Latest / NWPPA Morning Brief / NWPPA Morning Brief - Wednesday, November 04, 2026
Transcript
- 0:00SPEAKER_00: Before we begin, a quick note.
- 0:01SPEAKER_00: The NWPPA morning brief is Generative AI, daily intelligence on the federal and Western developments shaping public power.
- 0:09SPEAKER_00: It isn't human-reviewed before publication, so treat it like any AI tool and verify what you'll act on or cite.
- 0:16SPEAKER_00: Sources are in the show notes.
- 0:18SPEAKER_00: You're listening to the NWPPA morning brief.
- 0:21SPEAKER_00: On today's brief, PJM's data center backstop procurement collapses by up to 90% in a revised FERC filing.
- 0:29SPEAKER_00: Shallan PUD files post-license power sales contracts for Rock Island.
- 0:34SPEAKER_00: Wyoming signs a uranium permitting agreement under FAST 41.
- 0:38SPEAKER_00: Rocky Mountain Power faces a formal state investigation over industrial customer treatment.
- 0:43SPEAKER_00: Montana's Northwestern merger vote gets pushed again, and Exelon discloses up to$8 billion in regulated storage tied to the PJM supply crunch.
- 0:53SPEAKER_00: Today's briefing is brought to you by NWPPA's January Conference Series, covering three of the biggest issues facing utilities right now: wildfire risk, data centers and load growth, and power supply.
- 1:06SPEAKER_00: Three conferences, three days, one trip to Portland, January 26th through 28th.
- 1:11SPEAKER_00: Register at nwppa.org.
- 1:15SPEAKER_01: The PJM Data Center backstop story is the one to watch closely today.
- 1:19SPEAKER_01: The gap between 6,800 MW and 630 MW is not a rounding error.
- 1:25SPEAKER_01: It is a signal about how fast large load forecasts can move, and FERC's response will set national precedent.
- 1:33SPEAKER_00: Let's get into it.
- 1:34SPEAKER_01: Start with the PJM backstop filing.
- 1:37SPEAKER_01: PJM went back to FERC on October 29th with a scaled-back version of its reliability backstop procurement plan, the special auction designed to secure capacity for data center load.
- 1:47SPEAKER_01: The original target was 6,800 megawatts.
- 1:50SPEAKER_01: The revised floor is as little as 630 megawatts after utilities in PJM's footprint cut their large load forecasts.
- 1:58SPEAKER_01: FERC had already rejected most of the original plan in late September, flagging concerns that the cost allocation, transmission owner exit rules, and collateral requirements may have been unjust and unreasonable.
- 2:10SPEAKER_00: The revised filing tightens what PJM calls cost causation, the principle that costs should fall on the customers who drive them, and it lets backstop obligations and collateral follow a large customer when it switches load-serving entities.
- 2:24SPEAKER_00: That is a real structural fix.
- 2:26SPEAKER_00: But the 90% drop in the procurement target is the number that lands hardest for resource planners in the West.
- 2:33SPEAKER_00: Announced data center pipelines and actual committed dispatchable load are not the same number, and PJM is proving that in real time.
- 2:41SPEAKER_01: Western RTO proceedings will draw directly on whatever FERC approves here.
- 2:46SPEAKER_01: The cost causation framework, the collateral rules, the question of who pays when a large customer moves, those are live questions in Western markets too.
- 2:55SPEAKER_01: The procurement process is targeted to begin March 1st, so FERC's response lands soon.
- 3:00SPEAKER_00: And the precedent risk is real.
- 3:02SPEAKER_00: If FERC blesses a structure where large load cost exposure stays tightly tied to the customer who drove it, that is a better outcome for public power utilities serving existing ratepayers.
- 3:12SPEAKER_00: If the framework leaks costs onto the broader load base, that is a different conversation entirely.
- 3:19SPEAKER_01: Moving to the Rock Island contracts, Shellan County PUD filed three applications with FERC on October 16th, seeking approval of power sales contracts from its Rock Island hydroelectric project on the Columbia River.
- 3:31SPEAKER_01: The contracts extend beyond the expiration of Rock Island's existing license.
- 3:36SPEAKER_01: The Federal Register Notice, published November 3rd, opens the formal window for comments, protests, and motions to intervene, the step by which parties get on the record.
- 3:46SPEAKER_00: Section 22 of the Federal Power Act requires joint approval from FERC and the state authority for sales extending past a license's termination.
- 3:55SPEAKER_00: For Columbia Basin Utilities and Bonneville Power Administration customers, Rock Island is a significant mid-Columbia project, and how that post-license output gets marketed is a near-term market signal.
- 4:07SPEAKER_00: The intervention window is where parties with a wholesale interest stake their position.
- 4:12SPEAKER_01: Turning to Wyoming's uranium permitting move, Governor Mark Gordon and the Federal Permitting Improvement Steering Council signed a memorandum of understanding on October 26th to bring Wyoming infrastructure projects, including uranium mining, under FAST 41.
- 4:28SPEAKER_01: That is the federal framework from the 2015 FAST Act that coordinates federal and state permit reviews to shorten approval timelines.
- 4:37SPEAKER_01: Gordon said all new projects in the state going forward will be subject to it.
- 4:41SPEAKER_00: Wyoming is the largest uranium-producing state in the country, so a formalized permitting pathway there matters for the domestic nuclear fuel supply chain.
- 4:50SPEAKER_00: Utilities evaluating small modular reactors or other advanced nuclear options depend on that chain.
- 4:57SPEAKER_00: And faster permitting in Wyoming is a factor in long-range fuel sourcing decisions.
- 5:02SPEAKER_00: The MOU also opens access to federal funding and technical support for qualifying projects.
- 5:08SPEAKER_01: Over to Wyoming's regulatory front, the Wyoming Public Service Commission voted unanimously to open a formal investigation into whether Rocky Mountain Power, the Pacific Corps subsidiary, followed its tariffs and treated industrial customers fairly on requests dating back to January 2022.
- 5:26SPEAKER_01: Rocky Mountain Power President Dick Garlish called the probe unnecessarily burdensome and punitive and noted no formal complaint has been filed.
- 5:34SPEAKER_00: PSC Deputy Chairman Chris Petrie said a general investigation is the only way to determine whether widespread complaints have merit.
- 5:42SPEAKER_00: PSC Chief Counsel John Burbridge described it as fact-finding on large load requests and tariff compliance.
- 5:48SPEAKER_00: For Western Public Power, this proceeding matters because it is a live test of how a state commission scrutinizes an investor-owned utility's handling of large load interconnection and pricing, the same operational and tariff questions that come up when any utility cites a megaload project.
- 6:05SPEAKER_00: The Wyoming record will be on the shelf when peer commissions face similar reviews.
- 6:10SPEAKER_01: Shifting to Montana, the Montana Public Service Commission postponed its vote on the$15.4 billion Northwestern Energy Black Hills Corp merger until November 10th.
- 6:21SPEAKER_01: Commissioner Jennifer Fielder requested more time to propose an additional condition tied to concerns raised by two groups that have opposed the deal.
- 6:30SPEAKER_01: PSC legal and regulatory staff have recommended approval with conditions aimed at insulating Northwestern's Montana assets from parent company financial activity.
- 6:41SPEAKER_01: Montana Consumer Council also supports approval.
- 6:44SPEAKER_00: Nearly 30 public commenters urged rejection, pointing to data center load growth and potential rate effects.
- 6:51SPEAKER_00: The November 10th vote is the next hard decision point.
- 6:54SPEAKER_00: Whatever conditions the final order carries will shape how a combined entity interacts with public power counterparties across the region.
- 7:01SPEAKER_00: Wholesale contract terms, transmission access, cost allocation.
- 7:06SPEAKER_00: So the condition language matters as much as the outcome.
- 7:09SPEAKER_01: Next up, the Exelon storage announcement.
- 7:12SPEAKER_01: On an October 30th earnings call, Exelon officials disclosed that the company's utilities could spend$3 billion to$7 billion building 1.5 to 3.5 gigawatts of regulated energy storage on top of a separate$1 billion, 500 megawatt battery project proposed by Atlantic City Electric in New Jersey.
- 7:32SPEAKER_01: CEO Calvin Butler said PJM is not adding generation fast enough.
- 7:36SPEAKER_01: CFO Robert Klitschinski said regulated storage, built and owned inside the utilities rate base rather than developed by independent merchants, gives the company certainty that projects get built and control over deployment.
- 7:49SPEAKER_00: The New Jersey Board of Public Utilities is expected to decide on the Atlantic City Electric project late in the first quarter of next year.
- 7:57SPEAKER_00: The question Exelon is testing is whether regulated utility ownership can get storage financed and cited faster than merchant development.
- 8:04SPEAKER_00: Western public power utilities with battery storage in their IRPs are weighing a version of that same question from a different starting point.
- 8:12SPEAKER_00: Rate-based treatment, member benefit allocation, and procurement timing all look different when you are a consumer-owned utility.
- 8:20SPEAKER_01: And the connection back to PJM's backstop collapse is worth noting.
- 8:23SPEAKER_01: The same large load forecast volatility that drove the procurement target down from 6,800 megawatts to 630 megawatts is also the driver Exelon is citing for its storage buildout.
- 8:35SPEAKER_00: The uncertainty itself is becoming a capital allocation signal.17 per barrel, down from$98.77.
- 9:00SPEAKER_01: Western spot prices for November 3rd delivery, SUMUS Natural Gas was$2.33 per million BTU, and Mid-Columbia Power was$54 per megawatt hour.
- 9:11SPEAKER_01: On the capital side, the 10-year treasury yield was 4.91% on November 2nd, down from 4.94%.
- 9:19SPEAKER_01: Comex Copper settled at$6.44 per pound on November 3rd, up from$6.38.
- 9:27SPEAKER_01: One to watch.
- 9:28SPEAKER_00: The thread connecting PJM's backstop collapse and Exelon's storage announcement is worth sitting with.
- 9:33SPEAKER_00: PJM started this process trying to backstop 6,800 megawatts of data center load.
- 9:39SPEAKER_00: After utilities revised their forecasts downward, that number fell to as little as 630 megawatts.
- 9:45SPEAKER_00: At the same time, one of PJM's largest utilities is committing up to$8 billion to build regulated storage in response to a generation shortfall that may or may not materialize at the originally projected scale.
- 9:58SPEAKER_00: The question for Western resource planners is how to size commitments, generation, storage, transmission, when the demand signal is this unstable.
- 10:07SPEAKER_01: The FERC proceeding on PJM's revised filing will be the first major test of whether a national framework for cost causation on large load capacity can survive the volatility in the underlying forecasts.
- 10:20SPEAKER_01: If the allocation rules hold, even when forecast volumes shift by 90%, that is a durable structure.
- 10:27SPEAKER_01: If FERC has to revisit the framework every time the load forecast moves, Western utilities are watching a template they may not want to replicate.
- 10:35SPEAKER_00: Today's stories share a common fault line.
- 10:38SPEAKER_00: Forecast uncertainty is forcing decisions at every level of the system.
- 10:43SPEAKER_00: PJM is repricing a procurement target in real time.
- 10:47SPEAKER_00: Montana regulators are adding conditions to a merger that may look different depending on how data center load actually lands.
- 10:54SPEAKER_00: Wyoming is building a permitting infrastructure for a fuel supply chain whose demand curve depends on how many advanced nuclear units actually get built.
- 11:03SPEAKER_00: The decisions being made right now are carrying a lot of load on projections that are still moving.
- 11:08SPEAKER_01: And the public power utilities sitting on the other side of those decisions, managing rates for real customers, filing contracts, participating in RTO proceedings, are the ones who absorb the difference between the forecast and the outcome.