- 0:00Speaker 1: Welcome back to the deep dive, where we deliver high
- 0:02Speaker 1: value knowledge tailored just for you. Today, we're tearing into
- 0:06Speaker 1: one of the most critical documents for anyone building, designing,
- 0:10Speaker 1: or even just studying large steel structures. This deep dive
- 0:14Speaker 1: is really custom made for the engineering student, the young professional,
- 0:18Speaker 1: and frankly, the self taught learner who needs a shortcut
- 0:21Speaker 1: to practical expertise.
- 0:23Speaker 2: That's right. Our mission today is to pull out the
- 0:25Speaker 2: most actionable, ready to use concepts from what is really
- 0:28Speaker 2: the authoritative text here. It's the AISC Design Guide twenty
- 0:32Speaker 2: three Constructibility of Structural Steel Buildings. We're going to move
- 0:36Speaker 2: beyond just pure strength calculations and really dive into the
- 0:39Speaker 2: art of building efficiently.
- 0:40Speaker 1: Okay, so let's unpack that core idea constructibility. It's a
- 0:44Speaker 1: term that gets thrown around a lot. We aren't just
- 0:45Speaker 1: talking about whether something can be built right, We're talking
- 0:48Speaker 1: about optimizing the how exactly.
- 0:50Speaker 2: The Construction Industry Institute or CII, they define constructibility as well.
- 0:55Speaker 2: It's the optimum use of construction knowledge and experience in planning, design, procurement,
- 1:00Speaker 2: and field operations to achieve overall project objectives.
- 1:03Speaker 1: Okay, So boiling that down for us.
- 1:05Speaker 2: Put simply, it's all about maximizing simplicity, economy, and the
- 1:10Speaker 2: speed of construction. The goal is the simplest, easiest, fastest
- 1:14Speaker 2: design possible that still meets all the performance requirements.
- 1:18Speaker 1: I want to start with the why. I mean, you
- 1:20Speaker 1: often hear that the construction industry kind of lags behind,
- 1:23Speaker 1: say manufacturing and productivity and innovation. Why is constructibility the
- 1:29Speaker 1: remedy for that?
- 1:31Speaker 2: Because our industry is, by its nature often very fragmented.
- 1:36Speaker 2: You know, design happens over here in a silo, and
- 1:39Speaker 2: then construction happens over there in another silo. This can
- 1:42Speaker 2: and often does create a pretty adversarial relationship between the
- 1:45Speaker 2: design team and the field team. Constructibility breaks that down.
- 1:49Speaker 1: And the financial benefits you mentioned, I mean they're massive.
- 1:51Speaker 1: The guide site CII research suggesting cost reductions of at
- 1:54Speaker 1: least six percent.
- 1:55Speaker 2: At least six and potentially as high as twenty three percent.
- 1:58Speaker 1: Twenty three percent is just enormous figure. Where do those
- 2:01Speaker 1: gains actually come from? Is it mostly saving on materials
- 2:04Speaker 1: or is it labor?
- 2:05Speaker 2: It is overwhelmingly labor and schedule reduction. That's why the
- 2:09Speaker 2: benefit to cost ratio for adopting these practices can hit
- 2:13Speaker 2: ten to one.
- 2:14Speaker 1: Ten to one. Wow.
- 2:15Speaker 2: Yeah, the true value is removing complexity and just ensuring
- 2:19Speaker 2: the flow of work on site.
- 2:21Speaker 1: Okay, here's a crucial distinction one that I think often
- 2:23Speaker 1: gets confused, constructibility versus value engineering or VE. Why can't
- 2:29Speaker 1: we just ve the project later because.
- 2:31Speaker 2: VE happens when it's well when it's just too late.
- 2:35Speaker 2: Think about that curve showing your ability to influence cost
- 2:39Speaker 2: and schedule.
- 2:39Speaker 1: Right, it's highest at the very beginning.
- 2:41Speaker 2: It's maximal during conceptual planning, and then it drops off
- 2:44Speaker 2: a cliff as you move into design development. Constructibility is
- 2:47Speaker 2: a philosophy that starts right at the conceptual phase. If
- 2:50Speaker 2: you wait, the major decisions have already created what the
- 2:54Speaker 2: guide calls a limited access highway for your project.
- 2:57Speaker 1: I love that analogy. You can only make minor tweaks exactly.
- 3:00Speaker 2: You can fine tune the car once it's built, But
- 3:02Speaker 2: constructibility is designing the car from scratch to be easily
- 3:05Speaker 2: assembled in the first place.
- 3:06Speaker 1: So to make this work, you need that input really early.
- 3:09Speaker 2: Precisely, to get that knowledge in early, you need experienced
- 3:13Speaker 2: construction people, specialty structural engineers, contractor engineers, independent consultants. They
- 3:19Speaker 2: provide up to date cost estimates and site knowledge before
- 3:22Speaker 2: the fundamental layout is locked in.
- 3:24Speaker 1: And speaking of integration, I have to assume that Building
- 3:27Speaker 1: Information Modeling BIM is pretty much essential for this.
- 3:30Speaker 2: Now. It is the mechanism, it's the tool that makes
- 3:33Speaker 2: it happen. BIM supports constructibility by enhancing three D visualization.
- 3:38Speaker 2: The immediate benefit for you is interference checking. You can
- 3:41Speaker 2: spot clashes like a pipe running straight through a primary
- 3:44Speaker 2: beam web in the design.
- 3:46Speaker 1: Phase where it costs five minutes to fix.
- 3:48Speaker 2: Exactly, instead of finding it in the field where it
- 3:50Speaker 2: becomes an expensive clash requiring an RFI, a delay, and
- 3:53Speaker 2: a costume modification.
- 3:54Speaker 1: So, if that conceptual phase is our biggest chance for influence,
- 3:57Speaker 1: let's talk about where the concept moves next the board.
- 4:00Speaker 1: What are the key initial decisions that have to happen first.
- 4:04Speaker 2: Well, those initial planning discussions are where you establish the
- 4:07Speaker 2: project program the constraints. The design team has to review
- 4:11Speaker 2: all the site specifics soil conditions, seismic site class and
- 4:15Speaker 2: any special architectural needs.
- 4:17Speaker 1: Like architecturally exposed steel AESS which I know has really
- 4:21Speaker 1: stringent requirements.
- 4:23Speaker 2: Very stringent detailing and fabrication requirements and early decisions on
- 4:27Speaker 2: performance based design are also critical.
- 4:29Speaker 1: Right at this stage, Okay, onto the documents themselves. The
- 4:33Speaker 1: guide really hammers the point that coordinated and complete construction
- 4:37Speaker 1: documents are paramount. Can incomplete documents really derail a project
- 4:41Speaker 1: that dramatically?
- 4:42Speaker 2: Oh absolutely, Incomplete documents are the fast track to failure.
- 4:45Speaker 2: I mean they lead to inaccurate bids because contractors are
- 4:48Speaker 2: forced to guess.
- 4:49Speaker 1: Which means you get a high volume of RFIs, a.
- 4:51Speaker 2: High volume of requests for information, which slows the job
- 4:56Speaker 2: to a crawl, and that leads to conflict and you
- 4:59Speaker 2: know sometimes even litigation.
- 5:00Speaker 1: And that coordination goes beyond just your own grid lines, right.
- 5:03Speaker 2: Far beyond the structural engineer of record. The seer has
- 5:08Speaker 2: to coordinate tolerances with everyone, and that's a huge interface problem.
- 5:12Speaker 2: You have your precise deal tolerances and then you have
- 5:14Speaker 2: the much looser general concrete tolerances.
- 5:18Speaker 1: They often clash, especially at the columnbase.
- 5:20Speaker 2: I imagine that's ground zero for trouble. For example, general
- 5:24Speaker 2: concrete placement tolerances in ACI one seventeen can be plus
- 5:28Speaker 2: or minus one inch one inch. Meanwhile, the AIS Code
- 5:31Speaker 2: of Standard Practice specifies precision down to an eighth of
- 5:35Speaker 2: an inch for anchor rods. The seer has to see
- 5:38Speaker 2: that conflict coming and maybe even define special tighter tolerances
- 5:42Speaker 2: in the documents to prevent chaos in the field.
- 5:45Speaker 1: Let's talk about maximizing economy through some specific design choices.
- 5:48Speaker 1: The guide is very clear about repetition.
- 5:51Speaker 2: Maximize. It's one of the most essential constructibility principles. Maximize
- 5:54Speaker 2: the repetition of beam and column sizes, even.
- 5:56Speaker 1: If it means adding a little bit of extra weight
- 5:58Speaker 1: in some spots.
- 5:59Speaker 2: Yes, even if using a standard member across a floor
- 6:03Speaker 2: adds some weight in a few bays, the savings in detailing, fabrication, erection,
- 6:08Speaker 2: and inspection time will almost always outweigh that small increase
- 6:11Speaker 2: in material cost. Simplicity drives economy.
- 6:15Speaker 1: And that same idea extends to connections.
- 6:17Speaker 2: It does. You should favor simple, common connections, things like
- 6:21Speaker 2: single plate or single angle sheer connections. Fewer detailed pieces
- 6:24Speaker 2: means less shop labor and faster, safer erection. You want
- 6:27Speaker 2: to avoid or at least minimize costly items like stiffeners
- 6:31Speaker 2: and web doublers that just require so much extra welding
- 6:34Speaker 2: and material, and.
- 6:35Speaker 1: To avoid those coordination nightmares with other trades.
- 6:38Speaker 2: Avoid mixing your primary framing materials if you can. If
- 6:41Speaker 2: you try to integrate structural steel, load bearing masonry, and
- 6:45Speaker 2: precast concrete into one primary.
- 6:47Speaker 1: System, the coordination must be a nightmare.
- 6:49Speaker 2: It adds considerable time cost and a huge risk of error.
- 6:52Speaker 2: And you know, in a practical note, think about calm splices.
- 6:55Speaker 2: Just locate them at a safe, practical working height, typically
- 6:58Speaker 2: four feet above the top of the steel for the erect.
- 7:00Speaker 1: The guide also talks about the interdependence of elements. Can
- 7:04Speaker 1: you give us that example of the complex joint it references?
- 7:07Speaker 2: Yeah, the best illustration is a complex multi member joint,
- 7:10Speaker 2: usually where steel has to transfer significant forces to something
- 7:14Speaker 2: that isn't steel, like a concrete sheer wall. If the
- 7:17Speaker 2: design documents don't fully detail how those forces transfer, the
- 7:21Speaker 2: exact anchors, the embedments, the interface dimensions, the specialty engineer
- 7:26Speaker 2: is stuck creating a complex, time consuming field fixed later.
- 7:30Speaker 1: On, and that can delay a whole floor of work easily.
- 7:33Speaker 1: All right, let's tackle a major structural engineering myth for
- 7:37Speaker 1: students moving from theory to practice. What's the mistaken way
- 7:40Speaker 1: to measure economy?
- 7:41Speaker 2: Oh? This is a big one. Economy is so often
- 7:44Speaker 2: mistakenly measured in dollars per ton or pounds per square
- 7:47Speaker 2: foot of.
- 7:47Speaker 1: Steel, but that's not the real number.
- 7:49Speaker 2: No, the true measure of economy for the owner is
- 7:52Speaker 2: dollars per square foot of total building area. This is
- 7:55Speaker 2: a massive aha moment.
- 7:57Speaker 1: So a heavier steel frame can actually result in a
- 8:00Speaker 1: lower total cost. How do you explain that to a
- 8:02Speaker 1: client who's just focused on reducing steel weight?
- 8:05Speaker 2: You explain that by increasing the size and weight of
- 8:07Speaker 2: a member, you can reduce the total number of pieces,
- 8:10Speaker 2: the number of connections, the number of detailed items, and
- 8:13Speaker 2: even the number of supporting foundations. And since labor, both
- 8:17Speaker 2: in the shop and in the field is the dominant
- 8:19Speaker 2: cost driver, reducing the piece count reduces labor and that
- 8:23Speaker 2: usually offsets the material increase very quickly.
- 8:25Speaker 1: So if we apply that, what kind of guidance does
- 8:27Speaker 1: the guide offer for say, a typical floor framing system
- 8:31Speaker 1: for a.
- 8:32Speaker 2: Typical office floor, maximizing the bay area is key. A
- 8:35Speaker 2: bay size somewhere between seven hundred and fifty and two
- 8:38Speaker 2: hundred and fifty square feet, where the length is about
- 8:40Speaker 2: one point twenty five to one point five times the
- 8:43Speaker 2: width that tends to maximize economy.
- 8:45Speaker 1: Because the larger deeper beams mean fewer pieces.
- 8:47Speaker 2: Fewer components, fewer connections, and that drives down the total cost.
- 8:51Speaker 2: And another thing designers should consider non composite construction. If
- 8:55Speaker 2: only a few members would benefit from sheer studs.
- 8:58Speaker 1: Why is that?
- 8:59Speaker 2: Because the mobilization costs for the sheer stud crew can
- 9:01Speaker 2: sometimes just negate the benefits of going composite in the
- 9:04Speaker 2: first place.
- 9:05Speaker 1: What about for lateral load systems like bracing, what are
- 9:08Speaker 1: the better choices for constructibility?
- 9:10Speaker 2: For vertical bracing, the chevron system so a V or
- 9:14Speaker 2: an inverted V is often more efficient than traditional X bracing.
- 9:18Speaker 2: It uses shorter members and reduces the bending moment on
- 9:21Speaker 2: the floor beam. And for horizontal bracing like in an
- 9:24Speaker 2: industrial building, diamond bracing is simpler to design and install
- 9:28Speaker 2: than X pracing, which gives you a big reduction in
- 9:31Speaker 2: field labor.
- 9:32Speaker 1: Sometimes project constraints like city codes really restrict the total
- 9:36Speaker 1: building height. Are there special framing systems just for minimizing
- 9:41Speaker 1: floor to floor depth?
- 9:42Speaker 2: Yes, If height is the main constraint, two systems really
- 9:45Speaker 2: stand out. First is staggered truss framing. It uses story
- 9:49Speaker 2: high trusses that are staggered from floor to floor, often
- 9:52Speaker 2: with pre cast hollow core playing, and that.
- 9:54Speaker 1: Lets you get really tight four heights.
- 9:56Speaker 2: Incredibly tight, sometimes as low as eight feet eight inches.
- 9:59Speaker 2: The second is using integrated systems, which means beams with
- 10:02Speaker 2: web penetrations or trusses that let you run mechanical, electoral,
- 10:06Speaker 2: and plumbing within the structural depth, not below it.
- 10:09Speaker 1: Let's drive this home with that manufacturing case study from
- 10:11Speaker 1: the guide. It's a great example.
- 10:13Speaker 2: It's so powerful. It was one hundred thousand square foot
- 10:16Speaker 2: facility and it was an over budget. The original design
- 10:19Speaker 2: used roof trusses spaced at twenty five feet. After a
- 10:23Speaker 2: constructibility review, they increase that's basing to fifty feet. This
- 10:27Speaker 2: meant bigger, heavier trusses, sure, but the final outcome was
- 10:30Speaker 2: a four hundred thousand dollars cost reduction. Wow, a twenty
- 10:33Speaker 2: eight percent lighter overall frame, and a five week reduction
- 10:37Speaker 2: in the schedule. The heavier pieces just drastically cut the
- 10:40Speaker 2: number of connections and direction picks they needed.
- 10:43Speaker 1: Okay, let's move to the shop and the site. How
- 10:45Speaker 1: does good constructibility speed up detailing and fabrication?
- 10:48Speaker 2: Well? Complete design documents let the fabricator generate an advanced
- 10:51Speaker 2: bill of materials right away, and more than that, using
- 10:55Speaker 2: BIM models and standard data formats like CIS two can
- 10:58Speaker 2: totally change the shop drawing process. The seer can review
- 11:01Speaker 2: the model virtually, which can reduce their approval time from
- 11:04Speaker 2: weeks to just a few days.
- 11:06Speaker 1: Let's get into connections, starting with bolts. If uniformity is key,
- 11:10Speaker 1: how does that play out in the choices you make?
- 11:12Speaker 2: You have to minimize the number of high strength bolt
- 11:14Speaker 2: grades and diameters on any single project. And critically, from
- 11:19Speaker 2: a cost standpoint, snug Titan joints are the cheapest option.
- 11:22Speaker 1: Cheaper than pretention or slip critical.
- 11:24Speaker 2: Much cheaper, pretention joints cost more, and slip critical joints
- 11:27Speaker 2: are the most expensive. You should use snug titan to
- 11:30Speaker 2: wherever the RCSC specification allows it. Don't overspecify.
- 11:33Speaker 1: Is the cost difference really that big? Does it justify
- 11:35Speaker 1: the extra inspection time?
- 11:37Speaker 2: Almost never? Unless the service requirements absolutely demand a slip
- 11:41Speaker 2: critical joint, the labor and inspection costs are substantial. You
- 11:45Speaker 2: save those for the connections that truly need them. And
- 11:47Speaker 2: one practical note, if your steel is galvanized, you have
- 11:51Speaker 2: to use AsTMa three twenty five bolts A four to
- 11:54Speaker 2: ninety bolts cannot be galvanized.
- 11:56Speaker 1: What about welding, where are the big cost drivers and
- 11:59Speaker 1: the pitfalls to avoid the field fill.
- 12:01Speaker 2: At welds or partial joint penetration PGAP groove welds are
- 12:04Speaker 2: generally more economical than complete joint penetration or cgap welds.
- 12:09Speaker 2: And here's a major thing to avoid in the field.
- 12:11Speaker 2: Never just use the standard weld all around symbol without
- 12:14Speaker 2: a specific detail. Why is that a problem Because welding
- 12:17Speaker 2: the entire perimeter of a connection forces the welder to
- 12:20Speaker 2: change planes, which is a really common source of quality
- 12:23Speaker 2: issues Undercut, poor profile, undersized welds at.
- 12:27Speaker 1: The corners, so you need to be explicit specify.
- 12:30Speaker 2: The exact weld size, length, and location required.
- 12:33Speaker 1: Let's quickly touch on surface prep and codings. Is a
- 12:36Speaker 1: shop primer really necessary for steel that's just going to
- 12:39Speaker 1: be covered by interior finishes?
- 12:41Speaker 2: No, Generally it's totally unnecessary for steel that will be hidden.
- 12:45Speaker 2: That shot primer is really just a bonding layer for
- 12:47Speaker 2: other coatings. It offers almost no long term corrosion protection
- 12:51Speaker 2: on its own. But if you're galvanizing hollow structural sections HSS.
- 12:55Speaker 2: You have to be really careful to detail drainage and
- 12:58Speaker 2: vent holes to prevent gas expand, and also be aware
- 13:01Speaker 2: of risks with cold work steel which can get brittle
- 13:04Speaker 2: if it's not treated correctly.
- 13:05Speaker 1: On site. Efficiency really means minimizing material handling.
- 13:09Speaker 2: Yes, this is just in time delivery combined with what's
- 13:13Speaker 2: called first pass erection. The goal is to set the
- 13:15Speaker 2: materials down one time and never have to move them again. Now,
- 13:19Speaker 2: if the general contractor needs to control the specific sequencing
- 13:22Speaker 2: of erection, which happens on complex jobs, they have to
- 13:26Speaker 2: clearly state that requirement in the contract documents. That's per
- 13:29Speaker 2: the Code of Standard Practice.
- 13:30Speaker 1: Finally, we have to talk about maybe the most notorious
- 13:33Speaker 1: interface problem, anchor rod tolerances. You mentioned that huge disconnect
- 13:38Speaker 1: between AISC's eighteen inch expectation and aci's one inch concrete tolerance.
- 13:44Speaker 2: This conflict is so foreseeable and so frustrating. OSHA mandates
- 13:48Speaker 2: a minimum of four anchor rods per column base for
- 13:50Speaker 2: stability during erection, but if those rods are misplaced, and
- 13:54Speaker 2: they often are, it just shuts down the work.
- 13:56Speaker 1: So for our listeners who are SAH what is the
- 13:59Speaker 1: single most important coordination step to avoid that misalignment in
- 14:02Speaker 1: the first place.
- 14:03Speaker 2: Proactive coordination of the rebar and anchors rod drawings. The
- 14:07Speaker 2: seer needs to coordinate their anchor rod locations with the
- 14:10Speaker 2: reinforcing steel detailer to make sure there are no conflicts
- 14:13Speaker 2: before the concrete gets poured. But if it still happens,
- 14:16Speaker 2: the common field fixes and these all require ser approval
- 14:20Speaker 2: include using oversized holes in the base plate, cutting and
- 14:23Speaker 2: welding threaded extensions, or using heavy plate washers and slotted
- 14:26Speaker 2: holes for really severe cases.
- 14:28Speaker 1: And one last technical note on erection stability and camber.
- 14:32Speaker 2: The erector is fully responsible for stability during construction. Now,
- 14:35Speaker 2: it's not a substitute for proper engineering analysis, but the
- 14:38Speaker 2: guide does note a good rule of thumb for girders
- 14:41Speaker 2: the length to flangewidth ratio, so other dollars should generally
- 14:45Speaker 2: be less than eighty to ensure stability during erection, and
- 14:47Speaker 2: camber only specify it if the deflection is three quarters
- 14:50Speaker 2: of an inch or more. Do not camber short, non
- 14:53Speaker 2: uniform or moment connected members. It just often creates more
- 14:57Speaker 2: problems than it solves. So to synthesize this whole deep
- 15:00Speaker 2: dive constructibility isn't about being a design critic after the fact,
- 15:04Speaker 2: It's about proactive, integrated engagement across the entire process from
- 15:08Speaker 2: concept all the way to completion. By infusing that construction
- 15:12Speaker 2: knowledge early, you anticipate and solve expensive field problems before
- 15:16Speaker 2: they happen, and you maximize the prosperity of the entire project.
- 15:19Speaker 1: And here's a final provocative thought for you to consider,
- 15:22Speaker 1: one pulled straight from the reality of the job site.
- 15:24Speaker 1: Thermal effects. They are a huge reality on exposed steel structures.
- 15:29Speaker 1: Steel moves a lot throughout the day as temperatures change.
- 15:32Speaker 1: Erection teams will often plum high rise structures during the
- 15:35Speaker 1: early mornings, say between three am and five am, because
- 15:38Speaker 1: that's when the structure has thermally normalized. So considering that
- 15:42Speaker 1: movement and establishing a base temperature for adjustments is absolutely
- 15:45Speaker 1: crucial for long spans or high rise buildings.
- 15:48Speaker 2: And to really submit what we've discussed, here's a short
- 15:50Speaker 2: exercise for you to think through based on the principles
- 15:53Speaker 2: we covered. Specifically that dollars per square foot metric explain
- 15:57Speaker 2: the economic trade off between increasing the steel weight of
- 15:59Speaker 2: pie floor beams by using larger wider bays versus maximizing
- 16:03Speaker 2: the number of smaller beams and connections in a typical
- 16:06Speaker 2: low rise office building, which solution generally results in a
- 16:10Speaker 2: lower total project cost and why and remember to factor
- 16:14Speaker 2: in fabrication and erection labor versus the material cost