Latest / Illinois Valley - Shaw Local / Utica solar farm to go live late summer 2027, offering Ameren customers 15% savings
Transcript
- 0:05Utica solar farm to go live late summer 2027, offering Ameren customers
- 0:1015% savings.
- 0:12Written by Emily Beebe.
- 0:14This article is being read by an automated voice, brought to you
- 0:18by Everlit.
- 0:20A field that sat unused south of Route 6 is on its
- 0:23way to becoming a community solar farm, and if the timeline holds,
- 0:26it will start sending power to the grid late next summer.
- 0:30Utica Solar is a 6.7-megawatt project being built, owned and operated by
- 0:35Nexamp, a company founded in 2007 by two U.S. Army Veterans. The
- 0:40company is headquartered in Boston, runs a second headquarters in Chicago and
- 0:44has about 60 active projects in Illinois. The site, just west of
- 0:48Route 178, is about 28 acres of fenced farmland that will hold
- 0:54just over 10,000 American-made solar panels mounted on tracking systems that follow
- 0:59the sun through the day.
- 1:00This is for us a little bit on the larger side, said
- 1:03Keith Hevenor, communication manager at Nexamp. Most of our projects probably are
- 1:08more in the three to five megawatt range.
- 1:11Construction began at the start of June, and Nexamp is targeting permission
- 1:15to operate from Ameren by Sept. 1, 2027. The project was years
- 1:21in the making before that. The company leases rather than buys its
- 1:25sites, typically under 25 to 30-year agreements with landowners, and looks for
- 1:30land near electrical infrastructure where panels can connect to the grid.
- 1:34Like other community solar farms, Utica Solar will not send power directly
- 1:39to subscribers homes. It feeds the grid, and Ameren pays Nexamp for
- 1:43that power in the form of bill credits, which Nexamp then shares
- 1:46with subscribers at a discount. In Illinois, that discount is 15%.
- 1:51Hevenor used a household that uses $100 of electricity a month as
- 1:56an example: the subscriber would receive about $100 in credits to offset
- 2:01their Ameren bill, then be billed $85 by Nexamp, reflecting the $15
- 2:06discount. Credits are annualized, since panels generate more power in long summer
- 2:11days than short winter ones.
- 2:14There’s no other fee. There’s no enrollment fee. There’s no setup fee.
- 2:18There’s nothing, Hevenor said. The only thing you’re paying for is the
- 2:22credits that you earn that go toward offsetting your utility bill.
- 2:26Subscriptions are month-to-month, with no cancellation fee and no credit check, and
- 2:31subscribers don’t have to live near Utica. Anyone in Ameren’s service territory
- 2:36can subscribe. A project of this size could support about 1,000 residential
- 2:41subscribers, though a portion of Utica Solar’s capacity is committed to anchor
- 2:45customers.
- 2:47The build itself is being done by local contractors, providing typically 40
- 2:51to 50 jobs over a 12 to 18-month construction window. Once the
- 2:56farm goes live, no one will work on site regularly. Nexamp contracts
- 3:00with local electricians as needed and local landscaping companies for mowing and
- 3:04snow plowing.
- 3:06The project also will generate tax revenue for the village of Utica.
- 3:10Because the solar farm changes the land’s tax classification from agricultural to
- 3:15commercial, Nexamp pays commercial property taxes on the site.
- 3:19Nexamp establishes a decommissioning bond at the start of every project, with
- 3:24money set aside to cover removing and recycling equipment when the farm
- 3:27reaches the end of its life. Steel poles are driven into the
- 3:31ground, along with one or two 10-by-10 concrete pads for transformers and
- 3:35inverters, and a fence.
- 3:38Hevenor said the land could essentially be returned to farmland once the
- 3:42project ends, and the lease can be renewed by both sides or
- 3:46the land returned to its owner.
- 3:48As for the timeline, Hevenor said there is little that could delay
- 3:52the project at this stage. The schedule could slip potentially 30 to
- 3:5660 days depending on Ameren’s interconnection queue, with testing expected over the
- 4:01summer.
- 4:02I can’t say the schedule wouldn’t change at all, but I can
- 4:05say that it’s rare that it changes significantly at this stage, he
- 4:09said.