- 0:05Speaker 1: Yorkville Data center settlement delayed after second resident lawsuit file
- 0:09Speaker 1: against city developer. Written by Joey Weslow, this article is
- 0:16Speaker 1: being read by an automated voice brought to you by Everlett.
- 0:20Speaker 1: While attorneys previously said substantial progress has been made toward
- 0:24Speaker 1: a settlement for a resident claiming harm from the one
- 0:27Speaker 1: thousand and thirty four acre Project Cardinal Data Center in Yorkville,
- 0:32Speaker 1: another resident led lawsuit against the city and the developers
- 0:36Speaker 1: has cast everything up in the air. During a May
- 0:39Speaker 1: eight status hearing before Kendall County Judge Robert Pilmer, attorneys
- 0:43Speaker 1: for both sides said they need an extension until May
- 0:46Speaker 1: twenty second to see how the new lawsuit impacts the
- 0:49Speaker 1: settlement negotiations. Resident John Brian filed the lawsuit on October
- 0:55Speaker 1: twenty eighth, twenty twenty five, against the United City of Yorkville,
- 0:58Speaker 1: claiming that Project Cardinal, with its fourteen to two story
- 1:01Speaker 1: warehouses to be built over a decade or more, will
- 1:05Speaker 1: negatively impact his property values and quality of life. At
- 1:09Speaker 1: a December nineteen, twenty twenty five hearing, the developer, Pioneer
- 1:13Speaker 1: Development LLC, requested and was granted permission to join the
- 1:17Speaker 1: case as a defendant. Since then, both legal teams have
- 1:21Speaker 1: repeatedly asked for extension since late twenty twenty five, while
- 1:25Speaker 1: telling the judge they are close on a settlement agreement.
- 1:28Speaker 1: Neither side has disclosed a possible monetary amount or specific
- 1:32Speaker 1: details of the settlement. On April twenty ninth, several residents
- 1:37Speaker 1: filed a separate lawsuit against the City of Yorkville and
- 1:40Speaker 1: Pioneer Development LLC, claiming the city failed to notify immediate
- 1:45Speaker 1: area residents of the plans to annex the unincorporated Kendall
- 1:49Speaker 1: County land and rezone the property to manufacturing for data
- 1:53Speaker 1: center construction. The residents involved in the lawsuit have united
- 1:57Speaker 1: to form a community based organization, Preserve Our Use Yorkville
- 2:00Speaker 1: and Community, LLC, with the stated goal of filing lawsuits
- 2:04Speaker 1: against the city to halt data center construction. Accompanying the
- 2:08Speaker 1: group as plaintiffs is sky Fall Equestrian LLC residents Dorothy
- 2:12Speaker 1: and John Flisk, and Charles and Laura Casper. Pausing to
- 2:16Speaker 1: consider potential impacts During the May eighth status hearing, attorney
- 2:20Speaker 1: Matt Klepper, representing Pioneer Development LLC, said his client needs
- 2:25Speaker 1: time to assess how the new lawsuit impacts the path
- 2:28Speaker 1: forward with that new lawsuit. I think all the parties
- 2:32Speaker 1: right now are pausing to consider what, if any impact
- 2:36Speaker 1: that has on the settlement that we've been discussing with,
- 2:38Speaker 1: Brian Klepper said during the hearing. I think we would
- 2:42Speaker 1: ask that it be continued for a couple of weeks
- 2:45Speaker 1: so we can sort our whatever impact this new lawsuit
- 2:48Speaker 1: might have. Both Attorney Todd Rodden representing Brian, and Attorney
- 2:53Speaker 1: Tom Gardner representing the United City of Yorkville agreed to
- 2:57Speaker 1: the extension. Pillmer granted an extension to May twenty second
- 3:01Speaker 1: for further case status regarding the potential settlement. The lawsuit
- 3:06Speaker 1: filed by Preserve Are Yorkville and Community LLC is also
- 3:09Speaker 1: before Pilmer. The next court date for that lawsuit is
- 3:12Speaker 1: July twenty fourth. During the April fourteenth City Council meeting,
- 3:17Speaker 1: the city announced the developers for the proposed eighty acre
- 3:20Speaker 1: Meyer Data Center withdrew their proposal after losing city council support.
- 3:25Speaker 1: Mayor John Purcell said there's no more appetite from the
- 3:29Speaker 1: City Council for data center proposals outside of what's already
- 3:32Speaker 1: been approved. The city was at one point entertaining about
- 3:36Speaker 1: a dozen different data center proposals, stretched out across more
- 3:40Speaker 1: than three thousand acres of the Eldamain Corridor for Yorkville's
- 3:44Speaker 1: own data center alley, the city already has approved the
- 3:48Speaker 1: two hundred twenty eight acre Cyrus one Data Center, the
- 3:51Speaker 1: Project Cardinal Data Center, and the five hundred forty acre
- 3:55Speaker 1: Project Steel Data Center,