Tyrrhenian Link completes submarine works as energy security fears mount - Apr 9, 2026
As of April 9, today’s news sees the completion of Terna's Tyrrhenian Link submarine works and ongoing geopolitical tensions affecting energy supplies. The eastern section of the Tyrrhenian Link, Terna’s strategic HVDC interconnection between Campania, Sicily, and Sardinia, has completed its submarine works between Campania and Sicily within twelve months. Prysmian carried out the installation of the two 490-km submarine cables over 150 days of naval operations, using its vessels Leonardo da Vinci and Monna Lisa, supported by advanced technologies and continuous route monitoring. With a total…