SPEAKER_00: it seems really simple.
- 38:08There is a commuter rail line from the north shore of Boston
- 38:12that runs through the
- 38:13city of Somerville on tracks that are already owned by the MBTA
- 38:18without stopping.
- 38:20SPEAKER_00: So you're Somerville,
- 38:21SPEAKER_00: you have terrible transit,
- 38:22SPEAKER_00: you have these buses,
- 38:23and you watch these commuter trains full of people from distant
- 38:26suburbs going
- 38:27SPEAKER_00: through your city.
- 38:28SPEAKER_00: By the way,
- 38:29SPEAKER_00: they're diesel trains,
- 38:30SPEAKER_00: so they are spewing diesel exhaust into your city,
- 38:33SPEAKER_00: and you get no service.
- 38:34SPEAKER_01: And you're one of the densest places around for hundreds of miles.
- 38:38SPEAKER_00: And clearly you can support transit use.
- 38:41SPEAKER_00: You're denser than other places in Boston that have transit, right?
- 38:45SPEAKER_00: So someone asked the logical question,
- 38:47SPEAKER_00: well,
- 38:47SPEAKER_00: what if where the green line currently ends,
- 38:49SPEAKER_00: it ends at a station called Lechmere?
- 38:50SPEAKER_00: You can see the commuter rail tracks from Lechmere.
- 38:53SPEAKER_00: Like there's a road in between them, but like...
- 38:56SPEAKER_00: This is a engineering.
- 38:57SPEAKER_00: This is soluble, right?
- 38:58SPEAKER_00: You either move the road or you move the tracks,
- 39:00SPEAKER_00: but you move something and then boom,
- 39:02SPEAKER_00: the green line hits this existing commuter rail line.
- 39:05SPEAKER_00: You run a second set of tracks next to this existing commuter rail line.
- 39:09SPEAKER_00: Boom.
- 39:10SPEAKER_00: You now have six new stations in the city of Somerville.
- 39:13And instead of 20% of the city of Somerville being in walking
- 39:16distance of a stop,
- 39:18SPEAKER_00: 80% of the city of Somerville is in walking distance.
- 39:21And since housing is another issue that I know you and I both
- 39:24share an interest in,
- 39:25I will tell you that one of the reasons that the Green Line
- 39:27Extension becomes such
- 39:29SPEAKER_00: an important project that it's worth saving when we need to save it is,
- 39:33SPEAKER_00: to their credit,
- 39:34SPEAKER_00: the city of Somerville completely replanned and rezoned itself to buy.
- 39:40Bring in denser and often housing development in its new six
- 39:44station areas,
- 39:45right?
- 39:45SPEAKER_00: It actually took a 15 acre site, brought in a master plan.
- 39:49SPEAKER_00: Like this wasn't hypothetical.
- 39:50This wasn't zoning on the ground that allows for hundreds of
- 39:52housing units.
- 39:53SPEAKER_00: This went beyond that.
- 39:55SPEAKER_00: So the Green Line Extension starts as this is a really easy project.
- 39:58SPEAKER_01: It's a no brainer.
- 39:59SPEAKER_00: It's a no-brainer.
- 40:00SPEAKER_00: It's going to cost a few hundred million dollars,
- 40:02SPEAKER_00: but the big dig is going to cost a few billions.
- 40:04SPEAKER_00: So you just sort of attach them together and you go.
- 40:06SPEAKER_00: Well, that would work except for one thing.
- 40:09SPEAKER_00: If you think about train tracks or a road going through a busy city,
- 40:13it probably occurs to you that people are probably not crossing
- 40:16those train tracks
- 40:17SPEAKER_00: every day.
- 40:18You're building bridges over the train tracks so that you can
- 40:21get over it if you're
- 40:22SPEAKER_00: in a car or on foot or on a bike.
- 40:23SPEAKER_00: Right?
- 40:24SPEAKER_00: So you build those bridges.
- 40:26SPEAKER_00: Bridges have things underneath them that hold them up.
- 40:29SPEAKER_00: They're called abutments.
- 40:30SPEAKER_00: Where do you put the abutments?
- 40:31SPEAKER_00: You put them right next to the train tracks.
- 40:33SPEAKER_00: You don't leave enough room to put a second set of train tracks.
- 40:37Because if you put the train tracks next to it,
- 40:39there's literally a bridge abutment there.
- 40:41SPEAKER_00: Not just one.
- 40:42SPEAKER_00: Not two.
- 40:43SPEAKER_00: Eight.
- 40:44SPEAKER_00: Eight bridges...
- 40:45SPEAKER_00: have to be completely rebuilt.
- 40:48SPEAKER_00: Somehow, this is never part of the conversation.
- 40:51SPEAKER_00: It's not part of the cost estimate.
- 40:52SPEAKER_00: It was literally the conversation starts as lay down the tracks.
- 40:56SPEAKER_01: I mean, just back up for a second.
- 40:57SPEAKER_01: I know there's a lot to talk about here,
- 40:58but how is it that you have a bunch of smart people in a room
- 41:01thinking about
- 41:02SPEAKER_01: transit and nobody thinks about this?
- 41:04SPEAKER_01: What happens there?
- 41:06SPEAKER_00: I mean, I'm sure somebody thought about it, right?
- 41:08SPEAKER_00: But the public image of this is a no-brainer.
- 41:11SPEAKER_00: We're going to put one set of tracks next to a second set of tracks.
- 41:13SPEAKER_00: And they didn't think about friendship downturns.
- 41:15SPEAKER_00: And also the other question is this.
- 41:16SPEAKER_00: So Somerville's up here.
- 41:18SPEAKER_00: Train tracks are down here.
- 41:19SPEAKER_00: If the commuter rail is running through your city and it doesn't stop,
- 41:22SPEAKER_00: then there's a thing you don't need.
- 41:23SPEAKER_00: Somewhere to get on the train.
- 41:25SPEAKER_00: A station.
- 41:25You're going to build rapid transit and you want to have six
- 41:28stations along a less
- 41:29than five mile route because the whole point is to get
- 41:32everybody in walking
- 41:33SPEAKER_00: distance of a station,
- 41:34SPEAKER_00: right?
- 41:35Where does the station go when the tracks are down here and the
- 41:38world is up here?
- 41:39SPEAKER_00: Do you need elevator?
- 41:40SPEAKER_00: Like, you know, and people in wheelchairs and people with strollers.
- 41:43So one of the reasons I told you that projects cost a lot more
- 41:48is they never were
- 41:49SPEAKER_00: going to cost what people said at the beginning.
- 41:51SPEAKER_00: This project was never going to cost less than a billion dollars.
- 41:55SPEAKER_00: The problem was people spent many years,
- 41:57SPEAKER_00: and we'll fast forward,
- 41:59SPEAKER_00: and in 2014 and 15,
- 42:01SPEAKER_00: people really thought they knew what it was going to cost.
- 42:03SPEAKER_00: It had gone through the...
- 42:04SPEAKER_00: NEPA process.
- 42:05SPEAKER_00: It had gone through the Federal Transit Administration's process.
- 42:08SPEAKER_00: It had gotten its grant.
- 42:10You go through this huge process to figure out what a project
- 42:12costs before you can
- 42:13SPEAKER_00: get a grant from FTA.
- 42:15SPEAKER_00: FTA say it's going to cost $1.9 billion.
- 42:16SPEAKER_00: We're going to give you half of that.
- 42:19SPEAKER_00: The state of Massachusetts is going to pay for half of that.
- 42:21SPEAKER_00: They signed this agreement in January of 2015.
- 42:23SPEAKER_00: This is a project that's been in permitting,
- 42:26SPEAKER_00: planning,
- 42:26SPEAKER_00: and public engagement since 1990,
- 42:28SPEAKER_00: but 15 years in,
- 42:28SPEAKER_00: you're ready to go.
- 42:31SPEAKER_00: It is ready to go.
- 42:33And they use this new procurement method that has never been
- 42:37used before in Massachusetts,
- 42:38SPEAKER_00: probably without really understanding it.
- 42:41And it's a procurement method where you basically pick the
- 42:44person who's going to
- 42:45SPEAKER_00: build your project.
- 42:46And then you let them tell you how much each subsequent
- 42:49contract is going to cost.
- 42:50SPEAKER_00: So you don't put the contract out and let five people bid on it.
- 42:53SPEAKER_00: You pick the team and then you say, what's this going to cost?
- 42:56There's a whole bunch of other fancy parts around it,
- 42:58but that's the basics.
- 43:00SPEAKER_01: Now, why would you do that?
- 43:02Because it moves faster and because all major infrastructure
- 43:06projects occur in the
- 43:07SPEAKER_00: real world with real politics.
- 43:10And Deval Patrick is the governor of Massachusetts and Barack
- 43:13Obama is the
- 43:14SPEAKER_00: president of the United States,
- 43:16SPEAKER_00: except for that Donald Trump is running against Barack Obama and a strong
- 43:20SPEAKER_00: Republican is running against Deval Patrick.
- 43:23So the project is being designed so that there can be what's
- 43:28called a full funding
- 43:29SPEAKER_00: grant agreement,
- 43:29the legally binding agreement in which federal transit promises
- 43:32you your billion
- 43:33SPEAKER_00: dollars while Barack Obama is president and Deval Patrick is governor.
- 43:38SPEAKER_00: And when they work backwards from that date,
- 43:40they come to the conclusion this particular procurement method
- 43:44will get you there
- 43:46SPEAKER_00: and no other procurement method will.
- 43:49SPEAKER_01: Just to make sure I'm hearing you correctly,
- 43:51the political goal is get the contract done and move the money
- 43:55before we get any
- 43:56SPEAKER_01: major changes in administration,
- 43:58SPEAKER_01: either the state or at the federal level.
- 44:00SPEAKER_00: Get it paid for.
- 44:01SPEAKER_00: Because remember,
- 44:02I told you at the beginning that one of the things that kills
- 44:05projects is that at
- 44:05SPEAKER_00: the beginning,
- 44:06SPEAKER_00: you don't know where all the money is coming from.
- 44:08SPEAKER_00: So actually,
- 44:09it's not a bad idea to institute a process by which your goal
- 44:15is to have all the
- 44:17SPEAKER_00: money at the beginning,
- 44:18SPEAKER_00: right?
- 44:19SPEAKER_00: Like that actually is a good thing.
- 44:21There's this little political window in which you could have
- 44:24all $2 billion that
- 44:25SPEAKER_00: you need to build a project,
- 44:27SPEAKER_00: like from the get-go.
- 44:29SPEAKER_01: So we have to move fast.
- 44:30But it requires you to sort of do procurement in a way you've
- 44:33never done it before.
- 44:35And what are the consequences in this case of doing procurement
- 44:38that different way?
- 44:40SPEAKER_00: So the consequences are that they start to give small contracts,
- 44:44mostly for design or some early work to this consortium that
- 44:47they've hired.
- 44:48SPEAKER_00: The first project costs way more than they thought it would.
- 44:51SPEAKER_00: The second one does.
- 44:52SPEAKER_00: The third one does.
- 44:53SPEAKER_00: The fourth one does.
- 44:55SPEAKER_00: And the fifth one does.
- 44:56SPEAKER_00: And then Deval Patrick leaves office and Charlie Baker comes in.
- 44:59SPEAKER_00: The next package comes in and it's the first big construction package.
- 45:03SPEAKER_00: It's to rebuild one station,
- 45:05the one you have to move to connect the green line to the
- 45:07commuter rail line.
- 45:09SPEAKER_00: and to build the first two stations.
- 45:11SPEAKER_00: And it comes in wildly above.
- 45:15SPEAKER_01: Wildly meaning what?
- 45:16SPEAKER_00: What it's supposed to,
- 45:17meaning that what we thought was a $2.2 billion project becomes
- 45:21a $3 billion project.
- 45:22And that's assuming that the next package and the one after
- 45:25that and the one after that.
- 45:27SPEAKER_00: And I'm secretary and the governor is the governor and it's 2015.
- 45:31SPEAKER_00: And earlier that year in the wintertime,
- 45:34we had four blizzards in a row and 114 inches of snow and the
- 45:38tea literally closed
- 45:40SPEAKER_00: in the middle of a day.
- 45:42SPEAKER_01: Snowpocalypse.
- 45:44SPEAKER_00: It's no apocalypse.
- 45:45The general manager quits the legislature with the governor's
- 45:48strong approval,
- 45:49puts the T under a control board like this is like New York
- 45:53City in the 1970s.
- 45:55SPEAKER_00: And you got to go to the control board and tell them,
- 45:58SPEAKER_00: oh,
- 45:58SPEAKER_00: and the other thing you need to know is the federal money is fixed.
- 46:01SPEAKER_00: You get a billion towards your two billion dollar project.
- 46:03You also get a billion towards your three billion dollar
- 46:06project or four billion dollar project.
- 46:08All the cost overruns are on the tea,
- 46:10but the tea doesn't have the money.
- 46:11SPEAKER_00: And even if the tea has the money,
- 46:13SPEAKER_00: it is a valid question for the governor and the control board to ask,
- 46:17would you spend it on the Green Line extension or would you fix
- 46:21all the things that
- 46:21SPEAKER_00: we have discovered are wrong with the tea as the result of snowpocalypse?
- 46:24SPEAKER_00: So it is the summer of 2015.
- 46:26This is when it becomes impossible to ignore that this project
- 46:33does not cost what
- 46:34we thought it was going to cost and the feds are not going to
- 46:36give us any more money.
- 46:37SPEAKER_00: At that point,
- 46:38SPEAKER_00: the Federal Trends Administration actually says,
- 46:40we're going to freeze the money we did give you because we want
- 46:42to understand what
- 46:44SPEAKER_00: the heck is going on here.
- 46:45SPEAKER_01: Let me just jump in and ask your secretary of the State Department of
- 46:49SPEAKER_01: Transportation at this point.
- 46:51SPEAKER_01: Who are the different voices in your ear,
- 46:52the different pressures that you have on this question of do we
- 46:56stick the money in
- 46:56SPEAKER_01: the tea?
- 46:57SPEAKER_01: Do we take some other route?
- 46:58SPEAKER_01: What kinds of pressures are you under at this point?
- 47:01SPEAKER_00: This is a project I know well, sued over 10 years earlier.
- 47:03SPEAKER_00: It's also a project that I believe in because before I become secretary,
- 47:08SPEAKER_00: I'm doing a ton of work on getting housing built near transit.
- 47:11SPEAKER_00: And I know what Somerville has done.
- 47:13SPEAKER_00: And I know that the belief is that this project will support
- 47:17SPEAKER_00: 10,000 new housing projects, 45,000 new riders.
- 47:19SPEAKER_00: Like, I want to build this project.
- 47:21SPEAKER_00: This is what you need to convince.
- 47:22SPEAKER_00: You need to convince the governor.
- 47:24SPEAKER_00: This is going to be state money.
- 47:25You need to convince the control board that of all the things
- 47:28that are facing them,
- 47:30that they're going to peel off hundreds of millions that they
- 47:32weren't planning on spending,
- 47:33and they're going to put it into this and not all the other
- 47:35things that are wrong
- 47:35SPEAKER_00: that they're discovering at the T.
- 47:37You need to convince the local elected officials in Cambridge
- 47:40and Somerville who
- 47:40are expecting the project to be the project that they have been
- 47:43promised for 25 years.
- 47:45SPEAKER_00: Actually need to convince the legislature because at the end of the day,
- 47:48most of the new money is going to come in the form of state
- 47:50bonds or some other
- 47:52SPEAKER_00: form of state money.
- 47:52SPEAKER_00: Feds are not going to give you any more money.
- 47:55And you actually need to convince the Federal Transit
- 47:58Administration that it's
- 48:00SPEAKER_00: close enough to the project.
- 48:02SPEAKER_00: that they approved because there is a new president.
- 48:06SPEAKER_00: And if they want to freeze the grants,
- 48:08SPEAKER_00: something that we didn't think about as much in 2015,
- 48:12SPEAKER_00: they actually legitimately can.
- 48:14SPEAKER_00: Because say we said, we're not going to build seven stations.
- 48:16SPEAKER_00: We're just going to build the first three.
- 48:17SPEAKER_00: That's how we're going to save the money.
- 48:19They could say,
- 48:20well,
- 48:20I didn't give you a billion dollars to build three stations.
- 48:22SPEAKER_00: I gave you a billion dollars to build seven.
- 48:24SPEAKER_00: You don't get the billion.
- 48:25SPEAKER_00: So we had to keep the billion, right?
- 48:27SPEAKER_00: Keep the billion.
- 48:28SPEAKER_00: We hadn't stayed money.
- 48:30SPEAKER_00: and figure out how to build the rest of the project.
- 48:36SPEAKER_01: Okay.
- 48:36SPEAKER_01: That's great context.
- 48:37SPEAKER_01: So you're in this position.
- 48:38SPEAKER_01: You've got a lot of cross pressures, a lot of stakeholders.
- 48:42SPEAKER_01: What do you do?
- 48:43SPEAKER_00: For me,
- 48:44SPEAKER_00: this is where the whole,
- 48:46what does project development look like when you do it fast
- 48:48instead of slow?
- 48:49SPEAKER_00: Because I also know that time is not on our side at this point, right?
- 48:53We either have to sort this out,
- 48:55have a new project and get going again,
- 48:57right?
- 48:58SPEAKER_00: Or governor's going to say no.
- 49:00SPEAKER_01: Or they wouldn't come to the table.
- 49:01SPEAKER_00: Building it is on the table, but we got to get past all these barriers.
- 49:05SPEAKER_00: But canceling it is also on the table, right?
- 49:07SPEAKER_00: That was one of the things.
- 49:09SPEAKER_00: I honestly believe if he had not said canceling is on the table,
- 49:12SPEAKER_00: would have never gotten the political alignment.
- 49:14SPEAKER_00: People had to believe that there was a real risk.
- 49:16SPEAKER_00: We also did not have an infinite amount of time.
- 49:19SPEAKER_00: This becomes, how do you take everything you know and say the following?
- 49:23SPEAKER_00: Six months from now, I would actually like a go-no-go decision.
- 49:27SPEAKER_00: Six months from now.
- 49:28SPEAKER_00: And that means permitted planning,
- 49:31SPEAKER_00: public engagement and procurement all have to happen from where we are,
- 49:36SPEAKER_00: which is we have a $3 million project we can't afford,
- 49:38having a new project six months later in which we have an
- 49:42answer to planning.
- 49:44SPEAKER_00: Do we need a vote of the city council?
- 49:45SPEAKER_00: Do we need new permits?
- 49:46SPEAKER_00: Do we need new dollars?
- 49:48SPEAKER_00: Do we need a new procurement?
- 49:49SPEAKER_00: This is where you can't do waterfall comes in.
- 49:52SPEAKER_00: I mean, in fact, it was sort of easier for me internally in some ways.
- 49:56SPEAKER_00: It's like people say all the time,
- 49:58SPEAKER_00: you know,
- 49:58SPEAKER_00: when when I-95 burns down in Philadelphia,
- 50:01isn't it amazing that like overnight we can do something that
- 50:04we can't do?
- 50:05Or I-40,
- 50:05Secretary Duffy just said this about Interstate 40 in North Carolina.
- 50:09SPEAKER_00: This is a different kind of emergency, but it's the same thing, right?
- 50:13SPEAKER_00: It's like you just have to throw out the way you do things,
- 50:16SPEAKER_00: the business as usual,
- 50:17SPEAKER_00: inside your own agencies and say,
- 50:20SPEAKER_00: we're not going to do it that way.
- 50:21SPEAKER_00: We are going to literally simultaneously process this.
- 50:25SPEAKER_00: So we needed a different project team.
- 50:27SPEAKER_00: I didn't believe anything anyone said.
- 50:29SPEAKER_00: I didn't believe the engineers.
- 50:30SPEAKER_00: I didn't believe the cost estimators.
- 50:31SPEAKER_00: The governor wouldn't.
- 50:32SPEAKER_00: The control board wouldn't.
- 50:33SPEAKER_00: The legislature wouldn't.
- 50:35SPEAKER_00: They had been so wrong for so long, right?
- 50:37SPEAKER_00: Right.
- 50:37SPEAKER_00: I need a new team.
- 50:39SPEAKER_00: We hired the new team in January.
- 50:41SPEAKER_00: Like we announced this in August.
- 50:43SPEAKER_00: We hired the team in January.
- 50:44SPEAKER_00: We promised people an answer by May.
- 50:46SPEAKER_00: You have to do procurement differently to do that.
- 50:48We actually fired all of the old teams so that we were in a
- 50:51position to do a new procurement.
- 50:54And we re-engineered the project and we figured out the
- 50:57procurement strategy and we
- 50:58SPEAKER_00: figured out the finance,
- 50:59SPEAKER_00: like all of it.
- 51:00SPEAKER_00: Basically between December of 2015 and May of 2016.
- 51:06SPEAKER_01: Tell me about the redesigns.
- 51:08SPEAKER_01: What changes about the actual project?
- 51:11SPEAKER_00: So I live on the other end of the Green Line.
- 51:14SPEAKER_00: I live on the western end of the Green Line.
- 51:16When you walk to a Green Line station in my town,
- 51:18it's like walking to a slab of asphalt.
- 51:20SPEAKER_00: There's no station.
- 51:21SPEAKER_00: There's no fair gate.
- 51:22SPEAKER_00: There's no heat.
- 51:23SPEAKER_00: There's no rain.
- 51:25SPEAKER_01: And you just stand there and wait for the train to come.
- 51:27SPEAKER_00: It's like a slab of asphalt.
- 51:29They have designed beautiful stations,
- 51:3150,
- 51:3260,
- 51:34$70 million stations,
- 51:33okay?
- 51:34SPEAKER_00: If the stations cost 5 million instead of 50 million a piece,
- 51:37SPEAKER_00: and there are six of them like that,
- 51:38SPEAKER_00: it's hundreds of millions.
- 51:40SPEAKER_00: You know what I mean?
- 51:40SPEAKER_00: It's pretty easy math, right?
- 51:42SPEAKER_00: So people ride transit.
- 51:43SPEAKER_00: They ride transit because it's frequent and reliable.
- 51:45SPEAKER_00: It's not frequent and reliable.
- 51:47SPEAKER_00: They don't ride it.
- 51:48SPEAKER_01: Doesn't matter how nice the station is if it's not frequently reliable.
- 51:51SPEAKER_00: Exactly.
- 51:52SPEAKER_00: So what do you hold constant?
- 51:54And I think this was critical because you have to know what
- 51:56you're aiming at.
- 51:57The faster you're making a decision,
- 51:58the more you're compressing a process.
- 52:01SPEAKER_00: The key is everybody who's working on this knows what are you aiming.
- 52:04SPEAKER_00: And so we said two things.
- 52:06SPEAKER_00: It's got to cost hundreds of millions of dollars less.
- 52:08SPEAKER_00: Like we didn't give a cost,
- 52:09SPEAKER_00: but it wasn't like,
- 52:10SPEAKER_00: oh,
- 52:10SPEAKER_00: if you save 3%,
- 52:11SPEAKER_00: then we're going to clap and go ask the legislature for the money.
- 52:14SPEAKER_00: So you have to shave hundreds of million dollars of office.
- 52:17SPEAKER_00: And two is same amount of service.
- 52:19SPEAKER_00: Can't eliminate a station.
- 52:21Can't eliminate the purchase of the 24 new cars because you
- 52:24need them to run the
- 52:25SPEAKER_00: trains frequently left.
- 52:26SPEAKER_00: Like we're going to hold some things constant.
- 52:28And in a funny way,
- 52:29that means that the team and the public and the elected
- 52:31officials can focus.
- 52:33SPEAKER_01: It's not that hard to figure out where you have to cut.
- 52:36SPEAKER_00: I mean, it's not easy, but it's a lot easier.
- 52:38But it's one of the lessons is that you got to tell them what
- 52:41you're aiming at.
- 52:42SPEAKER_00: And what we were aiming at is same amount of service, less money.
- 52:46SPEAKER_00: Can we cut money?
- 52:47SPEAKER_00: Where can we cut?
- 52:48SPEAKER_00: Project costs.
- 52:49SPEAKER_00: The other thing I want to talk about for one minute is risk.
- 52:51SPEAKER_00: Project delivery is risk management.
- 52:54SPEAKER_00: But many project delivery teams are not about reducing risks.
- 52:59SPEAKER_00: They're actually about playing a game of hot potato with risks.
- 53:03SPEAKER_00: You take it.
- 53:03SPEAKER_00: No, you take it.
- 53:04SPEAKER_00: No, you take it.
- 53:05SPEAKER_00: You don't fix anything by doing that.
- 53:07It's just who gets stuck holding the hot potato when the risk
- 53:10blows up,
- 53:11right?
- 53:11SPEAKER_00: Like who eats the cost overrun?
- 53:14SPEAKER_00: Who gets the political egg?
- 53:16SPEAKER_01: Will you explain that a little bit more?
- 53:17SPEAKER_01: Like when you say that they're playing hot potato with risk,
- 53:20SPEAKER_00: So you hire somebody to build your project and they say,
- 53:24SPEAKER_00: well,
- 53:24SPEAKER_00: I'm going to build your project for $2.3 billion.
- 53:26SPEAKER_00: And then they start to build it and they say,
- 53:29SPEAKER_00: oops,
- 53:30SPEAKER_00: actually,
- 53:30SPEAKER_00: I'm going to build your project for $2.7 billion.
- 53:32SPEAKER_00: Maybe you can do that the first time you're building a project,
- 53:34SPEAKER_00: but we're now in the second time through.
- 53:36SPEAKER_00: Can't do that.
- 53:37So one of the things that we do during this period of time when
- 53:40we're resetting it
- 53:41SPEAKER_00: is we actually asked ourselves,
- 53:43SPEAKER_00: what are the biggest risks with the project?
- 53:45SPEAKER_00: And which ones could we actually fix before we put it out for bid again?
- 53:51So one of the biggest risks is you have to build it right next
- 53:53to an operating
- 53:54SPEAKER_00: commuter rail line.
- 53:55SPEAKER_00: We operate the commuter rail line and we own the tracks.
- 53:59SPEAKER_00: Those tracks need to be moved over a little to make room for it.
- 54:02We could do that,
- 54:04not put it in the contract for the new guy who's building it.
- 54:08SPEAKER_00: And then when they bid the new project,
- 54:11SPEAKER_00: The risk that when they go to move the tracks,
- 54:14they're not going to be able to do it or they're not going to
- 54:15be given permission
- 54:16because it's a busy time of year or the Patriots won the Super
- 54:19Bowl and we need to
- 54:20SPEAKER_00: have a parade.
- 54:21SPEAKER_00: And so we're not going to close the commuter rail down to move it.
- 54:24SPEAKER_00: People tend to sort of just try to keep risk constant.
- 54:27SPEAKER_00: And they do one of two things.
- 54:28They just try to turf it off onto other people or they build in
- 54:31what's called contingency.
- 54:33You just say in the budget,
- 54:34well,
- 54:34we'll just sort of throw $300 million in the budget.
- 54:37SPEAKER_00: If something bad happens, it's already in the budget.
- 54:40SPEAKER_00: So it doesn't make the budget go up.
- 54:41SPEAKER_00: The problem with that,
- 54:42SPEAKER_00: and the T have done that on the Green Line extension,
- 54:45SPEAKER_00: and I don't mean to speak ill of the engineering world,
- 54:47SPEAKER_00: but I have to say that I believe this is true.
- 54:50SPEAKER_00: If there's this big pot of hundreds of millions of dollars in the budget,
- 54:54you will find a way to make the case that you should be given
- 54:58that money to do the
- 54:59SPEAKER_00: work you're doing.
- 55:00SPEAKER_01: It's staring you in the face?
- 55:02SPEAKER_00: Yes.
- 55:02SPEAKER_00: FTA,
- 55:03SPEAKER_00: actually,
- 55:03its process of thinking about risk involves increasing the
- 55:07amount of contingency
- 55:08SPEAKER_00: for these big transit projects.
- 55:10SPEAKER_00: And I have come to the conclusion that that,
- 55:12SPEAKER_00: while well-intentioned,
- 55:13SPEAKER_00: is not actually de-risking any of these projects.
- 55:16SPEAKER_00: It's just creating a giant bullseye for the building.
- 55:20So we wanted a smaller contingency that was very,
- 55:24very tightly controlled.
- 55:26SPEAKER_00: And another place we save money is contingency.
- 55:29SPEAKER_00: We just said, we're really going to build it.
- 55:31SPEAKER_01: And you gave yourself less rope.
- 55:34SPEAKER_00: Because you hurt yourself when you give yourself too much rope.
- 55:37SPEAKER_00: And that is part of the story.
- 55:39SPEAKER_00: So long story short, so we fire the old contractors.
- 55:42SPEAKER_00: We hire a new team.
- 55:43SPEAKER_00: We go through a public process.
- 55:44SPEAKER_00: And we save money basically through much less elaborate stations,
- 55:49SPEAKER_00: downsizing the maintenance facility a bit.
- 55:51SPEAKER_00: But we keep the 24 trains.
- 55:53SPEAKER_00: We keep all seven stations.
- 55:55We cut the contingency and sort of design a different kind of
- 55:58procurement that risks.
- 56:00And then we start taking state dollars and doing work while
- 56:04we're doing this other
- 56:05process so that the contract we will eventually put out and
- 56:08sign in November of
- 56:10SPEAKER_00: 2017 isn't actually the same contract because work has been done.
- 56:14And the work has been chosen to make it less risky so that when
- 56:18we put it out to bid,
- 56:20The world that's going to come through the door in
- 56:21Massachusetts and bid is going
- 56:23SPEAKER_00: to say,
- 56:23SPEAKER_00: they call it bidding in risk.
- 56:25SPEAKER_00: This is what the big company.
- 56:26SPEAKER_00: So we do a lot of things.
- 56:28I spend an immense amount of time with the mayor of Somerville
- 56:31and the mayor of Cambridge,
- 56:32SPEAKER_00: including convincing them to kick in some money.
- 56:34And what the control board does in the end is they set a not to
- 56:38exceed price.
- 56:38SPEAKER_00: They say, we will vote to put it back out to bid.
- 56:41But if the bid comes in over this number,
- 56:43we're telling you right now,
- 56:45we're not approving it.
- 56:46SPEAKER_00: And this tells the world, don't even bother to prepare a bid back.
- 56:50SPEAKER_00: catch.
- 56:50And then the one other controversial thing I'll mention briefly
- 56:53is there was a
- 56:54really beautiful community path for walking and biking that
- 56:57paralleled the entire
- 56:58SPEAKER_00: Green Line extension.
- 56:59SPEAKER_00: And to some extent, you could say it was all one project.
- 57:02SPEAKER_00: It was a transit walking and biking project.
- 57:04SPEAKER_00: And to some extent,
- 57:04SPEAKER_00: you could say,
- 57:05SPEAKER_00: no,
- 57:05it's a transit project and they belonged to this walking and
- 57:07biking project.
- 57:09And the place where we got in the most trouble was there were
- 57:12places where there
- 57:13was enough room for the green line and there was not enough
- 57:15room for the bike path.
- 57:16So it turned into an extremely expensive bike path because you
- 57:19had to sort of add a
- 57:21SPEAKER_00: lot of stuff to get the bike path to work.
- 57:24SPEAKER_01: Like bridges or you had to bump it out horizontally.
- 57:27SPEAKER_01: Yeah.
- 57:27SPEAKER_00: Yeah, moving transformers out of the way, like really expensive things.
- 57:32And so I think probably the thing that got me the most grief
- 57:35was when we said we
- 57:36SPEAKER_00: are willing to build it with a non-continuous bike path.
- 57:39SPEAKER_00: We're not going to take it all out.
- 57:40We're just going to take the really expensive parts out and
- 57:43they'll be on city streets.
- 57:44SPEAKER_00: I mean, people do bike on city streets.
- 57:46SPEAKER_00: I do.
- 57:47SPEAKER_00: People hated it.
- 57:48SPEAKER_00: So this is where the obsession with procurement actually served us well.
- 57:52SPEAKER_00: We came up with the following idea.
- 57:53Well,
- 57:54we're going to bid it out and we already know what the highest
- 57:56price is going to be.
- 57:57It's going to be $1 below what the control board said they were
- 57:59willing to bid.
- 58:00SPEAKER_00: So we set up the competition very differently.
- 58:03SPEAKER_00: It's not low bidder.
- 58:04SPEAKER_00: It's a much more complicated thing.
- 58:05SPEAKER_00: It allows us to sort of pick a team we like.
- 58:07But we also say there are four things that we ourselves could
- 58:11not figure out how to pay for.
- 58:12SPEAKER_00: the most important of which is this community path.
- 58:14The bidder who can figure out the most of those four things and
- 58:18still come out
- 58:19SPEAKER_00: below the price wins.
- 58:21SPEAKER_00: And the winning team figured out how to pay for all four,
- 58:25SPEAKER_00: including the community path,
- 58:26SPEAKER_00: for less than the amount that the control board said they would pay.
- 58:30Because we let the private sector figure out the solution
- 58:34instead of trying to
- 58:35SPEAKER_00: design it to 100% and then asking the question what it would cost.
- 58:39This is where culture comes in,
- 58:40which I'm sure you talk about a lot on your show.
- 58:42SPEAKER_00: This is like against every, every ounce of culture inside the MBTA.
- 58:47Like you do not just go to the world and say,
- 58:50world,
- 58:50tell us how you would do this project.
- 58:52SPEAKER_00: Like you tell the world, we're the MBTA and we know more than anybody.
- 58:55SPEAKER_00: We're telling you what needs to be built down to every last detail.
- 59:00SPEAKER_00: This is culturally painful.
- 59:04SPEAKER_01: It's not in the DNA.
- 59:06SPEAKER_00: It is so not in the DNA.
- 59:07SPEAKER_00: It got us a $2.3 billion project,
- 59:10SPEAKER_00: which at the end of the day ended up being more than the 2.1,
- 59:13SPEAKER_00: but not by so much that we couldn't live with it.
- 59:16SPEAKER_00: And it's pretty much what the project came in at when it was done.
- 59:20SPEAKER_01: Stephanie,
- 59:20I had big dreams of asking you all about the Federal Transit
- 59:23Administration and
- 59:24SPEAKER_01: your time there.
- 59:25Instead,
- 59:25I've gotten sucked into a very interesting story about state
- 59:28and local transit.
- 59:30I'm curious,
- 59:30what lessons did you take from the Green Line extension into
- 59:34your role?
- 59:35What did you learn about the kind of broad principles of
- 59:37procurement or about
- 59:39managing these stakeholders that applied when you were in a
- 59:42different kind of
- 59:43SPEAKER_01: transportation role at the federal level?
- 59:45SPEAKER_00: It's a great question.
- 59:46SPEAKER_00: And I say this, I did not run the Federal Transit Administration.
- 59:49SPEAKER_00: I had a colleague who ran the Federal Transit Administration.
- 59:52Secretary Buttigieg ran USDOT as a team,
- 59:54and we often worked with each other.
- 59:56SPEAKER_00: So on very important projects like the Hudson River Tuttle,
- 59:59SPEAKER_00: Federal Highway and Federal Railroad and Federal Transit,
- 1:00:02we're in the room together working towards and actually the
- 1:00:04Build America Bureau,
- 1:00:05SPEAKER_00: which does loans.
- 1:00:07We were all a team and the team's job was to make sure that
- 1:00:10that project was going
- 1:00:11SPEAKER_00: to be funded and locked up in construction when the first term ended.
- 1:00:15SPEAKER_00: And in fact, it was.
- 1:00:17But I would say this,
- 1:00:18the federal rules create the path that you have to follow.
- 1:00:21SPEAKER_00: And this is true for federal highway and for federal transit,
- 1:00:24SPEAKER_00: which is why I'm comfortable saying it.
- 1:00:26SPEAKER_00: I think it's the wrong path.
- 1:00:28SPEAKER_00: Like many processes that we come to understand are dysfunctional,
- 1:00:32SPEAKER_00: it is very waterfall,
- 1:00:33SPEAKER_00: it is very sequential,
- 1:00:35SPEAKER_00: and it forces the project sponsors,
- 1:00:38SPEAKER_00: the people who are actually building these projects,
- 1:00:39SPEAKER_00: to follow this set of rules that,
- 1:00:42SPEAKER_00: in fact,
- 1:00:43SPEAKER_00: I think undermine good project management.
- 1:00:46SPEAKER_00: So, for example...
- 1:00:48One of the things I learned from the Green Line extension is
- 1:00:50that the most
- 1:00:51SPEAKER_00: important thing to do to a project is not to value engineer it.
- 1:00:54SPEAKER_00: Value engineering is just like spending less money and you get less.
- 1:00:57SPEAKER_00: It's doing less with less.
- 1:00:59SPEAKER_01: I don't know what value engineering means.
- 1:01:01SPEAKER_01: Tell me.
- 1:01:02Value engineering is what the engineers cost when you say,
- 1:01:04oh,
- 1:01:05it's $2.3 million.
- 1:01:06SPEAKER_00: I only have to find $300 million and take it away.
- 1:01:09That's called value engineering because you're engineering to a value,
- 1:01:12right?
- 1:01:13SPEAKER_00: But what happens is you take out $300 million and you lose benefits.
- 1:01:17SPEAKER_00: It's not like you hold the benefit constant.
- 1:01:19SPEAKER_00: You just make the numbers work.
- 1:01:21SPEAKER_00: Real project development is actually about de-risking a project.
- 1:01:25It's not asking what component can I take out so it doesn't go
- 1:01:28over budget.
- 1:01:28SPEAKER_00: It's saying, what is making it cost this much?
- 1:01:31Is there a different way to get the same thing but for less
- 1:01:34money or get it in a
- 1:01:35SPEAKER_00: way to minimize the risk so that you don't need all that contingency,
- 1:01:39SPEAKER_00: right?
- 1:01:40SPEAKER_00: The way you de-risk a project, you start to build pieces of it.
- 1:01:43SPEAKER_00: You start to move the tracks.
- 1:01:45SPEAKER_00: You start to fix the grade crossings.
- 1:01:47SPEAKER_00: You start to move the utilities.
- 1:01:49SPEAKER_00: Well, if the federal system...
- 1:01:51basically doesn't give you any money till you've gone through
- 1:01:54public engagement,
- 1:01:55SPEAKER_00: planning and permitting,
- 1:01:56SPEAKER_00: right?
- 1:01:57SPEAKER_00: Where does the money come from to do all that early work?
- 1:02:00SPEAKER_00: Comes from you.
- 1:02:02And does it count towards your contribution when the feds say
- 1:02:05how much is ours and
- 1:02:06SPEAKER_00: how much is yours?
- 1:02:07SPEAKER_00: Most of the time, the answer is no.
- 1:02:09SPEAKER_00: So weirdly,
- 1:02:10SPEAKER_00: we've created this path,
- 1:02:11SPEAKER_00: which makes it harder to do what I think is clearly a best practice.
- 1:02:16SPEAKER_00: FTA knew that,
- 1:02:17SPEAKER_00: and they were trying to fix that and trying to be more open to it,
- 1:02:20SPEAKER_00: and Federal Highway knew that.
- 1:02:21SPEAKER_00: But the point is that this whole system we have,
- 1:02:24SPEAKER_00: where it's all waterfall instead of test and learn,
- 1:02:27SPEAKER_00: and where it's all sequential instead of consecutive,
- 1:02:30SPEAKER_00: that is several decades of a creed in,
- 1:02:33SPEAKER_00: like,
- 1:02:33what happens when you put together the Federal Highway Rules
- 1:02:35with the NEPA rules or
- 1:02:36SPEAKER_00: the Federal Trade
- 1:02:37SPEAKER_00: Transit rules.
- 1:02:37And I'm not going to say it's federal transit because I ran
- 1:02:40federal highway.
- 1:02:41SPEAKER_00: We did the same thing.
- 1:02:41SPEAKER_00: There needs to be more flexibility in the system.
- 1:02:45SPEAKER_01: Last question for you.
- 1:02:46SPEAKER_01: You're a Democrat who worked very comfortably,
- 1:02:49SPEAKER_01: I would say,
- 1:02:49SPEAKER_01: with Massachusetts governor who was Republican.
- 1:02:52SPEAKER_01: If you were advising Duffy now in the federal transit administration,
- 1:02:55what advice would you give him based on what you just told me
- 1:02:58about the way we're
- 1:02:58SPEAKER_01: doing things wrong?
- 1:03:00SPEAKER_00: I mean,
- 1:03:00SPEAKER_00: Secretary Duffy testified before Congress recently,
- 1:03:03and he said that as he's looking forward to the next five-year
- 1:03:07bill that lays out
- 1:03:08SPEAKER_00: all the money for the state transportation agencies,
- 1:03:10SPEAKER_00: which is called Surface Transportation Reauthorization,
- 1:03:13SPEAKER_00: His priorities are safety,
- 1:03:14SPEAKER_00: which it's hard to disagree with,
- 1:03:15SPEAKER_00: especially when a plane crashes on your first day on the job.
- 1:03:18But after safety,
- 1:03:19his priorities are actually permitting reform and project delivery.
- 1:03:23SPEAKER_00: So what I would say to Secretary Duffy is if you're serious about that,
- 1:03:27SPEAKER_00: then be serious about really changing things up.
- 1:03:30SPEAKER_00: When we fix processes in government,
- 1:03:32SPEAKER_00: we tend to leave all the processes that were there,
- 1:03:34SPEAKER_00: and then we add these fixes on top of them,
- 1:03:37SPEAKER_00: and then you just get an even more well
- 1:03:39SPEAKER_00: intentioned.
- 1:03:40SPEAKER_00: I understand why politically, very hard to take things away.
- 1:03:43SPEAKER_00: Everything that's there is there for reason.
- 1:03:45SPEAKER_00: Every word that's there is there because someone cared about that word,
- 1:03:48SPEAKER_00: that permit,
- 1:03:49SPEAKER_00: that process,
- 1:03:50SPEAKER_00: that meaning,
- 1:03:50SPEAKER_00: that step in the planning process.
- 1:03:52SPEAKER_00: But honestly,
- 1:03:53I think that we have really built a system that makes it
- 1:03:56extremely difficult for
- 1:03:58SPEAKER_00: anybody to deliver a federally funded project.
- 1:04:02SPEAKER_00: We have gotten to the point,
- 1:04:03and I had these conversations when I was running a state and
- 1:04:06when I was at Federal
- 1:04:07SPEAKER_00: Highway with State,
- 1:04:08where people will look at projects for which they could get
- 1:04:11federal money.
- 1:04:12SPEAKER_00: This is the highway side.
- 1:04:14And they will choose not to use federal money because it
- 1:04:17complicates the process so
- 1:04:19much that they would rather go fight with the legislature and
- 1:04:22the governor to get money.
- 1:04:24When we build a system where people are willing to walk away
- 1:04:28from federal funding
- 1:04:29SPEAKER_00: because of the complexity of using it,
- 1:04:32that should be a giant flashing sign that we really need to
- 1:04:36dismantle or at least reevaluate.
- 1:04:39Not little things at the edges,
- 1:04:41but like the whole fundamental,
- 1:04:44does this make sense?
- 1:04:45SPEAKER_00: I am a naive person and an optimistic person.
- 1:04:48I still don't think that that is actually a Republican or a
- 1:04:51Democratic issue.
- 1:04:53SPEAKER_00: I think everybody wants roads and bridges,
- 1:04:56SPEAKER_00: and some people at least want transit and rail,
- 1:04:58SPEAKER_00: and some other people want bike lanes.
- 1:05:00SPEAKER_00: Some people want pipes.
- 1:05:01SPEAKER_00: Whatever it is you want,
- 1:05:03you should care that it can get built with the smallest amount
- 1:05:06of taxpayer dollar
- 1:05:07SPEAKER_00: in the shortest amount of time,
- 1:05:09SPEAKER_00: right?
- 1:05:09Then you can fight about which kinds of projects you're willing
- 1:05:12to put that money into.
- 1:05:13SPEAKER_00: That's political.
- 1:05:13SPEAKER_00: But whatever project it is,
- 1:05:15like making it hard to build it because there are these rules
- 1:05:19that we just haven't reconsidered.
- 1:05:21SPEAKER_00: And again, we can't take them all away.
- 1:05:23Some of them exist because people would have hired their
- 1:05:25brother-in-law and given
- 1:05:26SPEAKER_00: them the contract.
- 1:05:27SPEAKER_00: And that's probably not a great thing.
- 1:05:29SPEAKER_00: That's Mark Dunkelman and the progressives and all that.
- 1:05:32SPEAKER_00: If you are serious when you say,
- 1:05:34we've gotten to the point where we need to fix permitting and
- 1:05:36we need to fix
- 1:05:37project delivery and we need to make sure that we can
- 1:05:39efficiently build the things
- 1:05:41SPEAKER_00: that people need with the money that the government has to give them,
- 1:05:44SPEAKER_00: then it's not a little fix.
- 1:05:46SPEAKER_00: It's a, why can't it look more like rebuilding I-95 or Interstate 40?
- 1:05:52Or why can't it look more like the first six months of how we
- 1:05:55did the Green Line extension?
- 1:05:57SPEAKER_00: Like, why does it have to take so long?
- 1:05:59SPEAKER_00: Why do you have to follow this procurement rule and that permitting rule?
- 1:06:02SPEAKER_00: It's no one's fault.
- 1:06:03Every single person who put any one of those requirements in
- 1:06:06place meant well.
- 1:06:07But we have just added so many over so many decades that we are
- 1:06:11working at cross
- 1:06:11purposes to the fundamental objective of building the things
- 1:06:15people need in a
- 1:06:16reasonable amount of money at a reasonable amount of time at a
- 1:06:19reasonable cost.
- 1:06:20SPEAKER_01: Stephanie,
- 1:06:21I think I've learned more from this conversation than almost
- 1:06:24any of the interviews
- 1:06:25SPEAKER_01: that we've recorded.
- 1:06:26SPEAKER_01: So that's my last question.
- 1:06:27SPEAKER_01: Thank you very much for joining.
- 1:06:28SPEAKER_00: Thank you so much.
- 1:06:29SPEAKER_00: This has been a lot of fun.