Latest / Illinois Valley - Shaw Local / Strouss Park playground rebuild finally moving forward after repeated delays
Transcript
- 0:05Speaker 1: Strauss Park playground rebuild finally moving forward after repeated delays.
- 0:11Speaker 1: Written by Matthias Werner. This article is being read by
- 0:15Speaker 1: an automated voice brought to you by Everlett. There's light
- 0:20Speaker 1: at the end of the tunnel for the completion of
- 0:22Speaker 1: the Strauss Park playground in Mendota. Project director Annie Short
- 0:27Speaker 1: provided an update Monday, following the fourth snafu in rebuilding
- 0:31Speaker 1: the playground late last month. Cunningham came out and did
- 0:35Speaker 1: an assessment and after negotiations, they're going to send out
- 0:38Speaker 1: a whole team to build the playground for us, so
- 0:41Speaker 1: we do not have to Short said, I think Cunningham
- 0:45Speaker 1: recognized an opportunity to make up for what has happened.
- 0:48Speaker 1: Cunningham Recreation, the organization that oversees playgrounds with game time equipment,
- 0:54Speaker 1: repeatedly sent the wrong materials to the Strauss Park project,
- 0:58Speaker 1: delaying the completion date. We explain that with Sweetcorn Fest
- 1:02Speaker 1: this week, it's going to be a little crazy and
- 1:05Speaker 1: may be hard to get things around. So they're starting
- 1:07Speaker 1: next week and said it should take about two weeks.
- 1:10Speaker 1: Short said, it's a little late, but at least it
- 1:13Speaker 1: will get built, so we're excited about that. Short said
- 1:17Speaker 1: that Cunningham estimates it as a seventy five thousand dollars investment.
- 1:21Speaker 1: As part of the negotiated agreement for the labor to
- 1:24Speaker 1: be taken care of by the company rather than the city,