- 0:00SPEAKER_01: Before we begin, a quick note.
- 0:01SPEAKER_01: The NWPPA morning brief is Generative AI, daily intelligence on the federal and Western developments shaping public power.
- 0:09SPEAKER_01: It isn't human-reviewed before publication, so treat it like any AI tool and verify what you'll act on or cite.
- 0:16SPEAKER_01: Sources are in the show notes.
- 0:18SPEAKER_01: You're listening to the NWPPA morning brief.
- 0:22SPEAKER_01: On today's brief, DOE orders AI data centers on to backup diesel generators as PJM braces for an all-time demand record.
- 0:31SPEAKER_01: Senator King asks FERC to block the next-era Dominion merger.
- 0:35SPEAKER_01: A uranium project clears federal permitting.
- 0:38SPEAKER_01: Rocky Mountain Power activates a wildfire shutoff warning in southern Utah.
- 0:42SPEAKER_01: Montana residents pursue supermajority ballot approval for data center sighting.
- 0:47SPEAKER_01: A joint action agency and municipal utility announce a major battery storage partnership, and the renewable tax credit clock runs out in three days.
- 0:56SPEAKER_01: Today's briefing is brought to you by NWPPA's Women in Public Power Conference, July 28th to 30th in Santa Rosa, California.
- 1:04SPEAKER_01: Three days of connection, candid conversation, and community by and for the Women of Public Power.
- 1:10SPEAKER_01: Register at NWPPA.org.
- 1:13SPEAKER_00: The DOE emergency order story is the one that should stop every executive reading a large load interconnection agreement today.
- 1:20SPEAKER_00: DOE has now used its Section 202C Emergency Authority, the statutory power to compel generation to run when reliability is at risk, three times in PJM alone this year.
- 1:32SPEAKER_00: This time it's not just coal plants being forced to run past retirement, it's private backup generators at AI data centers being commandeered to get through a peak demand event.
- 1:41SPEAKER_00: That is a materially different application of emergency authority, and the precedent it sets for the Western Interconnection is not theoretical.
- 1:49SPEAKER_01: The cost question makes it worse.
- 1:51SPEAKER_01: Craig Station still has no resolution on who pays when DOE forces a plant to run against the owner's economic preference.
- 1:58SPEAKER_01: Until that gets settled, every utility sitting on a legacy resource agreement or a large load deal needs to understand that the federal government can rewrite the operating dispatch with no clear reimbursement path yet established.
- 2:10SPEAKER_00: Let's start with the DOE and PJM story in full.
- 2:13SPEAKER_00: DOE issued two emergency orders on June 30, directing PJM to force AI data centers and large commercial loads onto backup diesel generators through July 3.
- 2:25SPEAKER_00: PJM is projecting an all-time peak load of 166,304 MW on Thursday, just above the prior record of 165,563 MW set in 2006.
- 2:39SPEAKER_00: This is the third 202C order to PJM in 2026.
- 2:44SPEAKER_00: DOE has now used this authority to dispatch coal units and, separately, to commandeer private backup generation at large loads, two distinct applications of the same statutory tool.
- 2:56SPEAKER_01: For Western public power utilities, the immediate question is how a similar directive would land on your existing tariff provisions and behind-the-meter generation terms.
- 3:05SPEAKER_01: If you have data center interconnection agreements, pull the language on backup generation obligations now, before a heat event forces the question under pressure.
- 3:14SPEAKER_01: The federal government has demonstrated it will move fast.
- 3:18SPEAKER_00: Turning to the Next Era Dominion merger, Senator Angus King formally asked FERC on June 29th to reject the planned$67 billion deal, citing what he described as next era's anti-competitive conduct in New England, specifically its opposition to the New England Clean Energy Connect transmission project.
- 3:37SPEAKER_00: The combined company would bring roughly 110 gigawatts of generation and 10 million utility accounts under one roof.
- 3:45SPEAKER_01: The merger application hasn't even been filed at FERC yet, so King is getting in early on the record.
- 3:51SPEAKER_01: The wholesale market concentration question is legitimate regardless of the political framing.
- 3:56SPEAKER_01: When merchant generation, rate-based generation, and transmission ownership consolidate at that scale, the leverage on competitive markets shifts.
- 4:04SPEAKER_01: Western public power utilities don't sit in Next Era or Dominion Territory.
- 4:08SPEAKER_01: But the precedent FERC sets on market power analysis here will reverberate in future consolidation reviews.
- 4:15SPEAKER_00: Moving to the uranium permitting story, the Dewey Burdock N-C2 Recovery Uranium Project in South Dakota cleared its full federal permitting process on June 30th, the first South Dakota project to complete the FAST-41 coordinated federal review track designed to accelerate infrastructure approvals.
- 4:34SPEAKER_00: Ncor Energy Corp will recover uranium from subsurface sandstone using N-C2 recovery technology.
- 4:41SPEAKER_01: This is one data point in a longer supply chain buildout, but for utilities actively modeling SMR capacity in their IRPs, domestic uranium production milestones matter.
- 4:52SPEAKER_01: The fuel supply question is real.
- 4:54SPEAKER_01: You can license a reactor faster than you can stand up a reliable domestic fuel chain.
- 4:59SPEAKER_01: And that sequencing risk is worth tracking in your resource planning assumptions.
- 5:04SPEAKER_00: Shifting to Rocky Mountain Power.
- 5:07SPEAKER_00: The utility activated a 48-hour public safety power shutoff warning for roughly a dozen southern Utah cities: Cedar City, Milford, Moab, Price, Vernal, temporarily affecting more than 7,700 customers while monitoring wind-driven fire conditions.
- 5:24SPEAKER_00: Their spokesperson noted this was the third such watch in four years, using in-house meteorologists and hundreds of pole-mounted weather stations to build rolling five-day forecasts.
- 5:35SPEAKER_01: The operational playbook here, 48-hour watch, 24-hour customer notice, targeted de-energization, is becoming the regional reference model for public safety power shutoffs.
- 5:46SPEAKER_01: Public power utilities serving overlapping territory in Utah, Nevada, and the Interior West are working with the same dry vegetation and wind event conditions.
- 5:56SPEAKER_01: If you haven't formalized your own shutoff protocol and your vegetation management review cycle, Rocky Mountain Power's framework is worth benchmarking against.
- 6:31SPEAKER_00: Northwestern Energy has said it is in discussions with at least 11 data centered developers about Montana projects.
- 7:00SPEAKER_01: That tension between democratic sighting control and utility service obligation has no clean answer, and it's coming to a head in Montana this fall.
- 7:09SPEAKER_00: Next up, the Seven States Power and Nashville Electric Service Story.
- 7:14SPEAKER_00: Seven States Power Corporation, a joint action agency, announced on June 30th it will partner with Nashville Electric Service to deploy large-scale battery storage under the Energy Express project, targeting peak demand and grid resiliency.
- 7:28SPEAKER_00: This is outside the Western footprint, but the structure matters.
- 7:31SPEAKER_01: The Joint Action Agency plus Municipal Utility Procurement Model is directly applicable here.
- 7:37SPEAKER_01: Pooling capital through a joint action agency reduces individual member exposure on a large storage build.
- 7:43SPEAKER_01: That's the straightforward read.
- 7:45SPEAKER_01: Western public power entities working through their own storage acquisition strategies should look at how seven states structured the risk sharing before designing their next RFP.
- 7:55SPEAKER_00: On the pricing front, Front Month Henry Hub Natural Gas Futures were trading at$3.24 per million BTU on July 1st, down from$3.25.
- 8:06SPEAKER_00: NYMEX WTI Front Month Crude Futures were trading at$68.91 per barrel on July 1st, down from$71.51.
- 8:17SPEAKER_01: On the capital and material side, the 10-year Treasury yield was 4.38% on June 29.
- 8:24SPEAKER_01: COMEX Copper settled at$6.15 per pound on June 30th, down from$6.19.
- 8:32SPEAKER_00: Turning to the congressional scan, developers of wind and solar projects across the West are racing to bring systems online before the July 4th deadline under the one big beautiful bill, which accelerated the phase out of Biden-era renewable energy tax credits.
- 8:47SPEAKER_00: Minnesota's Commerce Commissioner noted that grid interconnection, not the tax deadline itself, is proving the binding constraint on projects reaching commercial operation in time.
- 8:56SPEAKER_01: That's the detail public power counterparties need to be pressure testing right now.
- 9:00SPEAKER_01: If your renewable power purchase agreement has developer milestone commitments tied to tax credit eligibility, the question is whether your counterparty can actually hit commercial operation.
- 9:11SPEAKER_01: And what happens to contract pricing if they can't?
- 9:14SPEAKER_01: Interconnection queue timing is outside the developer's control, and that's where deals fall apart.
- 9:20SPEAKER_00: The other federal story today is Craig Station.
- 9:23SPEAKER_00: DOE Secretary Wright confirmed his agency is in dialogue with Tri-State Generation and Transmission Association about cost allocation for Craig's forced extension through September 26th.
- 9:34SPEAKER_00: Right now, Tri-State and its consumers, along with the other owners, are bearing those costs.
- 9:39SPEAKER_00: Tri-State wants that to change.
- 9:41SPEAKER_01: This is the live test case for the entire 202C cost recovery question.
- 9:47SPEAKER_01: DOE has compelled Craig in Colorado, Centralia in Washington, and now Backup Diesel Dispatch in PJM, and there is still no settled framework for reimbursing owners who didn't want to run.
- 9:59SPEAKER_01: How Craig resolves will set the reference point for every future emergency order.
- 10:03SPEAKER_01: Watch it closely.
- 10:05SPEAKER_00: One to watch.
- 10:12SPEAKER_00: DOE's 202C Emergency Authority has now been used to commandeer private backup generation at data centers, a new application of a tool already used three times in 2026.
- 10:24SPEAKER_00: Simultaneously, Montana citizens are pursuing direct democracy governance that could make data center siting contingent on two-thirds voter approval.
- 10:33SPEAKER_00: On the operational side, federal emergency authority can override normal grid service arrangements with no clear reimbursement path.
- 10:41SPEAKER_00: On the siting side, local communities are reaching for blunt instruments to slow hyperscale load growth.
- 10:47SPEAKER_00: Public power utilities sit in the middle, serving load service obligations while managing both federal intervention risk and community governance pressure.
- 10:55SPEAKER_01: The two developments haven't intersected yet, but they're moving toward the same pressure point.
- 11:00SPEAKER_01: If a data center gets cited over community opposition, or can't get cited at all, and then federal emergency authority commandeers adjacent generation assets to keep it running, the political and operational fallout lands on whoever is the serving utility.
- 11:15SPEAKER_01: That's a scenario worth gaming out now, not after the first Montana ballot initiative passes.
- 11:21SPEAKER_00: The through line today is that Federal Emergency Authority is expanding in practice faster than the cost and governance frameworks can keep up.
- 11:29SPEAKER_00: Craig still has no cost recovery answer.
- 11:32SPEAKER_00: PJM data centers are on backup diesel with no clear reimbursement path.
- 11:37SPEAKER_00: And the renewable tax credit cliff arrives in three days with interconnection cues as the binding constraint, not legislative intent.
- 11:46SPEAKER_00: The frameworks that were supposed to manage these transitions are lagging the events.
- 11:50SPEAKER_01: Resource planners and legal teams need to be in the same room this week.
- 11:54SPEAKER_01: The operational questions and the contractual questions are converging, and waiting for regulatory clarity before acting on either is itself a choice with consequences.
- 12:04SPEAKER_01: That's your NWPPA morning brief for Wednesday, July 1st, 2026.
- 12:09SPEAKER_01: Sources for every story are linked in the show notes.
- 12:12SPEAKER_01: We'll be back tomorrow morning.
- 12:14SPEAKER_01: Keep the lights on.