- 0:00Speaker 1: Well, Cam, fixed price building contracts. That sounds you know,
- 0:04Speaker 1: pretty good on the surface, right does it? Does it?
- 0:06Speaker 2: Though? Well?
- 0:07Speaker 1: I think, and we're going to learn about this in
- 0:09Speaker 1: just a sec. Then there's a bit to dig down on,
- 0:11Speaker 1: a bit to investigate here, because I think there's a
- 0:13Speaker 1: few little hidden bits and pieces that might catch homeowners.
- 0:16Speaker 3: Out anytime I hear fixed price anything, Yes, warning signs exactly.
- 0:23Speaker 1: Adam Hoble, principal building designer, Adam Hoble Design and author
- 0:27Speaker 1: of the book Nail It is going to tell us
- 0:30Speaker 1: all about that, Adam, Good morning.
- 0:32Speaker 2: Good morning guys.
- 0:32Speaker 4: How are you good?
- 0:33Speaker 2: Now?
- 0:34Speaker 1: Look, we do hear it often fixed price contract? Is
- 0:39Speaker 1: that reassuring or not?
- 0:42Speaker 4: Well? Very good question, very good question.
- 0:46Speaker 2: The idea of a fixed price contract sounds great, no
- 0:49Speaker 2: doubt about that, and that's why homeowners love the idea
- 0:52Speaker 2: of them. But the understands there is no, they're not
- 0:56Speaker 2: They're not really as assuring or reassuring it they might sound.
- 1:01Speaker 2: Over ninety percent of residential building projects in Australia use
- 1:06Speaker 2: fixed price contracts, and almost none of them are truly fixed.
- 1:10Speaker 2: There are clauses written into these contracts. They're perfectly legal,
- 1:14Speaker 2: perfectly standard that mean the final cost can end up
- 1:18Speaker 2: a lot more than what you signed up for.
- 1:20Speaker 3: So what are some of the things that are hiding
- 1:22Speaker 3: inside one of these things? What should we be looking for?
- 1:27Speaker 2: Look, there's a couple of very simple little terms that
- 1:32Speaker 2: are are really important to understand on cost items and
- 1:37Speaker 2: provisional sums. You'll see them written as PC and PS
- 1:42Speaker 2: in the contract, and both fall into the broader terminology
- 1:45Speaker 2: of allowances. A PC item is basically a placeholder for
- 1:51Speaker 2: something in the build that you haven't chosen yet, things
- 1:54Speaker 2: like your taps, toilet appliances.
- 1:56Speaker 4: Flow tiles.
- 1:58Speaker 2: So the builder puts an allowance in the contract, and
- 2:00Speaker 2: if you end up choosing something that costs more than
- 2:02Speaker 2: the allowance, which is very easy to do when you're
- 2:05Speaker 2: standing in the bathroom showroom, that difference gets added to
- 2:09Speaker 2: your bill. An end of a contract, the builder can
- 2:12Speaker 2: also charge a margin of up to twenty percent on
- 2:14Speaker 2: top of that difference.
- 2:15Speaker 1: And look, I imagine correct me if I'm wrong, Adam, but
- 2:17Speaker 1: I imagine that those that allowance that they allow for,
- 2:21Speaker 1: you know, for taps and all those sorts of things,
- 2:23Speaker 1: would would that more often than not be for kind
- 2:26Speaker 1: of the real basic you know, standard kind of the risk.
- 2:30Speaker 4: Yeah, so this is this is where I guess we really.
- 2:32Speaker 2: Encourage our currents to be informed and kind of guide
- 2:37Speaker 2: that process to actually understand what is the reasonable cost
- 2:40Speaker 2: of a toilet? You know, if a builders putting in
- 2:43Speaker 2: an allowance of three hundred dollars for a toilet, then
- 2:45Speaker 2: he's kind of allowing a really basic entry level toilet.
- 2:49Speaker 2: So everythings you need to be aware of.
- 2:51Speaker 1: Okay, So when I'm after my brass lovely you know
- 2:54Speaker 1: tap that I want to get, I should just be
- 2:57Speaker 1: wary to put some extra cash aside.
- 2:59Speaker 4: Huh exactly?
- 3:00Speaker 2: So are there are things that we can can control
- 3:02Speaker 2: and guide to make sure that you know there are
- 3:04Speaker 2: no surprises lurking? Yeah?
- 3:06Speaker 3: I mean it sort of sounds reasonable though, doesn't it
- 3:09Speaker 3: Like a builder will put in the X amount, but
- 3:11Speaker 3: if you want more then you just have to.
- 3:14Speaker 1: Know about special defensey stuff.
- 3:16Speaker 2: Yeah, yeah, it is, it's reasonable a builder can't.
- 3:20Speaker 4: I mean. The other other term that we need to
- 3:24Speaker 4: be careful of is provisional some.
- 3:26Speaker 2: So we've got this idea of a PC and a
- 3:28Speaker 2: PS prime cost and provisional sum are provisional some is
- 3:31Speaker 2: the items that there's labor and material involved in so
- 3:37Speaker 2: things like kitchen joinery, a builder can't know for sure
- 3:41Speaker 2: how much you're going to spend on your kitchen because
- 3:43Speaker 2: it hasn't yet been designed. So it's perfectly reasonable to
- 3:46Speaker 2: use provisional sums, but they need to be done very
- 3:49Speaker 2: transparently and very clearly, and the client really needs to
- 3:52Speaker 2: make sure that they have an understanding of kind of what.
- 3:55Speaker 4: That money's like with to buy.
- 3:56Speaker 1: Yeah, absolutely, Adam, Just quickly, how do we sort of
- 3:59Speaker 1: avoid falling into these traps?
- 4:02Speaker 4: Ye, Two important things that you've got to get right
- 4:06Speaker 4: first before we.
- 4:06Speaker 2: Go anywhere near builder or builders. You've got to make
- 4:10Speaker 2: sure you've got your design and documentation sort of properly.
- 4:12Speaker 2: The more detail in your drawings and specifications, the lesser
- 4:15Speaker 2: in there is for vagueness and educated guesses in the quote.
- 4:20Speaker 2: As we said, the builders can only really price what
- 4:23Speaker 2: they are given, so if it's not in the documentation,
- 4:26Speaker 2: it's going to get missed or it becomes a guess.
- 4:29Speaker 2: And second, when you do get quotes, look really carefully
- 4:33Speaker 2: at how many provisional sums and prime costs are in
- 4:36Speaker 2: the quote and ask the builder to explain each one.
- 4:38Speaker 2: So you're looking for calculated estimates, not covered wild random guesses.
- 4:43Speaker 2: A well prepared quote should have as few provisional sums
- 4:47Speaker 2: as possible, especially for things that should reasonably be expected
- 4:50Speaker 2: to be quoted as fixed costs. And that's a big
- 4:53Speaker 2: part of what we do, making sure our clients are
- 4:55Speaker 2: really well prepared to get quotes that are thorough and
- 4:58Speaker 2: accurate and not exposed to those.
- 4:59Speaker 3: Blow prime costs provisional sums renee. When you see those words.
- 5:04Speaker 1: Ask the questions.
- 5:05Speaker 3: Ask the questions exactly.
- 5:08Speaker 1: That's been so interesting and informative. Thank you so much
- 5:11Speaker 1: for your time.
- 5:12Speaker 4: You're welcome, guys, have great weekend.
- 5:13Speaker 1: Sheers Adam Hobill, Principal building Designer, Adam Hobile Design. That's
- 5:17Speaker 1: really interesting, isn't it.
- 5:18Speaker 3: Cam Sure is