- 0:00Speaker 1: Welcome to the Deep Dive, the show where we take
- 0:02Speaker 1: those dense foundational guides that define an industry and well
- 0:06Speaker 1: we boil them down to what you absolutely need to know. Today,
- 0:10Speaker 1: we're getting into the very specialized world of industrial steel,
- 0:13Speaker 1: looking at Ra mccrimmon's CISSE Design Guide for crane supporting
- 0:18Speaker 1: steel structures. Our mission is to give you, if you're
- 0:20Speaker 1: an engineering student or maybe a young professional, a real
- 0:24Speaker 1: shortcut to the practical knowledge. Here.
- 0:26Speaker 2: It's a critical mission because these are not your average buildings.
- 0:30Speaker 2: This guide was specifically created to fill a major gap.
- 0:34Speaker 2: A gap yeah. It takes all these complex design details
- 0:37Speaker 2: and lines them up with the Canadian Limit states format.
- 0:39Speaker 2: So we're talking about the National Building Code and the
- 0:41Speaker 2: CSAs sixteen Steel Standard, because those standards they're good, but
- 0:46Speaker 2: they don't really get into the weeds on the unique
- 0:48Speaker 2: loading you get with overhead cranes. So we're focused on
- 0:51Speaker 2: the steel that supports EOTs, the top running overhead cranes
- 0:54Speaker 2: and also underslung cranes and mono rails.
- 0:57Speaker 1: So this isn't just about making a building stand up,
- 1:00Speaker 1: designing a structure that has to move, absorb shock, and
- 1:03Speaker 1: do it over and over again. For decades.
- 1:05Speaker 2: Okay, let's unpack that. The guide is really clear, crane
- 1:10Speaker 2: loads are not the same as standard live loads. What's
- 1:13Speaker 2: the fundamental difference here?
- 1:15Speaker 1: You said the word shock. It's all about dynamics. A
- 1:18Speaker 1: live load, you know, it just sits there. A crane
- 1:20Speaker 1: load is always moving, it's accelerating, its breaking, it's impacting.
- 1:24Speaker 1: So we start with the vertical loads what the guide
- 1:27Speaker 1: calls CVS and CVM. And because these loads are applied,
- 1:30Speaker 1: so suddenly we have to apply an impact factor. It's
- 1:34Speaker 1: also called a dynamic load allowance.
- 1:36Speaker 2: And the guide puts that at what twenty five percent
- 1:38Speaker 2: from most cranes. That's a huge immediate increase to the load.
- 1:42Speaker 2: I mean that must effect the entire structure, right, it does.
- 1:44Speaker 1: But this is exactly where the guide's insight is so important.
- 1:47Speaker 1: That twenty five percent impact factor. It's applied only to
- 1:50Speaker 1: the vertical wheel loads, okay, and only to the runway
- 1:53Speaker 1: beams themselves and their immediate connections. It is not applied
- 1:56Speaker 1: to the columns or the foundations. Wait, hold on, why
- 2:00Speaker 1: does it stop there? If the beam is feeling that impact,
- 2:03Speaker 1: doesn't the column underneath it feel it too?
- 2:05Speaker 2: It's a great question. And it's all about structural dynamics.
- 2:09Speaker 2: That spike in load, the thing that causes that twenty
- 2:11Speaker 2: five percent jump. It's incredibly brief, like a split second exactly,
- 2:16Speaker 2: and the massive inertia of the column and really the
- 2:20Speaker 2: whole building below it, it just filters that spike out,
- 2:23Speaker 2: it dampens it. By the time that force gets down
- 2:26Speaker 2: to the column base, it's not an impact load anymore.
- 2:29Speaker 2: It's just a sustained maximum load.
- 2:31Speaker 1: That makes perfect sense. The sheer mass of the structure
- 2:33Speaker 1: absorbs the quick shock. So what about the forces moving
- 2:37Speaker 1: side to side? The horizontal loads.
- 2:39Speaker 2: Right, So there are two main ones. First, a side
- 2:41Speaker 2: thrust the guide calls it CSS. This is the force
- 2:44Speaker 2: that pushes sideways perpendicular to the rails.
- 2:47Speaker 1: And where does that come from.
- 2:48Speaker 2: It's from a few real world things, the trolley accelerating
- 2:51Speaker 2: or breaking as it zips across the bridge. But the
- 2:54Speaker 2: big one is something called crabbing. Yeah, it's when the
- 2:57Speaker 2: crane bridge gets a little bit skewed on the runway,
- 3:00Speaker 2: the rails are slightly misaligned, and it starts pushing hard
- 3:02Speaker 2: against the side of the rail. For most light to
- 3:06Speaker 2: moderate duty cranes, the guide gives a simple rule of
- 3:09Speaker 2: thumb twenty percent of the combined weight of the load
- 3:12Speaker 2: you're lifting, plus the trolley itself.
- 3:14Speaker 1: Twenty percent of the vertical load. But applied sideways, that
- 3:18Speaker 1: is a massive lateral force for that beam to handle.
- 3:21Speaker 2: It really is, okay.
- 3:22Speaker 1: So what about the force along the runway when the
- 3:25Speaker 1: whole crane bridge moves.
- 3:26Speaker 2: That's the longitudinal force or traction load CLSs. It comes
- 3:31Speaker 2: from the entire crane bridge accelerating or braking. If you
- 3:34Speaker 2: don't know the exact specs, the guide says to use
- 3:37Speaker 2: ten percent of the total load on all the driven wheels.
- 3:40Speaker 2: That's the force that governs your column bracing in that direction.
- 3:43Speaker 1: Okay. And there's one more, an accidental one.
- 3:46Speaker 2: Yes, bumper impact CBS. This is what happens if the
- 3:50Speaker 2: crane hits the end stop at full speed. It's an
- 3:53Speaker 2: accidental extreme event. So the load factor we use for
- 3:56Speaker 2: it is just one point oh, not the higher factors
- 3:59Speaker 2: for normal.
- 4:00Speaker 1: And the guide pulls all these dynamic forces together using
- 4:04Speaker 1: the companion action approach from the building code. It lays
- 4:07Speaker 1: out a bunch of load combinations see one to see seven.
- 4:10Speaker 1: For checking the ultimate.
- 4:11Speaker 2: Strength exactly, you can think of c one to see seven.
- 4:14Speaker 2: As the recipes for the worst case scenarios, they force
- 4:17Speaker 2: you to check everything max vertical load, max vertical with
- 4:21Speaker 2: a max side thrust, traction load with a lower vertical load.
- 4:25Speaker 2: It makes sure you don't miss that one combination that
- 4:27Speaker 2: could cause a failure.
- 4:28Speaker 1: So that covers strength for a single event. But the
- 4:30Speaker 1: guide says, the single biggest difference from normal building design
- 4:33Speaker 1: is something else entirely. It's repeated loads. It's fatigue.
- 4:37Speaker 2: This is it. This is the real game changer. We
- 4:39Speaker 2: have to shift our thinking from one peak load to
- 4:43Speaker 2: the cumulative damage of millions of small movements. The vast
- 4:47Speaker 2: majority of failures you see in crane, runway beams, welled cracks,
- 4:50Speaker 2: bolts failing, it's not from one overload event.
- 4:53Speaker 1: It's death by a thousand cuts.
- 4:55Speaker 2: That's the perfect analogy. The core principle, which comes out
- 4:58Speaker 2: of the S sixteen Steel standard is that fatigue life
- 5:00Speaker 2: depends on three things. The type of detail, the stress
- 5:04Speaker 2: range it sees, and the number of cycles.
- 5:06Speaker 1: So a high stress range means a shorter life, and
- 5:09Speaker 1: the guide gives two ways to figure this out. The
- 5:12Speaker 1: first one is an abbreviated method using a classification system right.
- 5:16Speaker 2: This is the crane service classification from standards like CMAA
- 5:21Speaker 2: or CSA. Goes from Class A, which is just standby service,
- 5:25Speaker 2: all the way up to Class F which is continuous
- 5:28Speaker 2: severe service like a crane in a steel mill running
- 5:30Speaker 2: two four seven.
- 5:31Speaker 1: So it's a quick estimate based on how hard the
- 5:34Speaker 1: crane is going to work exactly.
- 5:36Speaker 2: But the second method, the one that's really preferred for
- 5:39Speaker 2: heavy duty applications, is a detailed duty cycle analysis.
- 5:43Speaker 1: Okay, that sounds a lot more involved.
- 5:44Speaker 2: It is. You actually analyze the full spectrum of loads.
- 5:47Speaker 2: You figure out how many lifts will be at ten
- 5:49Speaker 2: percent capacity, how many at fifty, how many at one hundred.
- 5:52Speaker 2: You take all that data and you use something called
- 5:54Speaker 2: the palm grind minor rule.
- 5:56Speaker 1: Can you break that down for us? What's the palmgrind
- 5:58Speaker 1: minor rule really trying to do.
- 6:00Speaker 2: It's basically a damage counter. It assumes every single load cycle,
- 6:03Speaker 2: even a small one, uses up a tiny measurable piece
- 6:07Speaker 2: of the structure's total fatigue life.
- 6:09Speaker 1: So you add up all those tiny pieces of damage
- 6:11Speaker 1: from all the different load sizes.
- 6:12Speaker 2: Precisely, and when you get at the end is a
- 6:15Speaker 2: single number. The equivalent number of cycles or ne at
- 6:19Speaker 2: the highest possible stress. That one number tells you the
- 6:23Speaker 2: total cumulative damage, and that's what you check against your
- 6:26Speaker 2: design curves.
- 6:27Speaker 1: That's fantastic. It turns a really complex real world scenario
- 6:31Speaker 1: into one design variable you can actually work with. So
- 6:35Speaker 1: the guide then links the crane service class to a
- 6:37Speaker 1: structural classification, say through SF. How does that work in practice?
- 6:42Speaker 2: It's how you set the design target for the structure itself.
- 6:45Speaker 2: For light duty cranes classes A, B, and C, the
- 6:48Speaker 2: structure is designed for about twenty percent of the crane's
- 6:51Speaker 2: total expected cycles.
- 6:52Speaker 1: Why only twenty percent, because we know.
- 6:54Speaker 2: Those cranes rarely operate at full capacity, But for the
- 6:57Speaker 2: heavy duty ones D, E and F they run near
- 7:00Speaker 2: capacity a lot more so for those, the structure has
- 7:03Speaker 2: to be designed for about fifty percent of the crane's
- 7:05Speaker 2: full load cycles. So for example, okay, say you have
- 7:08Speaker 2: a Class E crane that's expected to do two million
- 7:11Speaker 2: full load cycles in its life. The steel supporting it
- 7:15Speaker 2: needs to be designed for structural class SE, which means
- 7:19Speaker 2: it has to be good for about one million equivalent
- 7:22Speaker 2: full load cycles. That fifty percent factor gives you the
- 7:25Speaker 2: necessary safety margin on the steel details.
- 7:28Speaker 1: That feels like a huge responsibility for the engineer getting
- 7:31Speaker 1: that classification right from the start.
- 7:33Speaker 2: It is. It's everything, and there's one more check you
- 7:35Speaker 2: have to do first. If a structure is going to
- 7:38Speaker 2: see fewer than twenty thousand cycles in its entire life,
- 7:41Speaker 2: you might be able to skip the detailed fatigue check.
- 7:43Speaker 2: Might You can't just assume it, You the designer, have
- 7:46Speaker 2: to actually prove that the number of repeated loads is
- 7:49Speaker 2: below that twenty thousand threshold. If it's twenty thousand and one,
- 7:53Speaker 2: you're doing a fatigue check.
- 7:54Speaker 1: Okay, so we've got the loads, we've got the fatigue
- 7:56Speaker 1: life figured out. How does this translate to the actual
- 8:00Speaker 1: drawings the details?
- 8:01Speaker 2: The guide has a great checklist for this, broken down
- 8:03Speaker 2: by structural class. For example, for almost all these connections,
- 8:07Speaker 2: you have to use slip critical bolted connections, not the
- 8:10Speaker 2: standard bearing type bolts.
- 8:12Speaker 1: And why is that? Why slip critical because.
- 8:14Speaker 2: In a bearing connection, the bolt can shift just a
- 8:17Speaker 2: tiny bit inside the hole before it engages. Over millions
- 8:21Speaker 2: of cycles, that tiny movement leads to whear, to fretting,
- 8:24Speaker 2: and eventually to a fatigue failure.
- 8:27Speaker 1: So the slip critical bolt locks everything together and prevents
- 8:30Speaker 1: that movement completely.
- 8:31Speaker 2: It dramatically increases the fatigue life. Another big one is continuity.
- 8:36Speaker 2: The guide explicitly says do not use continuous runway beams
- 8:40Speaker 2: that span over multiple columns without a very careful, specialized analysis.
- 8:45Speaker 1: That's surprising. Continuous beams are usually stiffer. Why discourage them here?
- 8:49Speaker 2: Because they are incredibly sensitive to settlement. If one of
- 8:51Speaker 2: your columns settles even a fraction of an inch, it
- 8:54Speaker 2: can create huge, unplanned secondary stresses in the beam that
- 8:57Speaker 2: can lead to uplift at other supports and you guess it,
- 9:01Speaker 2: premature fatigue failure.
- 9:02Speaker 1: So simple spans are just more robust and forgiving in
- 9:05Speaker 1: the real world. What about things like deflection serviceability?
- 9:09Speaker 2: Oh, deflection is critical. The crane machinery hates movement for
- 9:14Speaker 2: vertical deflection. The limits are incredibly tight. For a light
- 9:17Speaker 2: service crane, it's maybe span over six hundred. For severe
- 9:21Speaker 2: service it tightens to span over one thousand. You're designing
- 9:25Speaker 2: something very very stiff and horizontally. Horizontally, it's span over
- 9:29Speaker 2: four hundred across the board. If you exceed that, you
- 9:32Speaker 2: get more of that crabbing we talked about, which wears
- 9:35Speaker 2: out the rails and the wheels.
- 9:36Speaker 1: Speaking of rails, what about just placing them correctly? I imagine
- 9:39Speaker 1: being off center would cause problems.
- 9:42Speaker 2: Big problems. The total tolerance for rail eccentricity, that's how
- 9:46Speaker 2: far off the center of the web you can be,
- 9:48Speaker 2: should not be more than three quarters.
- 9:50Speaker 1: Of the web's thickness, and if you go beyond that.
- 9:53Speaker 2: You introduce torsion, a twisting force that the beam was
- 9:56Speaker 2: probably not designed for icing projects where a sloppy field
- 10:00Speaker 2: building of the rail clips created too much eccentricity, and
- 10:02Speaker 2: it caused immediate problems. The crane wouldn't track right, the
- 10:05Speaker 2: rails would slip. It's a huge issue.
- 10:07Speaker 1: Twisting seems like a major theme. The guide calls out
- 10:10Speaker 1: a specific challenge with monosymmetric runway beams like a W
- 10:14Speaker 1: beam with a channel welded on top.
- 10:16Speaker 2: Yes, those sections are very common, but they're tricky. The
- 10:19Speaker 2: problem is that the vertical load from the crane is
- 10:21Speaker 2: applied above the section's sheer center, and the side thrust
- 10:25Speaker 2: is also at the top.
- 10:26Speaker 1: So you're creating a twisting moment, a torque.
- 10:28Speaker 2: A significant one, and that twisting action makes to be
- 10:32Speaker 2: much more susceptible to lateral torsional buckling. You can't just
- 10:36Speaker 2: use the simple buckling equations. The guide requires a rational
- 10:40Speaker 2: method of analysis, like the Flesher analogy to properly check
- 10:44Speaker 2: the stability of that kind of section.
- 10:45Speaker 1: Let's quickly touch on a few other things. Clearances seem obvious, but.
- 10:49Speaker 2: Critical, absolutely critical. You have to map out the crane's
- 10:52Speaker 2: entire operating envelope to make sure it doesn't foul on
- 10:55Speaker 2: knee braces or roof trusses or the columns themselves. And
- 10:59Speaker 2: if people need to get up there for maintenance, you
- 11:01Speaker 2: need to provide safe access. A common rule is about
- 11:04Speaker 2: four hundred and fifty millimeters of clearance.
- 11:06Speaker 1: And what about assessing older structures rehabilitation.
- 11:09Speaker 2: That's a huge part of this work, and it requires
- 11:12Speaker 2: a lot of engineering judgment. You might find that some
- 11:15Speaker 2: of the load factors we use for new design are
- 11:18Speaker 2: pretty conservative. If a structure has been performing perfectly fine
- 11:22Speaker 2: for thirty years under its real operating conditions, you can
- 11:25Speaker 2: often justify using slightly lower load factors.
- 11:28Speaker 1: Which could save a client a lot of money on
- 11:30Speaker 1: unnecessary upgrades millions.
- 11:33Speaker 2: It's about basing your assessment on proven historical performance.
- 11:37Speaker 1: Okay, let's bring this all home. Can you walk us
- 11:39Speaker 1: through the design process for a one way beam as
- 11:42Speaker 1: the guide lays it out.
- 11:43Speaker 2: Sure, it's a very logical process. Step one you establish
- 11:47Speaker 2: your design criteria, all the cranespecks, the four main loads
- 11:50Speaker 2: we talked about, and your required fatigue life from the
- 11:53Speaker 2: service class. Okay, except two, calculate your side thrust. Then
- 11:57Speaker 2: step three, and this is the key. You select a
- 11:59Speaker 2: preliminary beam section, but you don't select it based on strength.
- 12:03Speaker 1: You select it based on deflection.
- 12:04Speaker 2: You got it. Yeah. You find the minimum moment of
- 12:06Speaker 2: inertia the IX value that you need to meet that
- 12:09Speaker 2: super type span over one thousand limit for example. Serviceability
- 12:13Speaker 2: governs your first pick and after you have a section
- 12:15Speaker 2: that's stiff enough, and then you run the numbers. Step
- 12:18Speaker 2: four is the moving load analysis to find your maximum
- 12:21Speaker 2: moments and shears. Step five is to refine the section
- 12:24Speaker 2: and check its class. Then step six is the standard
- 12:28Speaker 2: strength check. You compare your factored resistance to your factored loads.
- 12:32Speaker 1: And the final can't miss step.
- 12:34Speaker 2: Step seven the fatigue check. You have to check the
- 12:37Speaker 2: stress range at every critical detail against the number of
- 12:41Speaker 2: cycles that's allowed. If you fail the fatigue check, you
- 12:43Speaker 2: have to go back. You either change the detail, make
- 12:45Speaker 2: the beam bigger, or sometimes both.
- 12:48Speaker 1: This has been incredibly insightful. It's so clear that the
- 12:51Speaker 1: mindset has to shift from just static strength to managing
- 12:54Speaker 1: these complex, dynamic, repeating loads. The fatigue analysis really is
- 12:59Speaker 1: the secret ingredient.
- 13:00Speaker 2: It is understanding that link between how the crane is used,
- 13:04Speaker 2: the service class, and how the structure needs to be
- 13:06Speaker 2: designed the structural class That is the most important concept
- 13:10Speaker 2: for any engineer in this field to grasp. So with
- 13:13Speaker 2: that in mind, let's end with a quick review exercise
- 13:16Speaker 2: for you. A new structure is being designed for a
- 13:19Speaker 2: Class E that's severe service crane. Your analysis shows that
- 13:23Speaker 2: the critical runway beam splice will see about five hundred
- 13:26Speaker 2: thousand equivalent full load cycles. Okay, according to the criteria
- 13:30Speaker 2: we discussed, what is the minimum recommended number of full
- 13:34Speaker 2: load cycles that structure must be designed for and what
- 13:37Speaker 2: structural classification does that put it in?
- 13:39Speaker 1: So think about that, is it a light or heavy
- 13:41Speaker 1: duty application? What factor do you apply to the actual
- 13:44Speaker 1: cycles to get your design target. If you get that,
- 13:46Speaker 1: you'll know exactly what structural class needs to go on
- 13:49Speaker 1: the drawings.
- 13:50Speaker 2: Use the guide check your load combinations and never ever
- 13:53Speaker 2: forget about fatigue.
- 13:54Speaker 1: Thanks for diving dep with us. Now go out there
- 13:56Speaker 1: and build something resilient.