Latest / Project Podcast / How to measure anything in project management
Transcript
- 0:14Welcome to the APM podcast. APM is the childhood body for
- 0:18the project profession. My name is Emma David and I'm
- 0:21the editor of Project APM's quarterly journal and your host
- 0:24today. In this podcast, we're talking
- 0:27about how to measure anything in project management.
- 0:29Yes, you did hear me write anything.
- 0:32It's the title of a new book that is co-authored by Douglas
- 0:35Hubbard, Alexander Budzia and Andreas lead.
- 0:38I have the pleasure of being joined by Doug and Andreas Now.
- 0:42Doug is founder and president of Hubbard Decision Research, is a
- 0:46management consultant and the author of a series of books
- 0:48including the brilliantly titled How to Measure Anything.
- 0:52Andreas is head of Data Science at Oxford Global Projects and is
- 0:56a PhD Fellow at AAHSA University in Denmark.
- 0:59Be prepared for mind expanding conversation about project
- 1:02management and how any aspect of it can be measured, including
- 1:06those things you thought might be immeasurable and why we
- 1:09should all be engaged in the most important project of all,
- 1:12the meta project of understanding how to manage
- 1:15projects better. I'd like to begin by welcoming
- 1:19Andreas and Douglas to the APM Podcast.
- 1:21So thanks very much for finding the time to speak to us today.
- 1:25Thank you for having us. You bet.
- 1:27Let's begin by you telling us a little bit about your area of
- 1:32work and interest within project management.
- 1:34So Andreas, tell us a bit about what you're what you're working
- 1:38on right now. Yes, Sir, of course.
- 1:41So I'm, I'm Andreas lead and the head of Data Science at Oxford
- 1:44Global Projects. And Oxford Global projects is a
- 1:47small consultancy which is really about analysing vast
- 1:51amount of vast amounts of project data and and using it to
- 1:58to have a better decision making around projects.
- 2:01Another of what we do is about, you know, debiasing estimates
- 2:05and kind of assuring estimates, realistic, basing estimates on
- 2:09historical data rather than bottom up type approaches.
- 2:14But it's also kind of bigger than that.
- 2:17So as the head of data science, I did some of the more
- 2:20quantitative engagements, things like using AI for machine
- 2:25learning for forecasting project outcomes or doing kind of
- 2:28econometric cost driver analysis.
- 2:32And the big goal with all of this is, is to better projects
- 2:35because after having looked at all the project data we have
- 2:39access to, which is now about 20 data from 20,000 completed
- 2:43projects, the the big conclusion is that rojects aren't erforming
- 2:48that well. O we'd like to understand, you
- 2:50know, what leads to success and how can we imrove roject
- 2:53erformance? Thank you.
- 2:55So that's not necessarily a controversial finding, is it,
- 2:58unfortunately. But good to know.
- 3:01We're here today to talk about how we can make perhaps make
- 3:04projects more successful through the way they're measured or what
- 3:07what is in fact measured. So Douglas, tell us a bit about
- 3:10your area of interest and and actually tell us how the book
- 3:13came about as well, because that's always good to know.
- 3:17Yeah, sure. So I'm Doug Hubbard.
- 3:21I'm the president and founder of Hubbard Decision Research, and
- 3:24for the past 36 or 37 years or so I've been in some form of
- 3:29quantitative management consulting.
- 3:32So all of my work, including all my books, this was my fifth book
- 3:37actually, They've all been on some topic related to decisions
- 3:42under uncertainty and difficult measurements.
- 3:45So that includes risk analysis, making big bets, and lots of
- 3:49different areas of forecasting problems.
- 3:52And of course, that applies to projects in general.
- 3:57My previous four books were not about projects specifically, but
- 4:00certainly a lot of my work was about risk return analysis on
- 4:04major new investments, which were usually projects in regards
- 4:08to how we met. Actually, I'll let Andres
- 4:12describe this because initially 2 of you called me.
- 4:18Yeah, so. So I was writing an article
- 4:20together with a colleague about cost, benefit, cost benefit
- 4:24analysis. Now kind of alternatives to, to
- 4:27typical inclusions in cost benefit analysis.
- 4:30I, I also teach cost benefit analysis at the Department of
- 4:34economics here in all who's where I'm based.
- 4:37But we found that Doug's work was really interesting.
- 4:40So we, we asked him for an interview and kind of some ideas
- 4:45around what should we include in this article.
- 4:48And I guess it was, it was a good match.
- 4:50Doug was looking for his next book project and project
- 4:53management was one of the topics he was considering.
- 4:56And so because we had access to a lot of data and a lot of
- 4:59analysis that kind of fit in really well with the book.
- 5:02I think that's fair, isn't it, Doug?
- 5:04Oh yeah, absolutely. In fact, I I chose this book
- 5:07title based on analytics. I decided to go after How to
- 5:13Measure Anything in Project Management because it had
- 5:16previously tied as one of the top 2 with How to Measure
- 5:20Anything in Cybersecurity Risk, which I've already wrote now.
- 5:24So I wrote that one first. And what tipped the needle in
- 5:27the in favour of the first book of the the 4th, my 4th book.
- 5:32But the previous How to Measure Anything in Cybersecurity Risk
- 5:34book was that I had a a well qualified, enthusiastic
- 5:38co-author that said, Hey, I'll write this with you.
- 5:42And I said, OK, well, then let's get started on that.
- 5:44And so I was really looking for the right people.
- 5:47I actually talked to a bunch of other possible candidates for
- 5:51co-authors for how to measure anything in project management.
- 5:54And my strategy is always to find somebody who's a
- 5:57specialist, an expert in renowned in that field because
- 6:02I'm always the outsider, I'm always the outside quant
- 6:04analyst, applying it to different kinds of problems,
- 6:07etcetera. So what I wanted to do a spin
- 6:09off of my first book, my first book was just how to measure
- 6:12anything. So that and I meant it
- 6:14literally. So how to measure anything.
- 6:17And I decided to do a series of spin off books like that.
- 6:20And so I waited for the right co-authors and when I learned
- 6:25about Oxford Global projects, I thought, well, that's ideal.
- 6:28They've got all this data. They, they already have these
- 6:32guys that are, that have been studying projects and all the
- 6:35problems with projects for many years now.
- 6:37So it seemed like the ideal co-authors.
- 6:42That's really interesting. So Doug, can you measure
- 6:47anything? Sorry, I've got to ask you.
- 6:50Yeah, absolutely. Including the hardest most
- 6:52possible things you've ever heard of.
- 6:54Can you, I'll think of some ideas as I as as we progress
- 6:58about what might be really hard to measure, but it sounds as
- 7:01though the book then is a really nice mix of the quality of
- 7:04quantitative, someone who's very deep with people who are very
- 7:07deeply involved in the profession and then more of an
- 7:10outsider. And I think that always adds a
- 7:13really valuable perspective on the same topic.
- 7:16I'm going to dive in there and ask you a really hard question
- 7:20and probably very hard to answer in not very much time.
- 7:24But but what's new about what you're saying in project
- 7:28management and how it's measured?
- 7:30Because I've read in the forward something very ambitious that
- 7:34you wrote that was that you don't just want to challenge
- 7:37traditional project management practises, but replace them with
- 7:40something more of rigorous, transparent and effective.
- 7:44This sounds really interesting. So.
- 7:46So tell me more. I don't know who'd like to go
- 7:49press. Doug, would you like to share
- 7:52that with us? So I approach everything as a
- 7:56sceptic and in every field I've looked in, whether it was
- 7:59cybersecurity risk or operational risk management or
- 8:02portfolio prioritisation methods that businesses use or just
- 8:06decision making in general, I tend to find that there's a lot
- 8:10of, a lot of assumptions they make about what works and what
- 8:14does it. They don't really know, they
- 8:16just assumed it always has worked.
- 8:19They they never really measured it and they're often surprised
- 8:22when they do measure it. So it's the sort of thing where
- 8:25it's not really obvious though, like if you're, if you're
- 8:29golfing, it's going to be obvious whether or not you're
- 8:32good or bad at it, right? You get your score right at the
- 8:34end of things, right, other kinds of sports, etcetera.
- 8:38But in a lot of management decision making, you have this
- 8:41really inconsistent and highly delayed and ambiguous feedback
- 8:45cycle. So it's not really necessarily
- 8:49obvious that what you're using is really one of the better
- 8:53methods. There's probably many other
- 8:54methods. People tend to be very
- 8:56overconfident about their own judgement.
- 8:58We know this from a lot of other research that's been, you know,
- 9:01spearheaded by many others. We also know that they're highly
- 9:05inconsistent, that they're influenced by irrelevant random
- 9:08external factors, and they dismiss too many things as
- 9:13immeasurable when all the research shows that you're
- 9:16better off doing the math on a wide variety of problems.
- 9:20Even relatively simple statistical models seem to
- 9:23outperform human experts in a variety of different fields.
- 9:26You can't trust the humans. Well, you can't trust the humans
- 9:30for some things. It's really important you figure
- 9:32out how to use the humans, what to use them for, and what not to
- 9:37rely on them for. Quantitative methods in
- 9:40mathematics are really important.
- 9:42Human invention, slash discovery.
- 9:45All right. As important as language itself.
- 9:48OK. And it solves a lot of problems.
- 9:52It's a tool that we should use more often.
- 9:54We we revert too frequently to just rely on our own judgement.
- 9:59We're having too much trust in other human beings when in fact
- 10:02the data shows that simple statistical models are
- 10:05outperforming them. So does that pass the argument
- 10:09in the book? Oh yes, absolutely.
- 10:12We, we take a sceptical view of, of a lot of the methods that are
- 10:15used in project management and Andres can talk a little bit
- 10:18about that. But we did, in addition to the
- 10:21analysis of the 20,000 or so projects that they had in their
- 10:24database, we did our own original survey of little over
- 10:28200 project managers and projects and pretty extensive
- 10:32literature review, more than 100 different, you know, peer
- 10:36reviewed articles, standards, other sources and so forth.
- 10:40And we were looking for what's the evidence that some methods
- 10:43are measurably better than others.
- 10:46And that was one of the surprising things.
- 10:50I'll let Andreas talk about some of that.
- 10:51But really, what works doesn't is will be a surprise to many
- 10:57project managers I think. Well, what?
- 10:59What were these discoveries you made, Andreas?
- 11:03So I, I might just, I might just take a, a step back because one
- 11:06of the first things we did when we approached the book was,
- 11:10well, can can we say something about some of the, do some
- 11:14projects perform better than others?
- 11:15Do projects use specific types of methodologies or frameworks
- 11:20or different types of tools for estimating how do they perform
- 11:24compared to others? And so the the first thing that
- 11:27we actually did was to look at our large database of projects,
- 11:31which goes back to we have some historical projects from the
- 11:341800s. And what we see there is kind of
- 11:38a very consistent trend in terms of projects not delivering to
- 11:42expectations in terms of cost and schedule and also benefits.
- 11:47And and that's despite the fact that since at least since the
- 11:5190s, we've gotten more and more kind of methodologies and
- 11:54frameworks and all these things that supposedly help us with
- 11:56projects. So we, if these frameworks and
- 12:00these tools we've developed works, we would expect to see,
- 12:04you know, budget overruns have gone down over time.
- 12:07We, we don't see as big delays. We are better at getting the
- 12:11benefits that we, we expect we will from projects.
- 12:14But when we look at kind of project performance over time,
- 12:18we don't see that a performance improvement since 1990s despite
- 12:23all this, all this work and improving projects in terms of
- 12:28methodologies and certifications and all this.
- 12:30So that was kind of the first clue.
- 12:34Afterwards, we, we launched this survey where we looked into,
- 12:38well, what, what do projects use?
- 12:40And can we see some kind of statistical differences between
- 12:44different types of approaches to delivering projects?
- 12:49And, and I think the, the evidence, what we found was was
- 12:54very contrasting because project management is a field where
- 12:56there's just a lot of claims, There's lots of methodologies
- 12:59that promise, you know, if you use this approach to deliver
- 13:03your project, you're going to get twice the benefits in half
- 13:07the time. But we didn't see that for any
- 13:09methods. We didn't see any methods really
- 13:11outperform others. We, we saw very few actually
- 13:15effects of applying any kind of methods at all to projects.
- 13:20I think that the one very consistent finding we had was
- 13:24that projects have spent more time in the front end
- 13:27development of projects. They they tend to perform better
- 13:31and and secondly projects that apply more quantitative and
- 13:34evidence based methods. They also tend to perform better
- 13:39in terms of adhering to their estimates compared to projects
- 13:42that use more qualitative and subjective estimating
- 13:46techniques. One of the things I thought of
- 13:50as I was going through the book was that I thought listeners
- 13:53might be interesting. Was was I, I?
- 13:57What can be measured in projects?
- 13:59Can everything be measured and what are the things you should
- 14:04be measuring? So the methodologies you're
- 14:06saying out there, many of them don't deliver any notable
- 14:09results. And is part of that because
- 14:11they're measuring the wrong things or what do you do with
- 14:15the measurements once you've got them?
- 14:17So big, a big couple of big questions there.
- 14:20So I guess if you want to take, can you measure everything in
- 14:25projects and then which are the ones you should be measuring?
- 14:29I think that would be really interesting.
- 14:32Well, the simple answer is yes. There's literally nothing,
- 14:37literally nothing that has any consequences at all for the real
- 14:41world. Every project that anybody has
- 14:43ever proposed had some expected consequences, right?
- 14:49And every consequence is necessarily observable.
- 14:53Otherwise, it wouldn't be something that everybody cared
- 14:56about, right? It would have to have observable
- 14:58consequences. No matter what you're thinking
- 15:00of, it's really hard to measure if you have a project that's
- 15:03supposed to improve collaboration or innovation or
- 15:06the environment or customer satisfaction, or some sort of
- 15:10social welfare or children's education, it doesn't really
- 15:13matter. In each of those cases, there
- 15:16are expected observable outcomes.
- 15:18Now, you might be highly uncertain about them.
- 15:21That's a different issue, but you can identify the
- 15:23observations first, then the rest is about observations and a
- 15:29little bit of math to reduce your uncertainty.
- 15:32Does that mean you need to know what you're observing before you
- 15:37start measuring? Do you know?
- 15:39Do you have to have an expectation of what there will
- 15:41be to observe before you can start thinking about measuring
- 15:44that thing? You don't have to, but you won't
- 15:48know the value that measurement until you know the reason for
- 15:50it. You can have purely exploratory
- 15:53discovery driven observations. A lot of science is this way.
- 15:56You you don't necessarily know what you're looking for, right?
- 16:01If I go to a, a, a, a new city and I'm walking around downtown,
- 16:06I don't know what I'm looking for necessarily, right?
- 16:08I might discover something. But if I'm going to spend a lot
- 16:12of time and effort measuring something in particular, I have
- 16:15to know what it's for, right? And all measurements are meant
- 16:21to reduce uncertainty, to make better bets.
- 16:24You're making better decisions. That's what all of this is
- 16:28about. Every project manager, what
- 16:31management means is all about making decisions before and
- 16:35during a project, sometimes even after a project.
- 16:39So you can think of projects, project decisions during the
- 16:42project as sort of intervention decisions.
- 16:46So what are they measuring if they're not going to do anything
- 16:49with the measurements during a project?
- 16:53That is, they can't think of anything they might do
- 16:55differently at all. If it was surprisingly high or
- 16:58surprisingly low, well then that has a information value of 0.
- 17:03This is a computable value, by the way, the value of
- 17:05information. So it's sort of like the cost of
- 17:08being wrong times the chance of being wrong.
- 17:11It can get a little bit more elaborate than that.
- 17:13But generally speaking, if there's, if you can't think of
- 17:16any consequence that would be different at all, or if there's
- 17:20no uncertainty about it already, well then there's no value to
- 17:22that that information. Do you think that project
- 17:26professionals. Oh, know that deep down that
- 17:30they do question why they're measuring something or is it
- 17:33just we're just measuring these things?
- 17:36So it's there's enough thought given to or consideration given
- 17:39to what's being measured and why, what the outcome you want
- 17:43from that measurement to be Andreas?
- 17:47So I think there's a lot of culture and project management.
- 17:50We typically measure the things we've measured before or that
- 17:54that other projects measure. And it's actually one of the
- 17:58things we go into that, you know, there's all these standard
- 18:01setting bodies, there's all these kind of influential
- 18:03organisations in, in the space of project management.
- 18:06And a lot of them just kind of repeat.
- 18:08This is how we've delivered projects before.
- 18:10This is how we've done project management and how we've thought
- 18:13about, you know, quantifying risk in some way.
- 18:16But they, they typically don't really distinguish between what
- 18:20are the methods that are proven to actually give you better
- 18:25results versus the ones that in, in the best case don't do
- 18:30anything, but at, at worst, they might add uncertainty.
- 18:34We use kind of a risk matrix as one of the examples of, so a way
- 18:39of we, we call it analysis placebo in the book, but it's,
- 18:43it's the idea that you, you feel you're kind of measuring a risk
- 18:48by using risk matrices to kind of quantify the impact versus
- 18:52the likelihood. But there's multiple problems
- 18:56with, with that type of more subjective scale approach where
- 19:01all the research from, from not just product management, but
- 19:05also different fields show that these types of quantifications,
- 19:09they, there's a lot of error with them and they don't
- 19:12actually contribute anything good.
- 19:15But in projects, we, we apply some of these tools and because
- 19:18we've been applying those tools, we feel that we've actually
- 19:21we've done some kind of assessment of a risk even though
- 19:25we haven't really, we call it analysis placebo that because
- 19:28we've spent time applying A structured framework, now we
- 19:32feel better about the situation even though we haven't reduced
- 19:35uncertainty at all. So, so I think that's a lot of
- 19:40that kind of culture. But another thing that's we
- 19:44found was pretty surprising in the book was that projects say
- 19:47spend a lot of time measuring things that have the lowest
- 19:50information values. If you want to stick to that
- 19:53framework of the value of information in terms of reducing
- 19:56uncertainty for our decision making projects, they spend a
- 20:00long time kind of estimating or measuring the CapEx cost, but
- 20:05they don't spend as much time measuring the OpEx cost of the
- 20:09kind of the maintenance of the the infrastructure, the project
- 20:13that they build afterwards. Where typically the
- 20:16uncertainties is typically in the latter and the Opecs the
- 20:21same with benefits. Often times big projects,
- 20:24especially big public projects have wider societal benefits and
- 20:28those are really uncertain. But projects they don't spend as
- 20:32much time trying to measure and reduce the uncertainty about the
- 20:35benefits side of the project as they do cost because they're the
- 20:39cost is the big typically it's, it's the big component that they
- 20:45could ask questions about. They have to deliver too.
- 20:48So should project professionals be focusing more on the benefits
- 20:56that will come from a project and measuring those?
- 20:59Yeah. Actually, when we compute the
- 21:02value of information, and we've done this many times on many
- 21:05different types of investments, including lots of different
- 21:07categories of projects, we tend to find the high information
- 21:11value variables. So I mentioned that's an
- 21:13algorithm you can actually run. These are more sensitive
- 21:16variables. They change the outcome of the
- 21:19decision more and they're more uncertain, right, than other
- 21:22variables. The high information value
- 21:25variables tend to be the things they haven't measured before,
- 21:28and that often includes benefits.
- 21:30They spend more time historically spending things
- 21:33that spending their time on, things that have lower
- 21:38information values, things that are statistically less likely to
- 21:41actually improve decisions. So we call this the measurement
- 21:44conversion in our books. I think this is a pervasive
- 21:49issue in every industry and projects and also outside of
- 21:54projects. I I don't know how it couldn't
- 21:56affect the GDP of countries. It would kind of have to.
- 22:00Why have we ended up this way? What?
- 22:03Why are we not measuring benefits better or measuring
- 22:07them at all? There's a general, there are a
- 22:11few different reasons I think and Andreas, you can comment on
- 22:15this. But First off, I think there's a
- 22:16habit of when you label something as intangible and
- 22:20immeasurable, it's never considered again.
- 22:24Once it's labelled intangible or immeasurable, no one ever goes
- 22:27back and ask, is it really immeasurable?
- 22:30Are there really no observable consequences at all that could
- 22:34reduce our uncertainty about this?
- 22:35Have we even figured out what it is that we're measuring right?
- 22:38Often things seem immeasurable because we have an ambiguous
- 22:41label. We're using terms like
- 22:42collaboration or innovation, but there's observable consequences
- 22:46that you can't identify out of each of those things.
- 22:48So there's that. Things get labelled too quickly
- 22:54or at all as immeasurable. That's one problem.
- 22:57They're all measurable. The other problem is that people
- 23:02are just as Andre has pointed out, it's just a matter of
- 23:05culture. They measure what they know how
- 23:07to measure. They don't really look at a
- 23:09problem and say, what should I measure given this problem and
- 23:13then learn how to measure those things.
- 23:15That's not the approach. The approach is I know how to
- 23:17measure these things. That's what I'm measuring.
- 23:21So what needs to change to make projects delivered more
- 23:27successfully or deliver better benefits?
- 23:29Is is part of that looking at benefits and realising that
- 23:34these can be measured in a useful way?
- 23:39Yes, that's part of it. The first big project management
- 23:44decision is approval and prioritisation.
- 23:47Should you even do the project in the first place?
- 23:51In those cases, even the decision of doing the project in
- 23:56the 1st place is. And that first big decision,
- 23:59modelling it quantitatively, is what's needed.
- 24:02Because when we start looking at that problem by itself, we find
- 24:06out that really most decision makers probably would not have
- 24:10accepted most of their projects. Seriously.
- 24:14Oh yes. So when you look at the data,
- 24:17there's a way to quantify risk aversion as well.
- 24:20And when and when you look at all the research on what
- 24:23executives say about how risk tolerant they are, how risk
- 24:26averse they are to, and then compare that to the actual
- 24:30uncertainties and risk of the big projects, they wouldn't have
- 24:34accepted almost any of them. So fewer projects, bigger wins.
- 24:41Is it one approach, right. And also spending more time on
- 24:45that early selection, you know, if somebody says, hey, this
- 24:49project is a good deal because we make more than our cost of
- 24:53money, that's not nearly good enough.
- 24:57If your return is just a little higher than your discount rates,
- 25:00you say, well, it's a good public project.
- 25:02You know, we're going to make the the cost of this big
- 25:06infrastructure project is justified or the cost of this
- 25:09big software project or Rd project is justified because we
- 25:13expect these returns. If those returns are modest,
- 25:17like modest improvements over your cost of money, your
- 25:19discount rates, that's not nearly good enough.
- 25:23If a project is expected, If we look at just all the projects in
- 25:27their database, if a project is expected to have a lot twice the
- 25:32benefits as costs, and this is present value discounted to
- 25:35current dollars, current units of monetary units.
- 25:39If you expect twice the benefits as you have cost, there's still
- 25:43so much uncertainty on benefits and costs.
- 25:45There's about a 14% chance of losing money still.
- 25:49In fact, there's even a chance of losing more than the money
- 25:51you put into it. And that's.
- 25:55Quite something, yeah. Yes, if you spend, if you spend,
- 25:59you know, £100 million on some big infrastructure project, is
- 26:04it possible you could lose more than 100 million?
- 26:08Yeah, actually there is. One of the cost that are not
- 26:11typically included in cost overruns is other process
- 26:15disruptions. So you've seen that's when
- 26:18there's a big infrastructure project, there's a bridge being
- 26:20built or a new road being repaid for something like this, and
- 26:23then there's a traffic congestion for a while because
- 26:26traffic has to be rerouted. Well, the project takes longer
- 26:29than expected. So that cost is the congestion
- 26:33cost is longer than expected, maybe even greater than
- 26:36expected. That's how you actually have
- 26:40cost that aren't in your budget. There's a other disruption cost
- 26:45in software cases. There's been cases of software
- 26:49where a lot of money has been spent to implement something.
- 26:52And then they figured out that this software that was supposed
- 26:54to improve productivity made things worse.
- 26:58So they had to unravel it. They had to undo it and take it
- 27:01out, go back to the old way. That's more that cost more than
- 27:06the cost of the project to do all of that.
- 27:09Now that doesn't happen every time, but it happens frequently
- 27:13enough that it's a risk we should consider and it's often
- 27:18not even acknowledges a possibility at the beginning of
- 27:21this approval process. So that's one big thing.
- 27:24Fewer projects, bigger wins, you know, a 20 or even 30 or 40%
- 27:29return. Not nearly good enough.
- 27:31You got to go bigger, spend more time in that upfront planning
- 27:36and look for better options. Keep exploring.
- 27:40There's one of the issues we talked about in the book is
- 27:42exploration versus exploitation. So this is kind of a classic
- 27:47measurement problem. It's a operations research
- 27:49problem. How long should I generate
- 27:52solutions before I pick the best one so far and and build on that
- 27:57one? Because there's a chance the
- 27:59next solution you generate is going to be better than any of
- 28:01the previous ones. On the other hand, you keep
- 28:04deferring the project, which has benefits itself presumably,
- 28:08right? So that's something that isn't
- 28:13typically looked at and it's something you could spend more
- 28:15time on in front end loading is you could spend more time
- 28:19generating solutions. It appears that people converge
- 28:24too quickly on a preferred solution.
- 28:27They should think of many more solutions and they should
- 28:31generate many more decision models and options to be used
- 28:35during the project. So it's not just the solutions,
- 28:37it's not the just the various designs of bridges, for example,
- 28:42that you're looking at. If you're also designing the
- 28:46measurement programme during the project, you're also designing
- 28:50the intervention options. These are decision models that
- 28:53run during the project. You're designing things.
- 28:57It's like what method should I use?
- 28:58Should this be an agile project or some modified version of
- 29:01that? That's all part of front end
- 29:03loading. And it's usually those things
- 29:06are they're not only not spend enough time on they're, they're
- 29:10just ignored as choices. They're just assumed that we're
- 29:13going to deal with this project with this way.
- 29:15We're going to follow this particular standard and we're
- 29:18going to measure these particular things and maybe
- 29:21after looking at a few solutions, we're going to pick
- 29:23that solution. That's a big problem.
- 29:27Just to add, when we talk about solutions, we mean solutions in
- 29:30a much broader kind of definition of that word.
- 29:34So when we talk about iterations of bridges, we really should
- 29:38spend more time thinking about alternatives to bridges as well
- 29:41that fulfil the same kind of requirement for the bridge.
- 29:44So thinking in fairies or tunnels or other types of
- 29:49solutions, not just iterations of bridges, because that's one
- 29:52thing that we saw too, is that we we fixate on a type of
- 29:56solution fairly quickly in projects and then we do
- 29:59iterations of that kind of design.
- 30:01How should that bridge look or how should that nuclear power
- 30:04plant be? Whereas we could consider much
- 30:07different types of solutions as well.
- 30:11I don't know where to start with everything I want to ask you,
- 30:13because that was quite macro. It's quite philosophical about
- 30:17what? What do we do and how do we do
- 30:20it in other alternatives, let alone the complication of
- 30:25political feeling or government. When you hit government mega
- 30:29projects for example, where the politics behind it can make it
- 30:34something happen without really being questioned why or is this
- 30:38the right thing to do. So for people listening, what is
- 30:44the how can they imagine someone just in a how I get a job
- 30:49working on a project? How can you begin to deliver,
- 30:55execute, think about your projects in a in a better way
- 30:59along the lines he suggests. And are you saying, let's look
- 31:04at the data, that let's make data more of a priority than
- 31:08these humans who might be too might be prone to optimism bias
- 31:12or and then with the rise of AI is, is this going to nudge
- 31:18projects more towards the way you're thinking that that if
- 31:22it's not measured, it should be measured, Everything could be
- 31:24measured and we should listen to the data and see the evidence of
- 31:27what actually works and be more objective about it.
- 31:33I think this is an interesting, interesting thing that comes up
- 31:36quite a lot. So many might say, but what
- 31:38about somebody who's working on a project right now?
- 31:42I think that's already too far down in the weeds because just
- 31:46organizationally that person doesn't really have the position
- 31:49or authority to make some of the changes we're talking about.
- 31:52We have to start much higher and much earlier in the
- 31:55organisation. We have to talk about
- 31:57stakeholders changing the way that they approach things,
- 32:00right? So it's stakeholders that are
- 32:02making ultimately making choices about where they should allocate
- 32:07funds in the first place. And something has to be
- 32:10communicated there that it's to their benefit to spend more time
- 32:15in this analysis before you make big bets.
- 32:18You know, if you're buying a house, you look at a few houses,
- 32:21right? If you're buying a car, you look
- 32:23at a few cars. You don't just pick the first
- 32:25one you see, right? And I think decision makers
- 32:30often are too quick to say we got to start coding or we got to
- 32:34start pouring concrete, right? I, that's a, that's a, this is a
- 32:40different way of thinking about it.
- 32:41We have to spend more time in that upfront analysis, analysing
- 32:45our choices. Again, fewer projects, bigger
- 32:48wins. That's the, the optimistic part
- 32:51here. I think it's the bigger wins
- 32:52part there. There's room for really
- 32:56impactful mega projects. That's where we should be
- 32:59thinking those really fundamentally life changing
- 33:05kinds of projects, socially changing kinds of projects.
- 33:09Like like what? Such as?
- 33:12Oh well, we have a couple of examples in the book, but at
- 33:15least in the states here, is it possible?
- 33:19Ideas have been proposed and it should be analysed.
- 33:21Is it possible to stop hurricanes?
- 33:25That's a hypothesis. And even if there's, if you work
- 33:28out the information value that if there were only a 5% chance
- 33:31of that being true, it'd be worth investigating just because
- 33:35it's so impactful. The cost of hurricanes is starts
- 33:40to compete with the cost of our entire aircraft carrier fleet,
- 33:44you know, in the US, right, or the entire Interstate system of
- 33:49expressways in the US. All of a sudden, when you add up
- 33:54a few big hurricanes like that, you say, well, yeah, actually,
- 33:57if it were even possible to even slightly reduce of the impact of
- 34:01hurricanes, what are the different ways we could do that?
- 34:04That's a big project. That could be a very big
- 34:06project. It might not even be a big
- 34:08project, Might be a bunch of little projects, by the way.
- 34:12But also, you think about AI itself.
- 34:15We talk about AI in the project and we tell people that you're
- 34:18single most important project, and this is the biggest project
- 34:21of all of them. By the way, the single biggest
- 34:24project the world is facing right now is how to do projects.
- 34:29That's the single biggest project.
- 34:32That's the most important mega project that any country or
- 34:35company is dealing with is how they should do projects.
- 34:39And this is a key message in the entire book.
- 34:42There's a lot of ways to run projects and a lot of ways to
- 34:44measure projects, and we're just not spending enough time
- 34:47figuring out which ways work better.
- 34:50Well, some are better than others, and we're still stuck on
- 34:53some, you know, habits that don't work as well as other
- 34:57things. Thanks Doug.
- 35:00Andreas, what? What are those better ways of
- 35:02running projects then what? What actually has does give some
- 35:07success. So we do have a lot of, I think
- 35:11one of the positive messages of the book is that there is a lot
- 35:14of potential, there are a lot of things you could be doing to
- 35:18improve the projects you're doing at the moment.
- 35:21So far we've talked a lot about, well, if we, we're able to
- 35:25reduce uncertainty about the bets that we're making, we would
- 35:28be making better bets, probably fewer bets, but the portfolio
- 35:32projects would be entirely different to what we're
- 35:34investing in now. And it would probably be better
- 35:37because a lot of what we, a lot of the projects we invest in now
- 35:41are the ones that look best on paper, but aren't necessarily
- 35:44the the best projects in in the book.
- 35:49Obviously the book is about measurement.
- 35:50So we talk about like what kind of measurement should you be
- 35:53making? Why are you doing?
- 35:55Why are you measuring in the 1st place?
- 35:57How should you be doing measurement?
- 36:00And one of the things when it comes to information value is,
- 36:04is often, if you don't know anything, almost anything will
- 36:09tell you something, right? So if the uncertainty is really
- 36:14high about something you haven't measured in your project, you
- 36:16don't need to collect a lot of data to reduce that uncertainty.
- 36:22And that's also part of the measurement inversion we talked
- 36:25about. We spend a lot of time fixating
- 36:27on the cost of the project. And sometimes to marginally
- 36:30reduce the uncertainty, we have to do a whole whole bunch of
- 36:33engineering in a project that might be really expensive and
- 36:37there's still a lot of uncertainty after we've done
- 36:39that detailed engineering. Whereas when it comes to some of
- 36:43the benefits coming out of projects, since we haven't
- 36:46observed it so far, we, we don't really need to make a lot of
- 36:50observation to be in a better place than we were before, to
- 36:53have reduced the uncertainty of what can we expect to get out of
- 36:56it and how can we manage that better.
- 36:58So we, we talk about, you know, you probably need less data than
- 37:04you think you need and you probably have more data than
- 37:07than you think you do. And that's generally going to be
- 37:11the case for organisations and for projects, especially on the
- 37:14things they aren't measuring so far.
- 37:17What what other things we talk about that you should be
- 37:20measuring as well as the the outside environment of projects.
- 37:23You mentioned politics as as an example of how it can add
- 37:27uncertainty to projects. And obviously that should be
- 37:30something if you're doing a big project that runs over multiple
- 37:33years, you should be measuring kind of the political context,
- 37:36political support of a project, because that's going to add
- 37:39uncertainty and it might mean that you're building in more
- 37:42decision options along the way of a project.
- 37:47But that's also one of the recommendations of the book
- 37:49that, you know, the projects, they aren't in their own bubble.
- 37:53They they do engage with and they are impacted by the
- 37:56external environment. So that's also some other things
- 37:59you should be measuring that you haven't been before.
- 38:03Thank you. Could you give an example of a
- 38:05project that perhaps does take on board the things you're
- 38:09telling me the recommend, the recommendations that you make in
- 38:12the book? Is there anything out there that
- 38:14people could find out more about?
- 38:17I've run into a couple of examples in in industries that
- 38:21do some of the things we're talking about.
- 38:23So for example, the option to cancel a project, that should be
- 38:30an option that's defined very well in advance.
- 38:33It's a part of a decision model that's run every day.
- 38:36Now nobody's doing quite that just yet, but in the
- 38:39Pharmaceutical industry and some related industries, they have a
- 38:42stage gate process. So only about 8% of all
- 38:47pharmaceutical products that are investigated ever make it to
- 38:50market. So how do they make any money?
- 38:53Well, when they quit, they quit early.
- 38:57And when you look at a lot of big projects that cancelled, and
- 38:59a lot of them do, they cancel with nothing to show for it
- 39:03after spending a lot of cost and having a lot of external
- 39:05consequences that are costly after.
- 39:09If you look at those kinds of projects, you often find out
- 39:12that they could have and should have cancelled it quite a long
- 39:16time ago. It they had all the data that it
- 39:18would would have justified cancellation quite a long time
- 39:21ago. It was just running on inertia.
- 39:24But also there's that feeling of, I think is it called sunk
- 39:27cost, sort of sunk cost of allergy where you've put all
- 39:31this money in already so it's too late to turn back.
- 39:36Right. It should always be on the
- 39:38forecast of the future. Here's what we here's our
- 39:41uncertainty about what there is remaining to be spent given what
- 39:45we've learned so far about the complexities of the project,
- 39:48because that might update our uncertainties about what's
- 39:52remaining to be spent. And we're comparing it to the
- 39:56outside world. It might not just be the
- 39:57project, it might be that something in the outside world
- 39:59has changed that changed the benefits of this thing.
- 40:04If I'm. 35% of the way into a project for some big
- 40:08infrastructure project and AI at the same time is improving
- 40:13because the and it will, because these are multi year projects,
- 40:17right? So there will be changes in not
- 40:20just AI, but materials and things like this and fabrication
- 40:23methods during the project. At what point during the project
- 40:27do we say there's enough that's changed about the outside world
- 40:31that I should now re engineer something about this project?
- 40:35That's a intervention decision. That's an intervention option
- 40:39that we should define in advance.
- 40:41So the pharmaceutical companies are one, but also aerospace does
- 40:46a little bit of something that we talked about where they do
- 40:50anticipate changes in technology.
- 40:52Because if they're developing a new crew re entry vehicle from
- 40:56the space station or something like this, they start designing
- 41:00it without necessarily assuming that the only materials they
- 41:04have are the current materials. Because it'll take a decade or
- 41:07more to design these things. And during that time there will
- 41:11be technological improvements. They're kind of counting on them
- 41:14in some ways. So we should take that into
- 41:17account. If we have a big infrastructure
- 41:19project, should we be saying asking questions like if AI
- 41:23could have changed this design if only I waited 2 1/2 years
- 41:27from now, what would I do differently?
- 41:31Is is there a point at which it might be worth waiting?
- 41:34There's something we introduced in the book called Technology
- 41:37Regret. Technology regret is includes
- 41:41things like you invest too soon in a technology that's rapidly
- 41:44changing, so you fixate on a bridge design or fixate on some
- 41:49software features at the same time while you're pouring
- 41:54concrete and writing code. AI is getting better.
- 41:59Not only AI, but materials and fabrication methods, 3D
- 42:03printing, hole bridges and so forth.
- 42:05That's getting better during this.
- 42:07Now AI is actually, I think improving faster than the other
- 42:10two items I mentioned. So we should at least be looking
- 42:14at there. There's not too many big
- 42:16projects that are going multiple years that shouldn't also be
- 42:19tracking what's going on with AI and asking questions about.
- 42:24Is there a point in time I should consider the possibility
- 42:27of right now and design an intervention option where I'm so
- 42:31far into the project and something the outside world has
- 42:34changed? And given how far I am into the
- 42:36project, and given the benefits of switching gears at that point
- 42:40in time, does it make sense to change something during the
- 42:43project? And you're saying that the
- 42:46answer could be yes, it could be, it could be beneficial to.
- 42:50So, so you're, you're planning in uncertainty, you're kind of
- 42:56planning that. That's quite probably quite a
- 43:00mindset shift for lots of people working on projects like this.
- 43:06Yeah, I think people are used to the concept of options, though
- 43:10some are. They're used to the concept of
- 43:12real options too. You know what's the what's the
- 43:15value of keeping an option open, right?
- 43:19Actually, even things like the option to cancel a project.
- 43:23This surprises people, but it de risk a project.
- 43:27Risk of a projects go down when you build in intervention
- 43:30options because in the case that you do need to cancel a project,
- 43:35you'll at least be able to cancel it sooner.
- 43:38So your expected losses would be lower if you do cancel a
- 43:41project. Now I've had lots of clients
- 43:44that would say, yeah, I've seen projects get cancelled, but
- 43:47prior to us developing decision models for them, they never saw
- 43:51a chance of cancellation on the business case for a project.
- 43:56How often do you see that right, if you're if you're presenting
- 44:01to a government agency or someone else in the corporation.
- 44:04I've got this idea for a project.
- 44:07Should I include the fact that there's based on historical
- 44:10data, there's about a 15% chance of cancellation with nothing to
- 44:12show for it. Some we've heard this, Andres
- 44:16and I were just talking to a group of the last time I was in
- 44:18the lending group of, you know, project managers and stuff like
- 44:21this. They'd say, well, you know,
- 44:23things wouldn't get approved if that were the case.
- 44:25If you're I said, well, if that's what you're looking at,
- 44:27then just leave out half the cost too.
- 44:30Why not? So the no, it's, it's about
- 44:34being transparent about these issues.
- 44:38Also, I think there's a fundamental conflict of interest
- 44:42here if the person opposing the project is the only one building
- 44:46the decision model for it, right, and the only one
- 44:50presenting it to decision makers.
- 44:53I do think there's room for some independent body of auditors.
- 44:57Actually, Oxford Global Projects does some of this right now
- 45:00because they audit people's projects, project plans and
- 45:03costs and schedules. That's part of the services that
- 45:05they do. And one of the values of having
- 45:09an outside consultant come come in, in general is that, hey, we
- 45:12don't have any skin in the game here.
- 45:14We're just going to do our analysis and give you an honest
- 45:19representation of the outcomes. Because usually we're working
- 45:21for the check writers, the people who were allocated funds,
- 45:25not necessarily the project manager or the person who wanted
- 45:28to promote the project. We're working for the people who
- 45:31have have to commit to the funds in the 1st place.
- 45:34So they want an honest answer and I think that's part of it.
- 45:39We have to think about some built in conflicts of interest
- 45:42in the way that we approach even proposing projects to begin
- 45:46with, but and then everything else that we just talked about.
- 45:51South more rigour what? Andreas, what would you like to
- 45:53add to that? I love this conversation has
- 45:56been about you know what, What type of projects should we be
- 45:59making? How can we plan projects better?
- 46:03But we do spend quite a long time in the book talking about
- 46:06different types of measurements for projects that are already in
- 46:09flights. What should you be start
- 46:11starting to measure and how can you make, how can you make kind
- 46:15of metrics more, more decision driven?
- 46:20So we, we talked a little about, we, we have specific chapters
- 46:24about, you know, cost and schedule and benefits progress,
- 46:27typical things that you need to measure on, on projects and that
- 46:31it's really useful to measure. But one of the things we
- 46:34observed was that a lot of the metrics that are currently being
- 46:38used and on all sorts of dashboards, they're very kind of
- 46:44exploratory, as Doug would put it.
- 46:46So they're there because decision makers are project
- 46:50managers, are risk managers. They feel that once they know
- 46:53that once they look at the dashboard full of metrics and
- 46:56they see like the right combination of different figures
- 47:01and charts and, and metrics, they'll have some kind of
- 47:04they'll know what to do in that kind of instance.
- 47:06They'll know how to react on the metrics on the dashboard.
- 47:09But a lot of the time what we discovered was that a lot of the
- 47:12metrics aren't geared for decision making really, and not
- 47:16about, you know, what intervention decision or how
- 47:19should we react if we see a specific metric.
- 47:23So the book spends a lot of time thinking about, you know,
- 47:27progress metrics like cost performance indicators or
- 47:32scheduled performance indicators and so forth, and thinking
- 47:35about, well, how could we make it reframe that into something
- 47:38that is easier to understand. And a lot of that is reframing
- 47:43it into, well, how much productivity increase would we
- 47:46need to have to actually catch up on our delay, for example?
- 47:51So we do give a lot of advice in terms of how should you be
- 47:56measuring, how should you be presenting metrics?
- 47:59And I think the other thing in the book that we do is we be
- 48:02sure that because this is a book about measurement, there is some
- 48:07maths in it. But we do show that, you know,
- 48:10all this maths isn't complicated.
- 48:12So alongside the book, we have a website where you uploaded a
- 48:16whole bunch of spreadsheets to show that all these things.
- 48:19We talk about the technology regret example, we have an
- 48:23example of using machine learning for predicting
- 48:26outcomes. We have different types of
- 48:28simulation exercises and we run it all in Excel, which you can
- 48:33download and apply it to your projects just to show that.
- 48:36It sounds pretty complex if you're used to using more
- 48:39subjective scores and scales and risk matrices, but it actually
- 48:43isn't that difficult and there's a lot of already built solutions
- 48:48out there that you can just apply.
- 48:52If there's one thing you'd like readers to take away from your
- 48:56book, what what might that be, Andreas?
- 49:02So if, if I can positively frame it, because you've talked about
- 49:05issues a lot on this on this podcast so far, is that there is
- 49:09actually a lot of evidence, even though there's in the industry,
- 49:13there's a lot of claims around or if you just apply our methods
- 49:17or our tools or our software, you're going to better projects.
- 49:21That's typically what we see. If we go out to conferences and
- 49:24we look at like vendor stands, it's all the same software
- 49:26companies with some kind of reframing of if you use our
- 49:30products, you're going to deliver to cost into schedule,
- 49:33right? That'll be the typical
- 49:35experience. But there's so many claims out
- 49:38there can be quite difficult to find out what works and what
- 49:41doesn't. And what we've tried to do is
- 49:44actually just to look at the data.
- 49:46The research has already been done.
- 49:49We've done some of our own research and we've identified
- 49:52that, you know, some things are better than others in terms of
- 49:56measurement or estimating or delivering projects.
- 50:01So that there's there's an opportunity to apply the things
- 50:05that work and kind of toss the things that don't work.
- 50:09Fantastic. That's very well put.
- 50:12Thank you, Doug. Any any one message you'd like
- 50:16to get across to to listeners? Yeah, we, we refer to the the
- 50:22most important project, the one that is about making projects
- 50:26better. We call that the meta project in
- 50:29the book. And everybody ought to start
- 50:32thinking about their meta project.
- 50:33You know, no matter how big your project portfolio is, no, no
- 50:39matter how big the individual projects are, some time is worth
- 50:43being spent on the meta project. Your most important decision is
- 50:48how to make decisions. By the way, that's in life and
- 50:52business and government and everything.
- 50:53Your most important decision is how to make decisions.
- 50:56So we should apply that here. And so the meta project is, is
- 51:01the project about making all the other projects better.
- 51:04What's a great way to spend 1% of a whole project portfolio
- 51:09trying to optimise the other 99%?
- 51:11That's the best way to spend 1%, right?
- 51:14And it might be about that much for a lot of project portfolios.
- 51:18If you look at some of the infrastructure portfolios, you
- 51:21know, even spending 1% of those portfolios is a significant meta
- 51:25project where a lot of analysis could be done.
- 51:29And so we recommend having a project called the Meta Project
- 51:34and Everybody's portfolio. Thank you, Doug.
- 51:38I feel as though we've just scrape the surface of what we
- 51:42could talk about in your book. I feel like I might have to do a
- 51:45follow up podcast sometime soon. But thank you very much for your
- 51:49time. Thank you for your thoughts.
- 51:51I wish you best of luck with the book, but it's been really
- 51:55fascinating talking to you and I'm sorry we couldn't cover much
- 51:59more of what you've what you've put in the book, but thanks very
- 52:01much for your time today. You best text.
- 52:05Thank you. Thanks again to Doug and Andreas
- 52:09for joining us and to you for listening to the APM podcast.
- 52:12I hope you've been left with much food for thought, so don't
- 52:16forget to look out for more episodes, alterate and reviews.
- 52:18Wherever you get your podcasts. We'd welcome you to get in touch
- 52:22with your comments, feedback and suggestions by emailing us at
- 52:25apmpodcast@thinkpublishing.co.uk. Spotify and YouTube users,
- 52:30please do also leave us your comments.
- 52:33This podcast has been brought to you by APM, the chartered body
- 52:37for the project profession. For more information on APM,
- 52:40visit apm.org.uk.