Latest / Project Podcast / Delivering a £3bn water infrastructure resilience programme
Transcript
- 0:15Welcome to the APM Podcast. I'm your host Emma DeVito.
- 0:18I'm the editor of APM's Core 2 Journal project.
- 0:20The question I'd like to put to our guest today is what's it
- 0:24like to get a once in a generation critical
- 0:27infrastructure programme off the ground?
- 0:29What's it like to work on a major project in an area water
- 0:33supply that is garnering so much public and media attention?
- 0:37Here to give me the fly in the wall view is John McNeil, Head
- 0:41of Programme Delivery at United Utilities, who's helping to lead
- 0:44the £3 billion horse water aqueduct resilience programme in
- 0:48Northwest England. Welcome, John.
- 0:50Thanks for joining me. Morning, Emma.
- 0:53Thanks for having me. Well, it's a pleasure.
- 0:57Let's begin with the basics when you tell me a bit about the
- 0:59project and its scope, and perhaps what's making it
- 1:03particularly unique. Absolutely.
- 1:07So the Horse Horse Water Aqueduct Resilience Programme or
- 1:10HARP as we as we fondly know it as it's been a project that's
- 1:15been running for about 7 years now and the project is all about
- 1:19addressing a very immediate and real resilience need.
- 1:24So the the horsewater reservoir as shown behind me on the on the
- 1:29photograph was built just you're.
- 1:31Not actually there. I'm not actually there.
- 1:33No, I'm not on site today. I'd love to be in that lovely
- 1:36weather. So the reservoir was built in
- 1:39the early sort of 1900s. And what connects the reservoir
- 1:43to the main conurbations of the northwest being sort of
- 1:46Manchester, is the horsewater aqueduct.
- 1:49And this aqueduct was built between 1930s and 1950s to allow
- 1:53the passage of water to effectively sustain the
- 1:56industrial growth around Manchester and the Manchester
- 1:58area. So a really, really important
- 2:01aqueduct, an asset. It runs for 110 kilometres or
- 2:05about 80 miles across an absolute variety of of, of
- 2:08terrain and different areas. It served us fantastically for
- 2:1370 years. The engineering that went into
- 2:16it is just brilliant and it's served as well, but it's now
- 2:21beginning to get to the end of its asset life.
- 2:23And so the project is all about looking at effectively replacing
- 2:26the key, the key sections of that to sustain this this water
- 2:31supply for many years to come. OK.
- 2:33Thanks John for that overview. And So what you have you been
- 2:37involved right from the start, so from 7 years ago?
- 2:41No, I haven't. So I joined the project about 3
- 2:43years ago, just at a stage when the project was beginning to go
- 2:47out into the procurement phase to look at suppliers and a
- 2:50supply chain network to to deliver this.
- 2:54OK. And what are your role and
- 2:57response? What's your role and
- 2:58responsibilities right now for the programme?
- 3:02So my experience throughout my career started out with
- 3:05engineering and I've moved into a variety of different roles in
- 3:08my career. But the, the area I've, I spent
- 3:12most of my career in his project delivery, project management,
- 3:15programme management. So I was brought in three years
- 3:18ago to effectively get the, the project ready, match ready, if
- 3:23you like, for when this project moves into the construction
- 3:25phase. So my role currently is the Head
- 3:28of Programme Delivery for United Utilities and I'm also the named
- 3:32representative under the commercial contracts we have
- 3:34with the with the supply chain. Could you give me a bit more
- 3:39about what work is actually involved, because I'm quite
- 3:43interested in the history of this.
- 3:44It is a kind of, you know, Britain, England is full of
- 3:48infrastructure that has been was built in Victorian times or, you
- 3:52know, a quite a long time ago. And certainly renewing critical
- 3:58infrastructure like this is is going to only increase as the
- 4:02decades go on. So like, I'm sure you've been
- 4:07into the system. Like can you give us an idea of
- 4:10what it's like and what work will actually be done to renew
- 4:14it, if that's not too of an obvious question to ask?
- 4:20Yeah, no, it's fine. So as I mentioned before, the
- 4:23as, as the Northwest was growing and as Manchester was growing as
- 4:26a city back in the early 1900's, the needs to supply water was,
- 4:32was was huge for population and industrial growth.
- 4:36So, so the lakes were an obvious place for storage and collection
- 4:42of water. Then of course that water then
- 4:43has to be transported down to to Manchester.
- 4:46So the Horse Water Aqueduct was constructed between 1933 and
- 4:501955 between the two world wars where resources were scarce,
- 4:56manpower was scarce. And it was constructed through a
- 4:59range of through, through geography, through hills where
- 5:03we where the team and the project were able to tunnel
- 5:06through the hills and through sections of pipe work as well
- 5:09where there's valleys. So what this ended up with was
- 5:12a, an 80 mile aqueduct that's made-up of tunnels and pipe work
- 5:15sections and, and and wells that effectively conveyed a huge
- 5:21amount of water to allow the growth of Manchester.
- 5:24And the absolute fantastic thing about the the the the aqueduct
- 5:28when it was built is that the water runs by gravity.
- 5:31So taking that amount of water from the north of our region
- 5:36down to the South of the region without a single KJ of energy,
- 5:39it's just a fantastic achievement, fantastic
- 5:42engineering and it's served us really well.
- 5:46But towards the kind of 20 tens, we as a company began to get
- 5:51concerned about some aspects of its condition and we were able
- 5:55to actually get an opportunity to isolate the the aqueduct and
- 5:59go in and have a look at it. Now even doing that was a huge
- 6:03task organisationally because if you can imagine the Northwest of
- 6:07England as a human body, the kind of heart of that body is
- 6:12the lakes where a lot of our water is stored.
- 6:14But the, the horsewater aqueduct is like the main aorta.
- 6:17So this is the main conduit that is distributing the water out to
- 6:21to a lot of the northwest communities.
- 6:24So to suddenly take that out of service to go in and have a look
- 6:27at it and inspect it, it's kind of doing like open heart surgery
- 6:30on, on a patient. So an awful lot of enabling
- 6:33where it's had to be done to just allow us to go in and have
- 6:36a look into this aqueduct. We've now done that two times,
- 6:39once in 2013 and once in 2016. And we're able to go in and have
- 6:44a look round and give it a bit of a poke and a prod.
- 6:47And what, what we found in those asset inspections is that this
- 6:50this asset is deteriorating, not imminently, but it definitely
- 6:54needs some, some intervention in the next, in the next few years.
- 6:59And that those inspections really are what drove the need
- 7:02to do the replacement of the of the horse water aqueduct.
- 7:06And that's effectively the the what gave rise to the project.
- 7:10So what will you be doing exactly to to renew it and to
- 7:13make it resilient and, you know, Fit for the Fit for use now and
- 7:18for the coming decades? So of of the of the the 80 miles
- 7:24of of of Horzaltrakodo that exists today, probably about
- 7:26half of that is in tunnel sections.
- 7:29So these are deep, effectively pipes or tunnels that have been
- 7:34hewn through the rock of of the hills in the northwest of
- 7:38England. Some of them are kind of 304
- 7:40hundred metres deep. The diameter is about two to
- 7:45three metres. So these are large kind of
- 7:47tunnels and they're the sections that we're most concerned about.
- 7:52So what we'll be doing on the HARP is effectively going in and
- 7:56creating brand new tunnels to replace those tunnels that are
- 7:59beginning to degrade. So effectively HARP is a huge
- 8:02civil engineering tunnelling project.
- 8:05Well, as we take on to replace those six separate tunnel
- 8:08sections that make up about like I say half of that sort of 80
- 8:11mile run. It's kind of awesome what people
- 8:15achieved, you know, what the engineers achieved in the
- 8:171930's. The way you describe it, it just
- 8:20must have been back breaking work and so dangerous at the
- 8:25time. Do you feel that kind of sense
- 8:27of history with a project like this?
- 8:30Yeah, absolutely. I mean, when you look back at
- 8:32some of the black and white images, it's like long before
- 8:36PPE, long before modern construction practises.
- 8:40It's just breathtaking. I mean, what what these guys did
- 8:42effectively trying to create a tunnel through just solid rock,
- 8:47effectively using dynamite, you know, drilling the little holes
- 8:50into the rock, filling them with dynamite, lighting the fuse and
- 8:53stepping back and letting this thing blow itself open.
- 8:56And then slowly then creating this this aqueduct, this tunnel
- 9:01by using fairly rudimentary sort of support systems and concrete
- 9:06forming systems was absolutely incredible.
- 9:08What they did back then and what they've achieved.
- 9:10And as I said before, to be able to build all that to such a
- 9:13level of accuracy that the water can flow completely by gravity
- 9:17for that that distance is, is an incredible feat.
- 9:20And the feeling around the project now is we're in a
- 9:25fantastic position to to replicate what our forefathers
- 9:29did, but but make it even better as well.
- 9:30We want this new aqueduct to operate again under gravity, but
- 9:36be completely, you know, suitable for carrying water and
- 9:41also to last even longer if we can.
- 9:42We're looking for this new tunnel suite of tunnels to last
- 9:46over 120 years. So there's a real feel that this
- 9:49is a project that will endure. It will be.
- 9:53It'll certainly help live me, my children and possibly their
- 9:56children and their children again.
- 9:57So it's a multi generational asset that we're delivering
- 10:00here. And the project does have that
- 10:02kind of special feel about it, a real pleasure to be on on on a
- 10:06project of such sort of scale and, and like I say, once in a
- 10:09generation opportunity really. Is that that must motivate you
- 10:13as a kind of project leader to that idea of legacy and working
- 10:17on something that is so critical?
- 10:19100 percent, 100%. Like I said before, we, we
- 10:22deliver a lot of projects within United Utilities, but this one's
- 10:24always kind of stood out as being a really special project.
- 10:28And, and even working day-to-day with the project team, we talk a
- 10:32lot about legacy. We talk a lot about projects
- 10:34like this not come along very often.
- 10:37And yes, there's a huge sense of like an obligation to do your
- 10:41best on any, any project on any, on any scheme and in any role,
- 10:45particularly on this, this one. It just feels that little bit
- 10:47special. It's it's a feeling that sits
- 10:50around the project, which is great.
- 10:53The motor face is definitely, definitely there to deliver
- 10:55something that that will endure and like I say, will last for
- 10:57many, many generations. But I think the other aspect of
- 11:02the project that really motivates me is what we can do
- 11:05while we're delivering the project.
- 11:06So we talk about legacy in terms of what we'll leave behind and
- 11:10what we'll leave for many generations to enjoy.
- 11:12But there's also an opportunity in the eight years that we're
- 11:16constructing this project have a massive positive impact on
- 11:19communities, on careers, on education.
- 11:22So one of the aspects of HARP I'm really proud about is our
- 11:26sort of commitments to social value, what we're looking to do
- 11:28during the construction of the project as well.
- 11:30What can you tell us a bit about that?
- 11:32So I guess you'd be creating a number of jobs in the local area
- 11:37and training people up. And is this also a platform for
- 11:40training people up on this kind of infrastructure renewal so
- 11:47that if, you know, if and when this happens again within the
- 11:50UK, then we've got people here who can sort of be ready to give
- 11:54their expertise? Yeah, 100%.
- 11:57So, so we, when we went out to market, one of the things we're
- 12:00really keen to do is engage with a supply chain that we're as, as
- 12:05passionate about this aspect of the project as we were.
- 12:08And, and social value is a really important thing to, to
- 12:10unite utilities and it absolutely flows through into
- 12:14the vision and values of of HARP as well.
- 12:16So some of our ambitions on social value where we've looked
- 12:20at small and medium enterprise spend, we're looking to commit
- 12:23at least 25% of our SME spend in the local area with local
- 12:27businesses and that can really make a difference on HARP.
- 12:32At the peak, we're looking to have Circuit 1500 employees
- 12:35across the various sites working on the project.
- 12:39And again, the commitment to that is that we'll have at least
- 12:4230% of that will be again from local communities and, and, and
- 12:45their local areas. And one that I'm really keen to
- 12:51have in there and really proud to have is 5% of the workforce
- 12:55at any one time will be apprentices.
- 12:57So that can be a kind of 60 apprentices a year that were
- 13:00taken from local colleges, local schools, local communities, and
- 13:04giving them hopefully a step into construction and that they
- 13:08can use on harp and obviously then take tape with them into
- 13:11the rest of their career. So that investment in
- 13:13communities, skills, education, it's, it's a huge part of the
- 13:17project and it's one that I'm really keen to kind of lead and
- 13:20keep, keep the fire lit under the whole, the whole of the
- 13:22eight years we're going to be building this.
- 13:25How much is climate change mitigation part of some you know
- 13:31the programme does it affect what you do?
- 13:33Is what you know how, how is that that risk sort of thought
- 13:39about and dealt with on on the programme?
- 13:43Yeah. No, it definitely has featured
- 13:45in our thinking and it factors into the programme in in
- 13:47probably at least two or three ways.
- 13:49So one of the things we've been really keen is during the
- 13:53construction phase of of the project is to invoke a keen eye
- 13:59on our impact on the environment.
- 14:01So tunnelling is a big civil engineering endeavour.
- 14:04He cannot get away from that requires big machines, you know,
- 14:08shifting larger large amounts of material.
- 14:11But that said, there are things you can do to to minimise the
- 14:14impact of where that material goes.
- 14:17So we've been really proactive in looking for local areas to
- 14:22dispose on that one, to cut down the carbon footprints of
- 14:25transporting the material to around the place, but also
- 14:28putting it to beneficial use. So we've been able to speak to
- 14:32local quarries or local land owners that might be able to use
- 14:35the material. We've also got some pretty
- 14:37stretching KPIs on energy use. So how some of the tunnel boring
- 14:41machines themselves, which are huge power users, how they'll
- 14:44actually be powered has also factored into our thinking.
- 14:47And we've come up with some quite iterative ways of looking
- 14:51at the least damaging or the least impacting ways for power
- 14:55use. So definitely while the
- 14:57project's been building, while project's been built, that's
- 14:59been in front of our mind, but also longer term.
- 15:02So, so water and water scarcity is, you know, a real issue, not
- 15:09just in the UK, but across the world.
- 15:11And when you're building an asset like heart that's going to
- 15:14last for potentially 120 years or more, thinking about its
- 15:18future use is just as important as think about it's the need for
- 15:22it today. So what we've been able to do is
- 15:25try and future proof as much as we can the assets.
- 15:29So in terms of the size of the existing horsal Tricroduct,
- 15:33it's, it's about 2 1/2, three metres, 3 1/2 metres in
- 15:37diameter. And going forward, we're going
- 15:39to make that bigger, not that that carrying capacity is needed
- 15:42today, but it might well be in the future.
- 15:46So again, the the trick there is obviously making sure we've got
- 15:49enough flexibility to future proof the asset in case we
- 15:51haven't needed to shift the water around in different ways
- 15:54or shift different volumes, but not burdening today's customers
- 15:57with that as a cost. And that's that kind of balance
- 16:00we've been we've factored in, in the sort of strategic approach
- 16:03on HARP. OK, thanks.
- 16:06And the programme is working on the new delivery model which is
- 16:12called the direct procurement for customers DPC model.
- 16:16And I think this programme is a Pathfinder for that.
- 16:18So can you tell us what that means exactly for people who
- 16:22might not be, who who might not know?
- 16:25So in the water industry, all water companies are have an
- 16:29economic regulator called Off Watt off water very much there
- 16:34to ensure that the water companies deliver in the most
- 16:36efficient and effective way. And probably 5 or 6 years ago
- 16:43off what looked into various different ways of delivering
- 16:46projects and they wanted to trial something that was a
- 16:48little bit different and that's where DPC came from.
- 16:52So DPC stands for direct procurement for customers and
- 16:56what it invites water companies to do is effectively not only
- 17:00engage organisations to design and build assets, but also to
- 17:05design, build them, finance them, maintain them and in some
- 17:10case operate them as well. And that's that's the sort of
- 17:14procurement approach that that the half will be delivered.
- 17:17Under what are the benefits that this model hopes to bring to the
- 17:21delivery of the programme? The idea behind DPC is to, as I
- 17:26said before, make projects more innovative and efficient.
- 17:31And the way it intends to do that is look at different
- 17:34sources of finance for projects. It's looking to attract
- 17:37different different parties, different delivery partners that
- 17:41might not normally have been attracted to the UK water
- 17:44industry, which with them then brings innovation.
- 17:46And that's certainly what we've seen on HARP in terms of the
- 17:49interest across the supply chain.
- 17:51We're now in a position where we've awarded the contracts to
- 17:53what we call a cap or a competitively appointed
- 17:56contractor. So that's the the special
- 17:58purpose vehicle that will actually deliver the scheme.
- 18:00And they are entities that certainly we in United Utilities
- 18:03have have not used before. So it's definitely seeing some
- 18:06fresh names in and around the sector.
- 18:09I'd like to ask you about stakeholders and who the
- 18:11stakeholders are that you deal with and United, am I correct?
- 18:17United Utilities, does it own all of the infrastructure that
- 18:21you're working on is that? It it does, yeah, it does.
- 18:25So all of our assets are owned by United Utilities.
- 18:29This will be the first asset that we've have ever delivered
- 18:31whereby effectively it's owned by a another for a period of
- 18:35time and that's a feature of the the DPC model.
- 18:38So as I mentioned before, the, the, the, the DPC model allows
- 18:44effectively a new entity called the CAP, a competitively
- 18:48appointed provider to design, build, finance, operate and
- 18:51maintain the asset. So once the construction of HARP
- 18:54is complete after sort of eight years, they will actually own
- 18:57the asset for another 25 years. And as effectively you, you and
- 19:02its customer base pay off the the initial sort of financial
- 19:06outlay and then that asset comes into our asset base fully.
- 19:11Who are the most critical stakeholders that you're
- 19:13engaging with and what challenges have you been able to
- 19:18overcome and any advice you'd pass on to professionals working
- 19:22in in, you know, in in a similar way or affected by similar
- 19:25issues? Yeah, so it's a great question.
- 19:29I mean the, the, the stakeholder reach on a, on a programme, the
- 19:32size of HARP is, is issues as you'd imagine.
- 19:36Key stakeholders are obviously our customers and we're doing
- 19:39this for our customers. Two and a half million of our
- 19:43seven million 7,000,000 customer base will benefit from this
- 19:46project. So it it'll impact from a
- 19:49beneficial point of view a huge proportion of our customers, but
- 19:53quite a small number of our customers will actually be
- 19:55impacted in the construction. But they're the ones that really
- 19:59have in the front of our minds as a, as a key stakeholder.
- 20:02Obviously, we have our industry regulator off Watts.
- 20:05This is their first DPC out of the blocks.
- 20:08They're hugely keen to see how it goes though.
- 20:10So they have all eyes on the project and we work very closely
- 20:12with those guys. We now have our supply chain,
- 20:15our partners in place. So we have the cap, as we said
- 20:18before, the competitively appointed provider.
- 20:20And we've got another body called the ITA, an independent
- 20:23technical adviser who also sits as part of the HARP supply
- 20:27chain. So really key stakeholders
- 20:28there. We have key stakeholders in the
- 20:32local communities with MPs, local councillors, local
- 20:35community leaders. So it's a, it's a vast array as
- 20:39you can imagine. And it's a real effort to keep
- 20:43all of the stakeholders at the right level of being informed,
- 20:47engaged and communicated with, consulted with.
- 20:49So it's a huge range. But one of the big challenges we
- 20:52faced on HAARP was in the, in the kind of relatively early
- 20:56phases of planning where we, we were really keen to go out and
- 20:58speak to particularly the customers and the local
- 21:00communities about the project, about the impacts it might have
- 21:03about what the what the project will look and feel like.
- 21:07And normally we'd go about that by take, you know, doing sort of
- 21:10town hall sessions or consultation sessions face to
- 21:13face. And that was the root and the
- 21:15tactic we adopted on HAARP. But bearing in mind the huge
- 21:18geographical spread, you know, the 80 miles kind of top to
- 21:21bottom, that was a huge endeavour.
- 21:23And that was all going really well.
- 21:26But then COVID hit. So this was around 2020.
- 21:29So that really sort of stymied our plans to to get out there
- 21:32and speak to people face to face.
- 21:35So for the first time, certainly in in United Utilities history,
- 21:40we took that public consultation online.
- 21:43It sounds old hat now because everything's done online, but
- 21:45back then it was kind of quite a new to us.
- 21:47And we held online drop in sessions, online surgeries,
- 21:50online briefings, presentations, and we didn't know how it was
- 21:53going to go right. But to be honest, it was
- 21:56fantastic. It meant, perversely, we reached
- 21:58far more people than we ever would have done doing it the old
- 22:02fashioned way. And we listened.
- 22:05I think one of the key lessons I've certainly picked up from On
- 22:07Harp is listen, you know, listen more and speak less.
- 22:14And we got an absolute wealth of feedback from the communities
- 22:17about what they were worried about, what they wanted to see,
- 22:20what they didn't want to see, how they thought it could be
- 22:22delivered better in a less impactful way.
- 22:25And because we did that early enough in the project, we were
- 22:27able to take some of those gems and actually like incorporate
- 22:30them into the scheme design, how we're going to deliver it, how
- 22:33we're going to constrain the supply chain when they deliver
- 22:35it. So that stakeholder engagement
- 22:38with the customers wasn't just there to get buy into the
- 22:42project, which is normally the step, the aim.
- 22:44It was, it was that, but it was also to get steerage on the
- 22:47project and allow that to to shape the project.
- 22:49So a lot of effort was put into it around that time in ways that
- 22:54we never imagined doing, but it was really, really successful.
- 22:57And it's actually our largest public consultation we've ever
- 22:59done for any project across United Utilities and it's really
- 23:04even now bearing fruit. Could you explain to me exactly
- 23:10where you are now on the programme and what you're
- 23:12working on right now? Sure.
- 23:14So, so we managed to close the procurement process at the back
- 23:19end of last summer. That was a lengthy process, but
- 23:25hugely rewarding to get to contract award or to call it
- 23:28financial close in ADPC setting and that happened last August.
- 23:33So a really great milestone for the project and, and such an
- 23:37effort, a huge amount of effort from the project team that was
- 23:42fantastic. So that was kind of seven or
- 23:44eight months ago now. So we're now beginning to get
- 23:47into what is an 8 year construction programme.
- 23:50We're in year 1. So a lot of the folks in the
- 23:54last sort of 6 to 8 months have been on mobilisation of the the
- 23:57new supply chain, getting them set up, getting them inducted
- 24:02into what we're trying to deliver, new systems, new
- 24:06people. We've Co located in a sort of
- 24:09new sort of programme office. So we're all sat together, which
- 24:12has been an absolute, absolute coup in terms of sort of
- 24:16promoting collaboration. How many people are based there
- 24:20do you think? So we've probably got over 100
- 24:23people, maybe 100 to 130 people Co located.
- 24:28And when I, when we first moved into this, our office, which is
- 24:31in kind of the city centre of Manchester, which got a nice
- 24:34link to obviously this is the community largely that this
- 24:37project will be, will be serving.
- 24:39I'm sat there thinking, there's no way we're going to fill this
- 24:41office. This is huge.
- 24:42And within six months we've outgrown it beyond all belief.
- 24:46So we're actually looking to open some other offices now and
- 24:49some of the sort of depots to sort of accommodate the growing
- 24:52team. But what, what that office has
- 24:54allowed us though, is to bring the whole of the programme
- 24:56together. So we're sat in there as the, as
- 24:59the kind of appointee for the scheme, as United Utilities.
- 25:02We've sat with the CAP who's an organisation called Cascade
- 25:06Infrastructure, they have their main contractor, an organisation
- 25:10called Strabag, Strabag UK and we've also got the independent
- 25:14Technical Shorer who sat with us who's children in Townsend and
- 25:19OTBE Engineering. So lots of different
- 25:22organisations but all sat together for two or three days a
- 25:25week. Yes, we meet and we have our
- 25:27formal meetings and our update meetings, but the power of
- 25:31sitting together are the corridor conversations, the kind
- 25:34of, you know, informal interactions that you have that
- 25:38just help really Foster and build those relationships.
- 25:42So having that set up has been a real, a real, a real game
- 25:45changer in my mind. It's really got the the
- 25:47programme out of the blocks. Was that something that you that
- 25:50United Utilities had always wanted to put in place for a
- 25:53project like this? Because it is a new way of doing
- 25:55things. So I'm wondering how what the
- 25:57approach to managing a programme like this would be and how it's,
- 26:02and now it's different to, to maybe previous programmes you've
- 26:05worked on. So I mean, I'm just here hearing
- 26:08collaboration, but I don't know what was kind of at the
- 26:12forefront of people's minds to in their approach to running
- 26:16this programme, the construction freight phase at least.
- 26:20Yeah, it's a good question, to be honest.
- 26:22We, we really wanted this as an organisation, but we didn't want
- 26:27to force people into it. So the way we actually procured
- 26:31heart was actually, we left it open.
- 26:33We said to our prospective partners, if you would like to
- 26:37work together and have a collaborative programme office,
- 26:41we'll be in it with you. You know, let's do it.
- 26:43But if you don't, you don't necessarily have to.
- 26:45But if you do, please make space for us kind of thing.
- 26:47And what was really pleasing is our preferred bidder and now our
- 26:50successful CAP really wanted that too.
- 26:54And so it was kind of a we, we dangled, I guess we fished for
- 26:57it and, and, and we got what we're hoping for really.
- 27:00But that's been a real sort of Energizer to, to bring people
- 27:04together like you're saying. And things, some of the things
- 27:08I've seen that really have helped that is it might seem a
- 27:12little bit twee and I know most projects have this, but we spent
- 27:15quite a lot of time in those early weeks and months
- 27:17developing our common sort of project vision, project values,
- 27:22which is the first kind of test of everyone working together,
- 27:24right? Can you just come up with
- 27:25something that you can all sort of centre around?
- 27:28And, and we did do that and we have that now and it's public
- 27:31and it's available and, and what we don't want it to be and it
- 27:37isn't, it's something that just sits on the wall that nobody
- 27:39ever looks at. People do talk about it.
- 27:41So when we're in meetings and we're talking about issues and
- 27:43we see behaviours that aren't quite right, we draw it back to
- 27:46the project vision because that sets out exactly what this
- 27:48project is trying to achieve. And I just don't think you would
- 27:52have got that cohesion around that kind of central idiom if
- 27:56you'd been sat in all over the world or in separate offices in
- 27:58the UK. So I'm a big believer in that
- 28:01sort of Co location aspect. I'm interviewing you for this
- 28:07podcast because you wrote a really interesting feature for
- 28:09the Summer 2026 issue project and there was some, there were
- 28:14two things in the feature that you mentioned that I wanted to
- 28:17pick up. The first was that you said your
- 28:21instinct has always been to seek clarity, define the problem,
- 28:25analyse the options, land on the optimal solution.
- 28:29And the more senior people I speak to in project management,
- 28:32the more clarity, simplicity and a kind of coherent vision seems
- 28:39to matter a lot. Can make the difference between
- 28:42a project that's OK and one that's highly successful, I bet.
- 28:45So I'm keen to pin you down a bit more now I've got you here
- 28:49for you before you go and jump, jump into that reservoir behind
- 28:52you. Hi inside Lake.
- 28:54Could you tell me a bit more about your clarity and how
- 28:58important that is to you as a as a programme leader?
- 29:02I guess when in my mind when you're dealing with a single.
- 29:04So if you perhaps as an engineer, I remember in the
- 29:07early parts of my career when you're dealing with A1 specific
- 29:10pro problem, say it's or an issue, it's relatively closed,
- 29:14it's relatively narrow. It's kind of 1 dimensional.
- 29:17It's, it can be 1 dimensional, relatively simple and clear.
- 29:21But on a project like HAARP has taught me and other projects
- 29:26before that is project programmes at scale, that
- 29:30certainty is, is elusive. It, it just isn't there.
- 29:34It's, it's the old Vuka world that we live in.
- 29:37The noise is louder, the issues and more numerous.
- 29:41The agendas are wider, it's more diverse, So what was once A1
- 29:45dimensional issue is now something that's far more
- 29:48complex. There's technical aspects,
- 29:50there's planning, there's finance, there's community,
- 29:52there's risk, there's schedule, there's just a lot more going on
- 29:55and it can be overwhelming. So from an engineering mindset
- 29:59it can easily, it can easily be overwhelming for you.
- 30:02But what I've kind of learnt is the same sort of principles can
- 30:06be applied and, and do apply. And it sounds obvious, but it it
- 30:10is just breaking it into those chunks that make it more
- 30:13manageable. And yes, they interconnect.
- 30:17So the technical chunk may interconnect with the planning
- 30:20chunk, which interconnects with finance and the community and
- 30:24they all have interdependencies. But if you can organise yourself
- 30:28and your team in a way that addresses each chunk and just
- 30:32make each area's life, I guess, as simple and as clear as
- 30:37possible, that just allows people to crack on.
- 30:40But the real magic is effectively bringing that
- 30:43together and making sure that they stay connected.
- 30:48Yes, you were doing your bit, but you also need to know how
- 30:51your bit perhaps interacts with this bit over here and how that
- 30:53then changes this bit over here. So it's really important I've
- 30:58been given that clarity at kind of chunk level, if you like, or
- 31:00work stream level to bring people together.
- 31:03Now I meet with my team once a week, every Friday morning to do
- 31:06exactly that. What's happened this week?
- 31:07What's happening in your world that might impact someone else's
- 31:10world? And we regularly have team
- 31:12scrums as well, again, just to make sure people can understand
- 31:14their interconnectivity and people can almost have that read
- 31:17across as to what's happening. So big projects are inherently
- 31:22complex. Like I said, that clarity and
- 31:26simplicity can be lost. But there is a way, I believe,
- 31:28of bringing that kind of rigour to it that simplifies what
- 31:31you're asking of each part of the team.
- 31:33But if the magic, as it says, is making sure you keep them
- 31:35connected so people don't sort of drift off into their own,
- 31:39it's their own areas. That's interesting.
- 31:41Also something I'm thinking about as you were telling me
- 31:45that was you have people from different organisations working
- 31:49closely together and each organisational team has their
- 31:52own culture. So how do you go about in
- 31:55skating the kind of over overarching culture for a
- 31:58project like this? How do you establish principles?
- 32:01Is it formal or is it just info? This is the way we do things and
- 32:04you lead by example I think. I think that's really
- 32:08interesting to get your kind of first hand expertise from that.
- 32:13Yes, it's a great question. It's something we've spent a lot
- 32:16of time on, like I said in the last six months on Harper as
- 32:20we're mobilised because I was really big on making sure that
- 32:24we can galvanised the new parties and the new
- 32:27organisations as we move into project award around something
- 32:31that unites us. But I think to suddenly say we
- 32:35want you all to now adopt the harp culture and that's the only
- 32:37culture you'll ever have. It's just like it's naive and
- 32:40it's not going to work. So I think in minds, in my
- 32:43mindset, the way we sort of pitched it to our various
- 32:48partners is that you will all come with your own
- 32:50organisational culture. Like United Utilities has one,
- 32:53Strabike will have 1, Cascade will have one, turn in towns and
- 32:56we'll have one. And we're not asking you to lose
- 32:58that because you can't. It's just, you know, you'll
- 33:00always have that kind of home organisational way of doing
- 33:05things. But what we want is a layer on
- 33:06top of that which is unique to HARP.
- 33:09So let's figure out what it is that unites us on a programme of
- 33:12this scale. What lights our fires?
- 33:14What are we here to do? What can, what sort of
- 33:17behaviours and values can we can we hang our hat on and you make
- 33:21something that's unique to the programme that doesn't then
- 33:24decry everybody else's home culture.
- 33:26They'll always be there, right? But what is it that makes U.S.
- 33:28special on that? That's what I was mentioned
- 33:30before about just even the vision of values bit.
- 33:33It just gives you that line of connectivity across and you can
- 33:36then start to build relationships on and collaborate
- 33:39around. So I don't think you can ever
- 33:42completely wipe everybody's old world away.
- 33:45Like the old men in black, you press the button and they've
- 33:47also forgotten and they they get reborn into a new project
- 33:50culture. I think you have to overlay
- 33:51what's already there with something that's that's unique
- 33:53and special for for what you're trying to achieve.
- 33:56You must feel under a considerable amount of pressure,
- 33:59not least because it's a Pathfinder programme, but also
- 34:03the level of public and governmental scrutiny and water
- 34:06projects at the moment. I mean, it's just in the
- 34:07headlines and there's a lot of strong sentiment about what
- 34:10needs to change in this country to clean up water and give us
- 34:13what we need. Is that what bearing does that
- 34:16have on the project as well? Yeah.
- 34:20Look, yes, you're absolutely right.
- 34:22The, the, the, the, the water companies and the water sectors
- 34:25and the huge amount of scrutiny at the moment.
- 34:28And that's felt within United Utilities as well.
- 34:34United Tools is looking to invest over sort of £13 billion
- 34:37over the next five years in as part of what we call the big
- 34:40Northwest upgrade. And that effectively to do many
- 34:43things. But a lot of that is around
- 34:46cleaning up rivers and seas. And it's the biggest investment
- 34:49in in the Northwest for over 100 years.
- 34:51So there's an awful lot going on.
- 34:54And how does that impact Harp? Well, hugely.
- 34:58I mean all of that work that will be carried out will have an
- 35:02impact on our customers bills. All of the work that will be
- 35:05carried out on HARP will have an impact on our customers bills
- 35:08and there's almost a moral duty on all of us to deliver HARP as
- 35:14efficiently as possible to minimise that impact.
- 35:17With the cost of living crisis and everything else going on, we
- 35:20have a position of responsibility and influence to
- 35:23make sure this project is delivered as efficiently as
- 35:26possible to minimise what people are paying.
- 35:29So I feel personally duty bound to kind of work in the best
- 35:32interests of our customers every day.
- 35:35And that's, that's something else a lot of the team feel as
- 35:37well. So, so yeah, there's a lot of
- 35:39scrutiny on the sector, but we can do something about that to
- 35:42to sort of make that make that better and a more palatable sort
- 35:47of thing we deliver. And does it then inform the kind
- 35:56of accountability and transparency in a project like
- 35:59this? You know, not it.
- 36:01It's about just being open with what's going on and honest about
- 36:06saying, not saying, not in any way saying that you wouldn't be.
- 36:09But it's almost a counter what's happened in the past by the
- 36:14water companies or whatever is it.
- 36:16Is it really? Does that inform the culture of
- 36:19the project as well? Yeah, it does.
- 36:21There's, there's an awful lot of scrutiny on water companies more
- 36:27generally like, like I said, so and the flip side of that is, is
- 36:32to effectively, like I say, adopt A more transparent way of
- 36:36working. So a great example of this
- 36:37slightly outside the heart, but with United Utilities is that
- 36:42every day now we publish our, our CSO, which is our, sorry,
- 36:46our combined sewer overflow activations on a map, you can go
- 36:50on it, you can find your nearest overflow.
- 36:52You can see if it's activated or not.
- 36:54It's completely out there in the public domain in the public
- 36:56interest. And people can see when projects
- 37:00are delivered, how it improves and impacts that situation.
- 37:04And the similarity on HARP is, is the sense that the level of
- 37:08regulatory scrutiny and sharing of information with our
- 37:12regulator is, is kind of off the scale.
- 37:14One, because of the size of HARP and, and what's riding on it.
- 37:17And secondarily because it is this this new delivery model of
- 37:20what really key to see how it goes.
- 37:22They want to take that learning forward.
- 37:23So there's not a week or a kind of month that goes by that I'm
- 37:27not asked or the team are not asked to go and present how
- 37:30things are going, where the numbers are up to where the
- 37:32programme up to how, how things are kind of transpiring.
- 37:36And we have every quarter a very open, we call it a quarterly
- 37:40liaison committee where we speak to offer about how all aspects
- 37:43of the project are, are sort of developing.
- 37:45So almost everything we do on HARP is, is shared pretty openly
- 37:49with our sort of regulator and with the the broader
- 37:52stakeholders as well. I'm going to go rewind back to
- 37:56the second point, which I wanted to ask you about, which you
- 37:59wrote about in the feature which really grabbed my attention was
- 38:02that you wrote that your biggest personal shift has been going
- 38:05from problem solver to systems steward.
- 38:09And I really love that. And I wonder when you're working
- 38:11on a hugely complex projects programme like this, that this,
- 38:16this idea of systems steward is a really valuable one and one
- 38:20that perhaps might only increase in the futures projects as
- 38:23collaboration increases. And you know, we live in a, like
- 38:27you say, a VUCA world, but can you tell me a bit more about,
- 38:32about that sort of personal shift?
- 38:36You know, what is the systems student?
- 38:37How does that work for you on a project like this?
- 38:40Yeah, Oh, sure, sure. So it's again, I guess it goes
- 38:43back to the origins of my career being in engineering.
- 38:47I've I've really pushed myself in my career.
- 38:49And again, this would be something I'd, I'd advise others
- 38:52to do who are, who are perhaps setting out in theirs is to, if
- 38:55you possibly can take the opportunity to broaden yourself,
- 38:59push yourself into different roles, different areas of
- 39:03learning. So I've been an engineer, I've
- 39:06also worked in design management, I've worked in
- 39:08commercial management, I've worked in project and programme
- 39:11management, and I've worked kind of in operational frontline and,
- 39:15and maintenance. And I think having been
- 39:17fortunate enough to move around in those different roles, the by
- 39:21product of that is it's allowed me to kind of see the bigger
- 39:23picture. And what I mean by that is, you
- 39:27know, a decision made in an engineering world can have a
- 39:32massive impact on the assets that someone then operates and
- 39:36maintains for the rest of their life.
- 39:37So that helped me to really start to understand this
- 39:42system's thinking. You know, everything's
- 39:43interlinked and, and unfortunately, the role,
- 39:46sometimes you can only ever see the bit to your left and the bit
- 39:48to your right. But to have the opportunity to
- 39:50see that bigger picture is, is really important.
- 39:53And I think working on hard has allowed me to apply that because
- 39:58leading the team from AUU perspective, you know what?
- 40:02I know that bigger picture and I know the history of the asset.
- 40:05I know what it does. I know the criticality of it.
- 40:09I can. So I know the commercial
- 40:11construct construct. I can see how the DPC models
- 40:15evolved over the years and it's landed.
- 40:17I understand the parties, the duty holders, how it all fits
- 40:20together. I understand the geography and
- 40:22the communities that we're going to be impacting.
- 40:24So from that kind of vantage point, I can really help bring
- 40:28the project vision to life and to encourage the collaboration
- 40:32that's needed to meet the meet the goal.
- 40:35And you just can't lead in that way if you if you're purely
- 40:37transactional. I think you need to kind of step
- 40:42up and kind of exit or demonstrate a little bit of a
- 40:44different project leadership style.
- 40:48Sometimes it's directive, it has to be it's just it's kind of
- 40:51just a go do. But more often that I feel I'm
- 40:54moving some more of a coaching kind of integration type style,
- 40:58you know, explaining the bigger picture, be it to off water or
- 41:02to the supply chain or to the customers, because all of those
- 41:04different stakeholders all have a very different lens on the
- 41:07project. You're or I find myself in a
- 41:10privileged position where I'm at the centre of that and I can see
- 41:13the the join up really, and I love it.
- 41:15I mean, it's great. Just to wrap up, are there any
- 41:21lessons that you've learned about working on a programme
- 41:26like this or any leadership lessons that you've learnt that
- 41:30you would pass on? Yeah.
- 41:34I mean, I think we've, we've maybe covered quite a few, but
- 41:36there's probably sort of four or five that sort of having
- 41:41reflected on, on half. I mean, number one problem being
- 41:47the breadth of experience I've been able to have him in my
- 41:50career has really put me in a good place to, to, to sort of
- 41:54take this project on. So like I said before, if, if
- 41:57people listen to this and have the opportunity to work on
- 42:01different roles, different project, that's stretchy and
- 42:03that's where that's where the growth is the personal growth.
- 42:05So, so do do that and you know, have breadth in your experience
- 42:11because, because when projects and opportunities come up in the
- 42:13future, that will really bear fruit.
- 42:17I think as we mentioned before, another key lesson is, is the
- 42:19one about stakeholder and stakeholder engagement being
- 42:23absolutely critical. Do it early.
- 42:25Listen more than you speak and allow, allow what you hear to
- 42:29influence the project. Don't just treat it as a tick,
- 42:31tick box exercise that that that can really help.
- 42:35I think the third one is that whole legacy piece, Like I said
- 42:39it, IT projects are more than just like tunnels through hills
- 42:42and, and you know, concrete tubes.
- 42:44It's a huge legacy that will impact society for years to
- 42:47come. And there's the here and now,
- 42:50there's the social value. What can your project do to make
- 42:53people's life better through careers, investment, education?
- 42:58And if that's what they can do, then lead it, you know, step
- 43:01into that and drive it forward. Perhaps the next lesson is, is,
- 43:06is just that importance about collaboration kind of is the way
- 43:10I, I tend to lead naturally, but make room for it.
- 43:14So like physically make room for it.
- 43:15Sit together, work together, spend time together, talk and
- 43:20really try and galvanise the team around you is another key
- 43:241. So yeah, it's, it's taught me
- 43:26lots. There's not a day I don't learn,
- 43:29which again, I think is another blessing, something it will
- 43:33continue to stretch me. This programme of sure, but it's
- 43:36been a real ride so far and I'm I'm looking forward to carrying
- 43:39on and see where we get to the next few years.
- 43:41John, thank you. When when is the project due to
- 43:44complete? So the project's eight years end
- 43:49to end, but we should start to receive the first tunnels, as I
- 43:53mentioned for the six of them. So we'll get, we'll get them
- 43:55kind of incrementally, but the first one will be brought into
- 43:57service in 2031. So we've got a few years yet, a
- 44:01lot of tunnelling ahead of us. And then sort of 2033 years will
- 44:05be when we get the final tunnel and we'll have a brand new north
- 44:09to South Horse water aqueduct and safely supplying water to
- 44:13two and a half million people. And that'll be a huge
- 44:17achievement, I'm sure. Brilliant, John.
- 44:20That's a great way to end our podcast.
- 44:22I just want to thank you again for your time.
- 44:25It's been so interesting speaking to you, finding out
- 44:28about what it takes to get a programme like this off the
- 44:30ground and what it's like to work on a once in a generation
- 44:33project. And if people would like to read
- 44:37more about it, then watch out for the Summer 2026 issue
- 44:40project where we you give us a detailed account of some of the
- 44:45background and what's going on there as well.
- 44:48So thank you John again for your time.
- 44:49It's been a pleasure talking to you.
- 44:52Also a pleasure. Thanks Emma for the opportunity.