Palm Bay Council Preview: No Vote on 911 Dispatch, $1.13M Western Parkway Widening, and an Appointed Board Power Shift
PALM BAY, FL — The promised 911 dispatch vote vanishes from the docket, while council advances $1.13M in Parkway widening and a quiet shift in zoning power.
Key Takeaways:
• Parkway Widening (Project 24PW03): Supplemental Agreement #1 allocates $430,331 to finalize engineering permitting and clear the corridor for multi-lane widening. The cost is split evenly: $215,165 from Nexus 32907 (Northwest) and $215,165 from Nexus 32908 (Southwest).
• Malabar Road Roundabout (Project 26PW03): The measure allocates $700,000 for initial civil engineering and intersection design at St. Johns Heritage…