Latest / NWPPA Morning Brief / NWPPA Morning Brief - Wednesday, September 23, 2026
Transcript
- 0:00SPEAKER_00: Before we begin, a quick note.
- 0:02SPEAKER_00: The NWPPA morning brief is Generative AI, daily intelligence on the federal and Western developments shaping public power.
- 0:10SPEAKER_00: It isn't human reviewed before publication, so treat it like any AI tool and verify what you'll act on or cite.
- 0:17SPEAKER_00: Sources are in the show notes.
- 0:19SPEAKER_00: You're listening to the NWPPA morning brief.
- 0:22SPEAKER_00: On today's brief, BPA files a$250 million rate increase tied to the Snake River Salmon Court Order.
- 0:30SPEAKER_00: New England states push FERC to eliminate the RTO membership return adder with direct implications for Western transmission owners.
- 0:37SPEAKER_00: Wyoming's consumer advocate moves to block Rocky Mountain Power's third rate hike in three years.
- 0:43SPEAKER_00: A Washington Appeals Court upholds a Columbia River hydro certification with expanded monitoring conditions and more from the West.
- 0:51SPEAKER_00: Today's briefing is brought to you by NWPPA's January Conference Series, covering three of the biggest issues facing utilities right now: wildfire risk, data centers and load growth, and power supply.
- 1:04SPEAKER_00: Three conferences, three days, one trip to Portland, January 26th through 28th.
- 1:09SPEAKER_00: Register at NWPPA.org.
- 1:12SPEAKER_01: The BPA rate filing is the story today.
- 1:15SPEAKER_01: The litigation risk from the Snake River Salmon case has been sitting on the books as an open liability.
- 1:21SPEAKER_01: Now it has a number,$250 million, and it lands directly on preference customers through BPA's wholesale rate structure.
- 1:29SPEAKER_01: The question that matters is how BPA allocates that cost across slice, load following, and block product customers, and what timeline the rate schedule sets for recovery.
- 1:40SPEAKER_00: The part I'd add is that this isn't the final number yet.
- 1:43SPEAKER_00: BPA opened an expedited rate proceeding, and the cost allocation methodology is still the open variable.
- 1:49SPEAKER_00: How that shakes out across product types is what determines which utilities absorb the most.
- 1:54SPEAKER_01: Let's start there.
- 1:55SPEAKER_01: Walk me through the BPA filing.
- 1:57SPEAKER_01: The Bonneville Power Administration formally notified customers it will pursue higher rates to recover revenue lost under a federal court order directing changes to hydro operations for salmon protection.
- 2:08SPEAKER_01: The proposed increase is roughly$250 million and is directly tied to the district court's February order in the ongoing Columbia River fish litigation.
- 2:18SPEAKER_01: That order forced operational changes to the federal hydro system, changes that cost BPA revenue, and now that cost is moving into the rate base.
- 2:27SPEAKER_00: Preference customers across the Northwest are the direct exposure point.
- 2:31SPEAKER_00: The rate proceeding is still running, so the final allocation across product types isn't set.
- 2:36SPEAKER_00: But the dollar figure is now concrete, and that changes the planning calculus for any utility holding a slice contract or a block product.
- 2:44SPEAKER_01: The expedited process means this moves faster than a standard rate case.
- 2:48SPEAKER_01: Utilities in the proceeding need to be engaged on the cost allocation methodology now, not after a proposed schedule drops.
- 2:56SPEAKER_00: Turning to the federal transmission picture, New England states filed at FERC asking the Commission to strip the extra half-point return on equity, the 0.5% RTO membership adder that transmission owners collect for belonging to a regional grid operator from main transmission owners, including Central Maine Power and Versant.
- 3:15SPEAKER_01: The argument is straightforward.
- 3:17SPEAKER_01: When state law requires RTO membership, the adder stops functioning as an incentive and becomes a windfall.
- 3:23SPEAKER_01: FERC has already removed it in California and Ohio on exactly that logic.
- 3:28SPEAKER_01: If FERC extends that reasoning broadly, transmission revenue requirements embedded in wholesale rates, including rates paid by Western public power utilities, could shift downward.
- 3:39SPEAKER_00: The main complainants put a number on it.
- 3:41SPEAKER_00: Roughly$6 million added to regional charges in 2024, just from the Central Maine Power and Versant Adder.
- 3:49SPEAKER_00: That's a small state with a relatively small transmission owner base.
- 3:52SPEAKER_00: Scale that logic to larger Western transmission owners, and the revenue impact gets meaningful.
- 3:58SPEAKER_01: Watch whether FERC treats this as a narrow main-specific ruling or as an opportunity to set a broader standard.
- 4:04SPEAKER_01: That distinction is what determines how directly Western utilities can cite this proceeding in their own transmission rate challenges.
- 4:12SPEAKER_00: Moving to the geothermal story, DOE awarded roughly$20 million to Fervo Energy for enhanced geothermal systems work, drilling engineered wells into hot rock that isn't naturally permeable, with one grant targeting well drilling in Elmore County, Idaho in partnership with National Labs, and a second for high temperature EGS technology development.
- 4:33SPEAKER_01: For Northwest and Mountain West public power utilities with firm low-carbon resource gaps in their IRPs, this is worth tracking as appraisal scale activity, not just pilot scale.
- 4:44SPEAKER_01: The Idaho work specifically puts commercial geothermal drilling in a state where public power resource planning is active.
- 4:50SPEAKER_01: What the well results show about levelized costs is what determines whether EGS enters real IRP scenarios in the next planning cycle.
- 4:58SPEAKER_00: On the regional front, let's take the Wyoming rate case.
- 5:01SPEAKER_00: Rocky Mountain Power filed for an 8.8% rate increase, its third in three years.
- 5:08SPEAKER_00: Wyoming's Office of Consumer Advocate announced it will formally intervene and push for a substantial cut or elimination of the request.
- 5:15SPEAKER_00: If approved as filed, cumulative increases since 2024 would approach 25%.
- 5:21SPEAKER_01: The OCA has a real track record here.
- 5:24SPEAKER_01: In 2023, it helped cut a 21.6% request down to less than half the ask.
- 5:30SPEAKER_01: The question for Wyoming public power utilities operating alongside Rocky Mountain Power Territory is how the outcome shapes the customer affordability comparison.
- 5:39SPEAKER_01: When an investor-owned utilities rates climb that fast, the contrast with community-owned utility rates becomes part of the political environment those utilities operate in.
- 5:49SPEAKER_00: The proceeding is early.
- 5:50SPEAKER_00: OCA intervention is the opening move.
- 5:53SPEAKER_00: Watch what the commission-ordered evidentiary schedule looks like and whether other parties pile in.
- 6:14SPEAKER_00: Thermal, renewable, storage, and regulation resources all qualify.
- 6:19SPEAKER_00: An MEA flagged interest in resources that could be shared across multiple railbelt utilities.
- 6:24SPEAKER_01: This is the concrete procurement step following months of planning signals out of the railbelt, the Cook Inlet Gas Outlook, Chugach Ratework, and STAR proceedings.
- 6:33SPEAKER_01: An RFP that opens the door to lower 48 developers is a significant shift in how the railbelt is framing its resource options.
- 6:40SPEAKER_01: It signals that internal Alaska supply alone may not close the gap.
- 6:44SPEAKER_00: Over to the Washington Hydro Certification Ruling.
- 6:47SPEAKER_00: A Washington Court of Appeals panel upheld the state's water quality certification for a hydroelectric project near the Columbia River, but added expanded monitoring and reporting requirements tied to potential watershed leakage.
- 7:01SPEAKER_01: The headline is that the certification survived appeal, which matters, but the added monitoring conditions are what operators in comparable relicensing proceedings should be reading carefully.
- 7:11SPEAKER_01: State certifications, the Section 401 water quality approvals required before federal licensing, can now carry enhanced monitoring requirements and still be upheld.
- 7:22SPEAKER_01: That expands the conditions range utilities need to model into compliance cost estimates.
- 7:27SPEAKER_00: Watch whether similar monitoring conditions get imported into other Section 401 proceedings on Columbia Basin projects.
- 7:34SPEAKER_00: If this becomes a template, it changes the cost baseline for relicensing negotiations across the system.
- 7:40SPEAKER_01: Next, the California Climate Credit Story.
- 7:43SPEAKER_01: Governor Newsom announced$886 million in bill relief for PGE, Southern California Edison, and San Diego Gas and Electric residential customers.
- 7:54SPEAKER_01: Automatic credits averaging$75 on August and September bills, funded by the state's Cap and Invest Program, which directs carbon allowance auction proceeds back to ratepayers.
- 8:05SPEAKER_00: The design choice that's newer here is the timing.
- 8:08SPEAKER_00: This is the first year California concentrated the credits on peak summer bills rather than distributing them evenly.
- 8:15SPEAKER_00: Washington and Oregon have discussed similar credit structures, and how California resolves the timing question is the element that feeds those conversations most directly.
- 8:25SPEAKER_01: On the advocacy and legal scan, the Minnesota Public Utilities Commission ruled that Minnesota Valley Cooperative Light and Power Association acted unlawfully and unreasonably when it threatened to disconnect the Upper Sioux Community's casino over a 2.5 megawatt behind-the-meter solar array with battery storage.
- 8:44SPEAKER_01: The Commission ordered continued service, directed the state attorney general to investigate and pursue penalties, and imposed conditions requiring the array to stay behind the meter pending an engineering study.
- 8:55SPEAKER_01: The cooperative says it will likely appeal.
- 8:58SPEAKER_00: The cooperative's board had a policy capping member self-generation at 40 kilowatts.
- 9:03SPEAKER_00: A 2.5 megawatt array blows past that threshold by a wide margin, and the commission found the disconnection threat crossed a legal line.
- 9:11SPEAKER_00: For Western public power utilities serving or bordering tribal lands, the ruling sets a precedent on how state regulators weigh interconnection caps and disconnection authority when tribal sovereignty and self-generation intersect.
- 9:25SPEAKER_00: That's a combination of factors that isn't going away.
- 9:28SPEAKER_01: The appeal will determine whether this stays a Minnesota-specific outcome or becomes portable precedent, worth tracking through the appellate process.
- 9:36SPEAKER_00: On the EPA front, the agency finalized a tighter residential soil-led cleanup standard at the Butte Superfund site, lowering the threshold from 1,200 parts per million to 456 parts per million, and expanding the cleanup footprint by roughly 3,600 acres, qualifying more than 7,000 additional properties for assessment over a 15-year window.
- 9:59SPEAKER_01: For Montana utilities operating in or adjacent to the Clark Fork Corridor, the expanded footprint changes the compliance environment on any project touching the newly covered acreage.
- 10:09SPEAKER_01: Vegetation management, pole replacement, underground work.
- 10:13SPEAKER_01: If it involves soil disturbance in the expansion area, it now triggers the tighter standard.
- 10:18SPEAKER_01: That's an operational reality, not an abstract risk.
- 10:22SPEAKER_00: Before pricing, a quick note on the APPA Cybersecurity Program.
- 10:27SPEAKER_00: APPA announced the first cohort under its Public Power Cybersecurity Accelerator Program, a public power-specific pathway for strengthening IT and OT cyber posture through assessment and recognition, separate from General CISA and EISAC channels.
- 10:43SPEAKER_00: Worth knowing it exists.
- 10:45SPEAKER_01: Agreed.
- 10:45SPEAKER_01: Now on pricing.
- 10:47SPEAKER_01: Frontmonth Henry Hub Natural Gas Futures were trading at$3.05 per million BTU on September 23, up from$2.83.
- 10:56SPEAKER_01: NYMEX WTI Front Month Crude Futures were trading at$90.63 per barrel, up from$89.82.
- 11:05SPEAKER_00: Western spot prices for September 22 delivery.
- 11:08SPEAKER_00: Sumas Natural Gas was$2.49 per million BTU.
- 11:12SPEAKER_00: Mid-Columbia Power at$39.75 per megawatt hour.
- 11:17SPEAKER_00: On the capital side, the 10-year Treasury yield was 4.96% on September 21st, down from 5.01%.
- 11:24SPEAKER_00: Comex Copper settled at$6.81 per pound on September 22, up from$6.76.
- 11:33SPEAKER_01: One to watch.
- 11:34SPEAKER_01: The BPA rate proceeding deserves more attention than it's getting right now.
- 11:38SPEAKER_01: The$250 million figure is the opening position in an expedited process, and expedited means the window for preference customers to engage on cost allocation methodology is short.
- 11:49SPEAKER_01: How BPA assigns those costs across slice, load following, and block products will determine which utilities absorb the most, and the final rate schedule sets the recovery timeline.
- 12:00SPEAKER_01: These are not abstract variables.
- 12:02SPEAKER_00: The deeper question is whether the salmon litigation produces more of these cost impacts.
- 12:08SPEAKER_00: The February court order was one ruling in an ongoing case.
- 12:12SPEAKER_00: If further operational changes are ordered, the rate mechanism BPA establishes now becomes the template for recovering those future costs too.
- 12:21SPEAKER_00: That's the structural risk worth tracking, not just the$250 million on the table today.
- 12:27SPEAKER_01: The federal hydro system's operational constraints and the Pacific Northwest wholesale rate base are now directly linked through this proceeding.
- 12:35SPEAKER_01: That connection doesn't resolve when the rate case closes.
- 12:39SPEAKER_00: Today's session concentrated a lot.
- 12:41SPEAKER_00: A concrete litigation cost converting to wholesale rates, a transmission adder precedent building in the East with Western implications, and a tribal interconnection ruling that opens new questions about self-generation policy on cooperative systems.
- 12:56SPEAKER_00: The cost exposure signals are specific enough now that the planning conversations they feed are overdue.
- 13:02SPEAKER_01: The BPA number, the RTO adder trajectory, and the Montana Cleanup Expansion all share the same quality.
- 13:08SPEAKER_01: They moved from open risk to defined obligation this week.
- 13:12SPEAKER_01: That's when the planning work has to catch up to the legal record.
- 13:15SPEAKER_00: That's your NWPPA morning brief for Wednesday, September 23rd, 2026.
- 13:20SPEAKER_00: Sources for every story are linked in the show notes.
- 13:23SPEAKER_00: We'll be back tomorrow morning.
- 13:25SPEAKER_00: Keep the lights on.