- 0:05Speaker 1: Lawsuit against Yorkville to halt one thousand, thirty seven acre
- 0:09data center likely heading for settlement. This article is being
- 0:13read by an automated voice brought to you by Everlett
- 0:18while a residence lawsuit filed against the City of Yorkville
- 0:21to halt the one thousand thirty seven acre project Cardinal
- 0:24Data Center project began with a lot of fanfare, The
- 0:27litigation appears likely headed for a quiet settlement. During a
- 0:31hearing at the Kendall County Courthouse in front of Judge
- 0:34Robert Pilmer on December thirtieth, the lawyers representing all parties
- 0:38said they are working on a settlement. All parties agreed
- 0:40to a next court date of January sixteenth. Neither side
- 0:44disclosed a possible monetary amount, where specific details of the
- 0:48settlement or if the amount would be revealed during the
- 0:51January sixteenth hearing. John Bryan's lawsuit argues the data center
- 0:55campus and its construction with fourteen two story warehouses built
- 0:59over a decade or more, will negatively impact his property
- 1:03values and quality of life. Brian filed his initial lawsuit
- 1:07against the city to stop the project from going through
- 1:10on October twenty eighth. The City Council approved the planned
- 1:12unit development for Data Center on November tenth. At a
- 1:16December nineteenth hearing, Pioneer Development LLC requested and was granted
- 1:20permission to join the case as a defendant. Project Cardinal
- 1:24is lined up to be the city's largest ever manufacturing undertake.
- 1:29The project plans include a six hundred and twenty five
- 1:32foot setback from the warehouses to Bristol based subdivision and
- 1:37a twelve hundred foot setback from Equestrian. The states its
- 1:41location is northwest of Illinois Route forty seven and Galena Road,
- 1:45south of Baseline Road, and east of Ash Road. Bryan's
- 1:49legal team is claiming the city's comprehensive plan slates the
- 1:53area solely for residential and not for manufacturing. The lawsuit
- 1:57calls the city's actions to rezone the property to manufacturing arbitrary, capricious,
- 2:02and illegal. During a city council meeting earlier this year,
- 2:05Brian demonstrated the expected noise pollution generated from the Data
- 2:09Center campus by blaring the decibels through a speaker. City
- 2:14administrator bart Olson previously said data centers will be required
- 2:18to keep their noise pollution under the city's ordinance the
- 2:22city is making the developers of each project undergo a
- 2:25sound engineering and noise pollution study. However, so far, the
- 2:29sound studies have not included information related to the lengthy
- 2:32periods of construction. City officials and aldermen have previously said
- 2:37they envisioned three thousand acres of former agricultural land along
- 2:41the Eldemain Corridor becoming Yorkville's own data center alley. The
- 2:44city has moved forward several data center projects outside of
- 2:47Project Cardinal, including the five in two acre Project Steel.
- 2:53At several city council meetings over several months, many residents
- 2:56voice their opposition to the projects. Some residents said they
- 2:59would rather move away from their Yorkville neighborhoods rather than
- 3:02live next to manufacturing behemoths. Several residents claim that the
- 3:07construction alone will negatively impact their quality of life for
- 3:10more than a decade to come. Several members of local
- 3:14trade unions spoke at a city council meeting in favor
- 3:16of the project, saying it will create construction jobs. This
- 3:19city has argued that tax revenues generated by data centers
- 3:23will be a game changer for the community. Olsen said
- 3:27at full buildout the Project Cardinal development is projected to
- 3:30generate between thirty five million dollars and seventy million dollars
- 3:34in property taxes annually for Yorkville School District one point fifteen.
- 3:38In addition, each individual warehouse will generate between one point
- 3:42four million to two point nine million in utility taxes.
- 3:45This translates to twenty million to forty million at full buildout.
- 3:50Mayor John Purcell has asked some of the developers to
- 3:53write an upfront check to the school district before full
- 3:56city approval is granted. After hours of debate spread across
- 4:00multiple city meetings, the PUD for Project Cardinal was passed
- 4:04unanimously by City Council