Latest / The Best of the Money Show / SA's first gas-to-power tender fails over supply concerns
Transcript
- 0:00Speaker 1: The Department of Electricity and Energy confirming no preferred bidders
- 0:03Speaker 1: have been appointed under the first round of the Gas
- 0:06Speaker 1: Independent Power Producer Procurement Program. I think if my memory's right,
- 0:11Speaker 1: the first gas procurement process was supposed to start nearly
- 0:14Speaker 1: 10 years ago. Jose Moleshe is an energy expert, joins
- 0:18Speaker 1: us now. Jose, good evening. It seems the real problem
- 0:21Speaker 1: here is that there's no reliable supply of gas. Is
- 0:25Speaker 1: that why no independent power producers came forward?
- 0:30Speaker 2: Good evening to you, Stephen, as well as the listeners.
- 0:33Speaker 2: The problem is yes and no. Yes, the problem is that,
- 0:39Speaker 2: in my view, that there's no proper coordination and proper
- 0:44Speaker 2: sequencing of the whole procurement program to enable certainty and
- 0:50Speaker 2: risk allocation to all the role players that could play
- 0:53Speaker 2: in this market. There is demand for guests. There's There's
- 0:57Speaker 2: no question about that. Industrial users are going to lose
- 1:02Speaker 2: their supply in 2028. That is coming from Mozambique. And
- 1:07Speaker 2: then you have ESCOM that requires the gas. And then
- 1:10Speaker 2: there are suppliers. Obviously, there were bidders, four bidders showing
- 1:14Speaker 2: that there's an interest. However, we don't have the infrastructure
- 1:17Speaker 2: that is required in the middle that will enable the
- 1:21Speaker 2: suppliers to take the gas to the users. and vice versa.
- 1:25Speaker 2: And why do we not have that? It's a bankability problem.
- 1:29Speaker 1: Is that a problem that can be easily fixed, or
- 1:31Speaker 1: should governments sort of abandon this process for the moment?
- 1:36Speaker 2: No, if you have four peters that are putting their,
- 1:39Speaker 2: it takes a lot of time, and backed by banks,
- 1:43Speaker 2: it takes a lot of time to be able to
- 1:45Speaker 2: prepare those kind of projects for bankability. That means that
- 1:48Speaker 2: there are serious players out there in the markets. What
- 1:51Speaker 2: is needed is for government to elevate this at a
- 1:54Speaker 2: higher level and coordinate with all the role players in
- 1:58Speaker 2: the market to make sure that they put together proper
- 2:01Speaker 2: risk allocation and proper ensuring that if they are anchor customers,
- 2:05Speaker 2: for instance, if they are anchor customers like ESCOM, the
- 2:09Speaker 2: industrial users, that government understand what the industrial users need.
- 2:13Speaker 2: need in terms of infrastructure? Or do they just go
- 2:17Speaker 2: and procure without understanding that? What is needed for the
- 2:21Speaker 2: guest suppliers to be certain that that demand is reliable,
- 2:27Speaker 2: you know, so that they build the infrastructure necessary? So
- 2:30Speaker 2: it's a question of coordinating all these things at a
- 2:34Speaker 2: higher level to be able to make sure that we've
- 2:37Speaker 2: got a bankable solution on the table. They did that
- 2:40Speaker 2: with the Renewable Energy IPP program. although these are not
- 2:43Speaker 2: the same, but they put a procurement framework that made
- 2:47Speaker 2: sense together so that this could be evaluated by lenders.
- 2:52Speaker 2: And that, in the end, is what led to successful procurement.
- 2:57Speaker 2: So every bit and pieces are all over the place
- 3:00Speaker 2: at this point in time.
- 3:00Speaker 1: There are certain advantages to gas. You can switch it
- 3:03Speaker 1: on and switch it off, and the moment you switch
- 3:05Speaker 1: it on, it works, unlike a coal-fired power station. You
- 3:08Speaker 1: don't have to worry about the weather. It doesn't rely
- 3:10Speaker 1: on the sun or the wind.
- 3:12Speaker 2: But.
- 3:13Speaker 1: ESCOM says it has too much electricity at the moment.
- 3:16Speaker 1: We have a lot more solar power being produced both
- 3:19Speaker 1: by IPPs and connecting that to the grid and by
- 3:23Speaker 1: people who just produce their own at the moment. Do
- 3:26Speaker 1: we need independent power producers using gas to actually generate electricity?
- 3:31Speaker 1: I mean, do we need that at the moment?
- 3:34Speaker 2: Yes, we do. We do need gas because right now
- 3:39Speaker 2: we have intermittency in terms of renewable energy. And you
- 3:43Speaker 2: find that during the time when the energy is needed.
- 3:49Speaker 2: And remember that we're not talking about developing this infrastructure today.
- 3:53Speaker 2: We're talking about 2030, somewhere there. So look at it
- 3:57Speaker 2: that way. So I guess we will always be able
- 4:00Speaker 2: to come in at those intervals because it has flexibility,
- 4:04Speaker 2: as you correctly point out. However, that could be a
- 4:08Speaker 2: challenge as well because you build infrastructure, you pay for infrastructure,
- 4:13Speaker 2: and you use it for only certain periods of time.
- 4:16Speaker 2: So that is why there needs to be coordination with
- 4:19Speaker 2: industrial users to understand their needs as well to fill
- 4:22Speaker 2: in the gap of investing in infrastructure and then supplying
- 4:26Speaker 2: very little gas. That's not a bankable solution. So that
- 4:29Speaker 2: is why we talk about coordination. What are the needs
- 4:32Speaker 2: of the industrial users? Can they pick up that gap
- 4:35Speaker 2: and how? So the minister just went out for only
- 4:40Speaker 2: the independent power producers not the whole market requirement. And
- 4:44Speaker 2: yet there's a certainty that industrial users are running out
- 4:47Speaker 2: of gas and they already employ a lot of people
- 4:50Speaker 2: in the industry. There's already companies that are functioning. We
- 4:54Speaker 2: forget that if that is not catered for, that's going
- 4:57Speaker 2: to have an impact on South Africa's market and competitiveness
- 5:02Speaker 2: in the long run. That's more serious than anything else.
- 5:05Speaker 1: Hmm. I mean, the process of people leaving the grid
- 5:08Speaker 1: and generating their own electricity, whether they be companies or
- 5:12Speaker 1: whether they be individuals and homeowners, has been so quick.
- 5:16Speaker 1: And yet most of that electricity really comes from solar.
- 5:20Speaker 1: Are we perhaps running the risk of getting ourselves into
- 5:22Speaker 1: a problem where we become not used to using the
- 5:26Speaker 1: grid and when we need it, we haven't invested enough
- 5:28Speaker 1: in the grid?
- 5:32Speaker 2: Well yeah i'm not sure i understand that what's the
- 5:35Speaker 2: question with that we might have too much.
- 5:38Speaker 1: So so people have have taken themselves off the grid
- 5:41Speaker 1: where they can lots of companies have done that they
- 5:43Speaker 1: okay most of that most of that generation is coming
- 5:45Speaker 1: from solar whether it be mines or homeowners they're all
- 5:48Speaker 1: using solar a moment could come where we're not investing
- 5:52Speaker 1: enough in the grid and something comes along and we
- 5:55Speaker 1: need to use it in other words One of the
- 5:57Speaker 1: things that government is supposed to do is make sure
- 5:59Speaker 1: that we have enough of a diversity of power supplies
- 6:04Speaker 1: that it's always going to work no matter what.
- 6:07Speaker 2: Absolutely.
- 6:08Speaker 1: Are we putting ourselves in a situation where we're not
- 6:10Speaker 1: doing that enough now?
- 6:12Speaker 2: Yes, because we are assuming also, I mean, unless we
- 6:15Speaker 2: assume an economy that will never grow, unless we assume
- 6:19Speaker 2: that there will be no data centers coming in, unless
- 6:21Speaker 2: we assume that they will always be in this situation.
- 6:25Speaker 2: And remember, we still have to decommission some of the plants.
- 6:28Speaker 2: So infrastructure is a long term. It has long lead times.
- 6:33Speaker 2: When you build today, you're not building for today. You're
- 6:35Speaker 2: building for a longer term, like 2030. So you have
- 6:39Speaker 2: to do your planning well in advance. Like the gas
- 6:42Speaker 2: is going out for industrial users in 2028, and you
- 6:46Speaker 2: still have not got a proper procurement program on the table.
- 6:50Speaker 2: So that means that the risk is there. We also
- 6:53Speaker 2: have a risk when it comes to transmission infrastructure, which
- 6:57Speaker 2: we are still trying to procure. So all of these
- 7:00Speaker 2: things could find us wanting as a country.
- 7:04Speaker 1: Thank you so much, energy expert. Really appreciate your time
- 7:07Speaker 1: on The Money Show tonight.