- 0:00We've implemented this exact process with dozens of general
- 0:03contractors. And the result?
- 0:05Faster estimates, better clients, and actually more time
- 0:09to help grow the business. I've been walking you through it
- 0:12step by step. Great thing about this process
- 0:15is it's it's very simple to conceptualize.
- 0:18There is 3 different levels of estimating that you're gonna
- 0:21provide to a client and each one helps bring the client to the
- 0:24next stage or weeds out the clients that either budget is
- 0:28out of whack or you don't want to be working with.
- 0:30So first of all, bring me talking about is the ballpark
- 0:33budget. This one is a quick budget
- 0:36you're going to do typically at the clients house or you know,
- 0:40insert inside the first sort of initial meeting and it's to take
- 0:44maybe 5, 10 minutes. You're gonna use some sort of
- 0:47spreadsheet or maybe like a quick go to template that you
- 0:49have in your project management software.
- 0:51And what you're doing here is just using a very broad brush as
- 0:54far as figuring out, you know, how many square feet is this
- 0:58home for a new home build. So you know, square foot times
- 1:01price, this is going to cost you $600,000 or if it's a remodel,
- 1:05you know, the size of kitchen, you're just very ballpark.
- 1:09The idea is you're going to provide the client some sort of
- 1:12a range of costing. So Mr. and Mrs. Smith, you know,
- 1:17this new home build that you're talking about based off the
- 1:20square footage. And then so your location where
- 1:22you know, probably in the ballpark range of 600,000 to
- 1:26$750,000 to, to build this home is that sort of in the, in the,
- 1:30you know, budget that you envisioned, right.
- 1:32So this is a real easy step to give them some sort of number
- 1:36you're looking to be within maybe 15% or so of, of what you
- 1:39know, the final cost could be for them.
- 1:42And it really is quick. You give them a price that's
- 1:45free and you can see if this is something that is worth pursuing
- 1:49further or if you know, we need to go back to the drawing board
- 1:52because they're expected budget is nowhere near the actual cost
- 1:56that you know it's going to take to build their project.
- 2:01Alright, so that's the first level of estimate.
- 2:03The second level of estimate that you're going to provide to
- 2:05a client is a rough budget. So this is going to be something
- 2:08that's detailed. You're going to work from a
- 2:10template you're using sort of base pricing.
- 2:13The idea with this rough budget is let's say you go to an auto
- 2:17dealer, you're going to buy a brand new car.
- 2:19You know, you're excited, you saw the advertisement, MSRP
- 2:23$30,000 for this new car. Of course, when you go to the
- 2:26dealership to buy the car, you're going to want, you know,
- 2:29the hill 17 inch rims where the sunroof for extended warranty
- 2:33here, you know, there's all these kind of different things.
- 2:35So they're gonna advertise the price 30,000.
- 2:38But of course you know, you're more than likely going to want a
- 2:40few upgrades or a few additional things that's going to bump up
- 2:43the price to maybe 35 or 40,000, you know, depending on what you
- 2:47know, extra stuff you get. So this is the idea of the rough
- 2:50budget you're providing that kind of that baseline base
- 2:53build, standard items, allowances, things like that.
- 2:58The idea is you want kind of like the very sort of lowest
- 3:02cost that you can provide this this budget or this project to
- 3:06the client for because you don't want to scare them off, but you
- 3:09do want to give them a lot of detail.
- 3:11So that's why you're going to provide an actual, you know,
- 3:14written estimate budget, all the different line items in there.
- 3:17And the goal of this one is hopefully you're within
- 3:20somewhere like 10%, you know, obviously the more close to the
- 3:24better. But if you're within 10% of the
- 3:26final budgeting, which I'm gonna get to step number 3IN in a
- 3:29minute here, where you get more refined that you're in, you're
- 3:32in a good place. And this gives the client enough
- 3:35to see that you've put in the detail, you put in the work.
- 3:37You know, you've done takeoffs. So you're using specific square
- 3:41footages for all the different parts of the project, but you're
- 3:44not going out and getting supplier clothes.
- 3:46You're not doing going through selections of specific things
- 3:49that that the client wants and the project.
- 3:51I don't not doing bid requests for subcontractor pricing and
- 3:56stuff like that. That's something that we're
- 3:58going to get to in the next step.
- 4:00And from here the goal is that you provide this to the client.
- 4:05Typically you're going to do it for free.
- 4:06It should take maybe one to two hours if you're really good and
- 4:09got a template and it's like a standard project, maybe even do
- 4:11it in less, but it's very it's fairly quick.
- 4:15Typically this is free and the purpose is to move the client
- 4:18then into pre construction service agreement.
- 4:21And the PC USA is sort of that next step and ensures that
- 4:24you're actually going to get paid for the drill down
- 4:27budgeting, which is coming up to #3 here.
- 4:30So the drill down budgeting and ideally if your process in
- 4:34place, you've got a preconstruction agreement.
- 4:36So you're getting paid for the time that you're putting in.
- 4:38So you don't mind going into the level of detail and working
- 4:41through the with the client or their designer or your designer
- 4:45with the selections and different things.
- 4:47And this is probably going to take anywhere from 5 to 10 plus
- 4:50hours depending on the complexity of the project and
- 4:53how much your communication you have back and forth with the
- 4:55client and things like that. But you're gonna go through
- 4:59selections, you're gonna tender our bids to your subcontractors,
- 5:02get their pricing and supplier quotes for specific materials
- 5:07that are going into the project. And you're helping sort of value
- 5:11design. And if the scope changes, you
- 5:14know the client. The good thing about this like 3
- 5:17tiered level estimating is that the client is always going to
- 5:21know sort of right away, you know, what the base price is and
- 5:26then they can see how their selections or their input
- 5:29affects the price. So you're not kind of getting
- 5:32all the way to the end with this huge sticker shock.
- 5:34There's been an iterative process.
- 5:36The clients knows like first, you know, ballpark range.
- 5:40Yeah, seems OK. You move on to the next step.
- 5:42Rough budget. Yeah, that looks like feasible.
- 5:45Good. And you move on to the next
- 5:47thing to drill down. So by the time you get to the
- 5:49construction contract that you've already worked with the
- 5:52client for potentially months if you're going through the whole
- 5:57construction process and it should be a very easy transition
- 6:00then for them to sign for the construction contract.
- 6:04So if you want more help with this and you want to learn how
- 6:08to get a preconstruction process in place, go check out this next
- 6:14video. We guide you through how to
- 6:16build a pre construction service agreement and process to help
- 6:20you know, give you a high converting process that you can
- 6:22sell the client into the construction process plus get
- 6:25paid for the estimating, the budgeting, the scheduling, all
- 6:28that stuff for the preconstruction.