- 0:05Yorkville OK's contract for more environmental testing as part of Downtown Hazard
- 0:09Cleanup. This article is being read by an automated
- 0:16voice, brought to you by Everlit. As part of the 4.3 million
- 0:21revitalization project of the hydraulic district into an entertainment and recreational hub,
- 0:27Yorkville, will have to invest more in the significant environmental hazard cleanup
- 0:32of the area before any development can begin. Holes were drilled beneath
- 0:36the downtown parking area in Yorkville, but the underground pollution proved too
- 0:41extensive to map out. Holes were bored, air, soil, and water samples
- 0:46were examined for pollution across the downtown FS property located along Van
- 0:50Emman Street, but another eighty-six thousand dollars with Terracon Consultants is needed
- 0:56to find The pollution, map it out, and develop a remediation plan.
- 1:00A remediation plan is key to the Illinois Environmental Protection Agency green
- 1:05lighting any future work on the Brownfield site. The contract approved by
- 1:10the city council is on top of a previous 100,000 contract with
- 1:14Terracon approved last August, which failed to establish a detailed enough pollution
- 1:20plan to move forward. City Administrator Bart Olson said the new environmental
- 1:25samples will be more in-depth, better defining where The pollution is located,
- 1:29and how best to clean up the brownfield site. The contract includes
- 1:33testing at 29 locations within the site. We had not done any
- 1:38testing down there for over a decade, Olson previously said. The pollution
- 1:43migrated. The
- 1:44amount of tests that we did wasn't detailed enough for us to
- 1:47be able to get a site remediation plan. Olsen said having the
- 1:51IPA sign off on a remediation plan opens up the site for
- 1:54potential state grant funding. The additional round of testing is expected to
- 1:59take around eight to twelve weeks. The IPAR review is expected to
- 2:02take another twelve to sixteen weeks before the remediation process can actually
- 2:07begin. Once the AIPA goes over the pollution findings, the city will
- 2:12either get clearance to move the contaminated soil or clean it up
- 2:16further. The severity of environmental pollution discovered in the soil gas, and
- 2:21groundwater studies will determine the extent of the necessary cleanup and the
- 2:25timeline of the hydraulic district's rejuvenation project going forward. Why it's taken
- 2:30time. It is difficult to map the underground pollution at the popular
- 2:34social site behind Rowdy's adjacent to Southbank original barbecue because for decades
- 2:40the soil soaked up agricultural and industrial chemical products. The FS property
- 2:45included a lumber yard, feed mill, equipment repair services, fertilizer supply, animal
- 2:50feed supply, diesel fuel supplies for local farmers, and A distributor of
- 2:54kerosene, oil, and gasoline. New pollutants from these services ceased in 2000.
- 3:00But chemical, metal, and organic contaminants remain in the soil requiring remediation.
- 3:06Also located in the Hydraulic District is the former Kendall County Farm
- 3:11Bureau building, which has been used as a cold storage facility, slaughterhouse,
- 3:15food pantry, and a meat processing facility. A large portion of the
- 3:20area features a public parking lot, which was first paved in 2000.
- 3:25An additional 21,500 is needed to remove concrete foundation walls beneath the
- 3:31walking lot, according to city documents. Plans for a renewed downtown area
- 3:35City officials have envisioned the site as key to revitalizing the downtown
- 3:39area. City plans propose a music stage, an events plaza, and renovated
- 3:44businesses and walkways. In May 2025, the city was awarded a 3
- 3:50million Illinois Transportation Enhancement Program grant to revitalize the downtown area, including
- 3:56new walking and biking paths, improved safety features, and aesthetic improvements like
- 4:01outdoor lighting and decorative pavers and entryways. City planners hope this will
- 4:07someday spur mixed-use residential and commercial developments near the Fox River. The
- 4:12city has been trying to start the cleanup as early as 2016
- 4:16and was finally able to move ahead once it bought the downtown
- 4:19FS property in 2024. The entire site is located west of Illinois
- 4:25Route 47 between East Hydraulic Avenue and East Van Emmen Street. Olson
- 4:30said the site is currently TIFF eligible, which should help mitigate the
- 4:34city's costs. As part of the rejuvenation project, the parking lot would
- 4:39be scaled down, with expanded parking spaces placed in adjacent areas, including
- 4:44along the river. The city has been working with different private and
- 4:48public property owners over decades, along with seeking grant funding, to plan
- 4:53a course of action, Olson said.