Latest / Project Podcast / State-of-the-art risk management in projects: What you need to know
Transcript
- 0:08Welcome to the APM Podcast. APM is the chartered body for
- 0:11the project profession. My name is Emma De Vita and I'm
- 0:15the editor of Projects, APM's Quarterly Journal and your host
- 0:19this podcast. I'm speaking with Peter Simon, a
- 0:22director at Lucidus Consulting and a member of the APM Risks
- 0:25Committee. He is co-author with Alexander
- 0:28for Brooke, Marianne Bosch Reichelt, both of the Technical
- 0:32University of Delft and Sara Rye of the University of Bradford.
- 0:36Venue report to be published by APM in the autumn, this
- 0:40groundbreaking research looks into opportunity management as
- 0:43part of the overall project risk management process.
- 0:46The findings of the research and survey revealed a number of
- 0:49notable areas where what is defined in the standards and
- 0:52written in textbooks do not in fact match what's happening.
- 0:56But quite simply, few organisations do it.
- 0:59Some have tried and failed, while others don't believe in
- 1:02it. Listen on for Pete's expert
- 1:04consideration and advice. Welcome, Peter.
- 1:13Thanks for joining us today at the APM podcast.
- 1:16Why don't we start at the beginning?
- 1:18How would you define risk management?
- 1:22First, management is the management of those things that
- 1:25might happen that, if they did, would impact the objectives of
- 1:29the project. It could be more than just
- 1:31objectives. We talk about time, cost and
- 1:33quality. It could be the benefits.
- 1:36Some types say the outputs and the outcomes and the benefits.
- 1:40And I would say there also that it might be, it's things that
- 1:42might happen by chance. We might come onto that later
- 1:45on. So things that could just
- 1:47happen, but it's a marriage with the votes.
- 1:49Where does the opportunity and threat of risk fit within this
- 1:54and how would you define those concepts?
- 1:58In 1996, the PMI redefined the term risk to be something that
- 2:05ever happened, could have a positive or negative impact on
- 2:09the project's objectives, and likewise APM followed I think in
- 2:131997. So the concept there is that
- 2:17things might happen, but they could either have a beneficial
- 2:21impact on your project, which is an opportunity, or they could
- 2:25have a negative impact on your project, which would be a
- 2:28threat. Unfortunately a lot of people
- 2:31don't recognise that because risk to many people is a purely
- 2:34negative term. So risk management or
- 2:37opportunity management is the management of the good things
- 2:39that might happen and threat management both as subsets of
- 2:43risk management is the management of the negative
- 2:46things that might happen. Why was it redefined in the 90s?
- 2:50You know, I've tried to look at this.
- 2:52I actually stopped this and research and I couldn't find an
- 2:55answer except a lot of it led down.
- 2:59You might have heard of it technique called SWAT,
- 3:01strengths, weaknesses, opportunities, and threats.
- 3:03So that's where my research found the terms came from.
- 3:08Opportunity and threat out of there.
- 3:11But there's also recognition that sometimes, if you like,
- 3:16things might take longer to to happen and they might be
- 3:19shorter. Things might cost more, they
- 3:22might cost less. And if we only only ever focus
- 3:27on the bad things that might happen.
- 3:29Then we don't get the chance to improve anything.
- 3:32And if you only really managing the bad things that happen, what
- 3:36happened on the project, then your project will at best be on
- 3:39time. But inevitably, because you're
- 3:41not, you'd have to be the luckiest person in the world.
- 3:44But none of the bad things that might happen to happen.
- 3:46Your project's going to be late, but if you manage the good
- 3:50things that might happen, then it's like a counterbalance.
- 3:53It will pull the project back or make it better in some way.
- 3:57So that's where the ideal came from.
- 3:59Let's look at the good things as well.
- 4:03I mean we're talking about this right now that the, the language
- 4:05around opportunity and threat and risk and risk management
- 4:08because of the work you've been involved with recently which
- 4:12will be published by PM in the autumn, I think.
- 4:15Do you, do you want to give us a bit of background on that or a
- 4:18little kind of overview about the survey and the research and
- 4:21and what that threw up? So I've been working in and
- 4:27around risk management for a very long time, probably 40
- 4:31years. What what I see and what I've
- 4:34observed in my many years as a practitioner is that even though
- 4:39we talk about risk being threat and opportunity.
- 4:44Having the positive, negative side, most organisations I come
- 4:48across don't do it. Some don't even attempt to do
- 4:53it, and some claim to do it but don't really do it.
- 4:58But I still think there is value at looking at good things that
- 5:01might happen and there are other ways of doing it.
- 5:04So within the the research team. So half of it really was the APM
- 5:09ristic with Sarah and myself, and then we had some friends of
- 5:13mine, colleagues from TU Delft, Netherlands Alexander.
- 5:17And Marian and we worked out some hypotheses around that to
- 5:23test whether organisations really did take risk to be
- 5:28threatened opportunity and if they did, did they perform it.
- 5:33As part of that study, and I won't go into any of the details
- 5:37of the findings, what we found was.
- 5:39Certainly the majority and I mean that as more than 51% and
- 5:43it's probably more than that do attempt to do.
- 5:47Threaten opportunity management, but they don't call it
- 5:50threatened opportunity management.
- 5:51They call it risk and opportunity management, which is
- 5:54which is appears to be the most understood terminology.
- 5:59And also when it comes to opportunity management, I sort
- 6:03of added into an earlier definition.
- 6:05That a risk is something that might happen by chance.
- 6:10That means that if you don't even influence in any way, it
- 6:13could happen. It's like saying, you know, if
- 6:16you it might rain in the next 10 days.
- 6:19It's a chance it will. Actually, we can't prevent it
- 6:22from raining, but we could put an umbrella up to stop it having
- 6:25an effect on this. But we can't stop it raining.
- 6:27It can happen by chance. So when it comes to thinking
- 6:31about threats, we do tend to think of the things that happen,
- 6:33could happen purely by chance, but one of the problems with
- 6:36opportunity management. Is that a lot of the things that
- 6:41I see described as opportunities are not things that will happen
- 6:46purely by chance. They are choices, we call them.
- 6:50So try not to think of anything too technical here, but there
- 6:56might be something. We might be able to use a
- 6:59different material which would save us money.
- 7:02That material isn't just going to drop out of the sky and come
- 7:05onto your building site and integrate itself into what
- 7:07you're doing. You're going to have to choose
- 7:09that to happen. It'll never happen by chance.
- 7:13So if we actually take those choices out of an opportunity
- 7:18management focus, very little people do it properly at all in
- 7:21fact. There's another discipline you
- 7:24might have heard of called Value Management.
- 7:27Value management is very, very good at looking at good things
- 7:31that might happen. So anyway, we had all these
- 7:34ideas and the survey was sent out.
- 7:37But, but the results of the survey clearly show.
- 7:41To me anyway, that we should stop calling the process risk
- 7:46management as threats and opportunities.
- 7:48We should call it risk and opportunity.
- 7:50And we should potentially look at other ways of managing
- 7:54opportunities. By using other techniques.
- 7:57And that's where the world of value management and value
- 8:00engineering could help. Because what's also apparent
- 8:05from my own working practise and it also came out in the survey.
- 8:09If I asked 10 people in a room tell me what tell me the risks
- 8:13on the project, they will all make automatically think of bad
- 8:17things. And if I said OK, now think of
- 8:19good things that might happen, They'll find it very difficult.
- 8:23Because your mindset is in the negative way if I set to.
- 8:27But if I started afresh and literally came in and gave you
- 8:32all a yellow baseball cap, you ever heard of Edward de Bono 6
- 8:37Thinking hats? Think happy.
- 8:38Think sunshine. Now, before you say anything
- 8:40else, think of good things that might happen.
- 8:43You'll do it. And what I'm suggesting there is
- 8:45that processes need separated. Now that's a bit of a personal
- 8:49opinion, but that also comes out in the case study.
- 8:53If we change the terminology of the way we talk about risk, how
- 8:58would this impact on the delivery of the project that
- 9:02would be more successful? The terminology is is already
- 9:06changed so I won't name any names, but no I'm.
- 9:09Most of the Copic corporate members of APM actually used the
- 9:14term risk and opportunity. But what I would also suggest is
- 9:18absolutely an advocate for looking at the good things that
- 9:23might happen, or even the choices that you could do to
- 9:26make things better and not ignoring them.
- 9:29But my practitioner view now is if you try and throw that in
- 9:34with the bad things that might happen, you probably do a bad
- 9:38job of both. What should you be doing instead
- 9:41as a project professional? Well, I think and others like me
- 9:47agree is you have a risk management effort, risk
- 9:50management process which focuses on the bad things that might
- 9:54happen and you have a an opportunity management process
- 9:58that could be facilitated, administered, governed by the
- 10:03same group, but you separate the two.
- 10:08And really go about the opportunity management in a more
- 10:12using techniques and facilitation skills that are
- 10:16more akin to what I've mentioned before.
- 10:19What value management would look at?
- 10:22Are you suggesting that on a project as much attention should
- 10:26be given to the opportunities, and I'm thinking of those as the
- 10:29positive side of things, as to the risks and the and the
- 10:33threats and and if and if so, would that then shift the
- 10:39mindset or the energy on a project towards some more
- 10:43positive? I don't want to just think of
- 10:47projects as purely as costing money and and taking time, but
- 10:52all projects do have a budget. When things go wrong, they can
- 10:56go very very wrong. So something can cost twice as
- 11:00much as you anticipated or take twice as long.
- 11:04It's very unlikely for something to cost.
- 11:08Half as much as you thought it was going to be.
- 11:11I'll take half as long. So what that's what I mean by
- 11:14that is the it's a skew the term which is it's a skewed
- 11:17distribution. Things can get a lot worse than
- 11:21they can get. Then On the contrary, they can
- 11:24get a lot better. So that's one of the dilemmas.
- 11:27Do we spend time trying to find the little things that might
- 11:31happen when there's a lot more bigger things out there that, if
- 11:34they happen, could destroy the project?
- 11:37So there is that dilemma. So should you put as much effort
- 11:40in? And the answer therefore is
- 11:42probably not. But don't ignore it, because
- 11:44there might be using a a metaphor, some low hanging fruit
- 11:48somewhere that you can pick and get, but but putting the same
- 11:52amount of effort in? Probably not, but also what
- 11:55tends to happen. In projects and you will be
- 11:59aware that projects go through a life cycle.
- 12:02And a certain point in that life cycle, the project gets signed
- 12:06off. And it doesn't matter if this is
- 12:08a an agile or iterative lifecycle, There's a point where
- 12:11we can decide to spend some money because we've got
- 12:13something we're going to do. What tends to happen is.
- 12:18Psychologically, and that you might have heard the term
- 12:22optimism bias, all the good things that might happen.
- 12:26Tend to be put into our baseline.
- 12:29It's like saying it's going to be a sunny day every day, we
- 12:32assume, but it's not. On all the good things, we might
- 12:36be able to get that little bit cheaper.
- 12:37So we put that in a base case and that happens a lot,
- 12:41especially when people want to get their project to go ahead
- 12:44for some reason. They've got to meet a hurdle of
- 12:47it's got to cost less than this. So it's got to be done in a
- 12:49shorter time than that or something.
- 12:52Which means if you've built in all those opportunities, and
- 12:56this is borne out in the research that people do
- 12:59opportunity management right at the beginning, then things can
- 13:02only get worse. You know if if you put a plan
- 13:06together and it doesn't matter what it is the schedule together
- 13:09and it's and it's based on 8 hours productivity everyday
- 13:14doesn't matter what you're doing.
- 13:15It being a sunny day everyday all the equipment arriving on
- 13:20time all IT code working first time and people do that then it
- 13:26can. It can't get better than and
- 13:29that's what the dynamics would opportunity.
- 13:31We do it and we we grasp it too early.
- 13:36So what's your advice about mitigating that kind of optimism
- 13:40bias or our natural proclivity towards opportunities?
- 13:46Understanding that you're doing it is one thing, but what also
- 13:50then can overcome that If you do end up doing, and again you
- 13:55might have heard the term quantitative risk analysis where
- 13:57you do simulation models, then that exposes that.
- 14:01That will expose the fact that everything's very optimistic.
- 14:05But be aware you're doing it and maybe thinking.
- 14:09Just think it might not be a sunny day every day.
- 14:12A lot of that also comes down to and another word that gets used
- 14:15in mismanagement even though it's a commonly used term is his
- 14:19assumptions. You know what are we assuming
- 14:22and you know you could say we it might be sunny everyday or and
- 14:26that's fine, but are you assuming it's going to be sunny
- 14:29everyday And if you are then it can only get worse.
- 14:32So sometimes think of what? What are you assuming and
- 14:36whether you're over assuming things because it's the
- 14:38assumptions of the good things. In that sense, what do you think
- 14:43needs to change about the way the project profession views
- 14:47risk management in the context, you know, what we've been
- 14:50discussing? Well, I think it's always been,
- 14:54it's been high on the agenda of the project management
- 14:58profession since since I joined it and it's always been there
- 15:03and if you look at any of the. Sort of surveys that come up
- 15:08with you know why do projects fail?
- 15:099 out of 10 that ten of those will see ineffective or
- 15:13inadequate risk management. So it's important, but it's
- 15:17obvious that people still don't do it as well as it could be
- 15:21done. Now that's a generalisation and
- 15:26so and and I think it would be fair to say most and if what the
- 15:2951% or even 80% of organisations don't do it as well as it could
- 15:34be done but some do it very well.
- 15:35I won't name any names. Some who have have, I think have
- 15:38cracked it but that but the other organisations need need to
- 15:42just focus on it and take the hit.
- 15:46Because one of the problems with doing risk management is it
- 15:49doesn't always give you the answer you want.
- 15:52What I mean by that is someone's got this great idea to do A to
- 15:57for a project that's going to deliver a change that's really
- 16:01needed, and then says, well, hang on a minute, let's do a
- 16:04risk assessment and you do look at all the risks.
- 16:07When you come up with all these things and it's now, it's gloom
- 16:11and doom. You know, we, you know, we, we
- 16:13were happy till you said that. And if you then do a
- 16:16quantitative risk analysis, it might come up with, but you've
- 16:20only got a 10% chance of achieving what you've just told
- 16:23the world you're going to achieve.
- 16:24So it's often the bringer of bad news.
- 16:27And so people, some people don't like it for that very reason.
- 16:32It also takes time. It costs money and it's it
- 16:37requires a. The level of understanding that
- 16:40some people. Don't really appreciate it isn't
- 16:45as natural as some people think it is and it's needs constantly
- 16:50to be looked at. But at that point, I always
- 16:53think it's it's, you know, the health, health and safety in
- 16:57many arenas of project management is absolutely
- 16:59paramount. I wouldn't say that's been using
- 17:03a phrase I used earlier cracked completely, but that's really
- 17:07taken seriously. And that's an element of risk
- 17:10management, it's what's what is the chance that someone might
- 17:13get hurt or worse and and the consequences of that
- 17:17organisations take that really seriously.
- 17:20But when it comes to. Money and time and benefits.
- 17:27It doesn't always get taken seriously because it's not your
- 17:31money. I bet you don't miss many
- 17:35flights for your holiday or missed trains, or go over budget
- 17:39when too far over budget. When it comes to any home
- 17:42project, most people don't. Some do.
- 17:44That's always outliers. But if you take personal
- 17:47projects and how successful they are compared with wider
- 17:51projects, it appears that we do a better job of managing.
- 17:56Our own than it does for managing others and in fact one
- 17:59organisation I work with says you should spend the money as if
- 18:03it's your own. Well, data analytics or AI bear
- 18:09fruit for risk management. Is it something you regard as
- 18:13helpful in doing risk management?
- 18:17Has to people find it more difficult to refute data.
- 18:22It's just a lot of a I is about big data.
- 18:25If you use the right technology and you've promised someone
- 18:30you're going to deliver your project for a certain budget in
- 18:34a certain amount of time, and the AI says that's impossible
- 18:40and unless and will it be based on is it's impossible because
- 18:44we've found 4000 other projects that have similar.
- 18:47Countries and none of those achieved in that type.
- 18:50And there are software tools, I won't mention the names that
- 18:52actually do that at the moment, who allow you to look at your
- 18:57schedule and compare it with thousands of others and they'll
- 19:00tell you how risky it is. And that's really, it's not AI
- 19:05in that because it doesn't learn, but it's it's a I in the
- 19:09terms it's it's sucking on lots of data.
- 19:12So I think it will improve things.
- 19:15What are the key findings from 4 decades of experience when it
- 19:20comes to risk management that that you'd like listeners to
- 19:24take away, particularly for those people who are kind of
- 19:28fresher to the profession? Take it seriously and and any
- 19:34plan that you put together and plan with the big P so that I'm
- 19:39in that sense, I'm talking about a schedule, a cost estimate, a
- 19:44contracting plan, communication. Whatever you put together should
- 19:49take into account things that might happen that if they did
- 19:54could impact what you're trying to achieve.
- 19:56So take it, take it seriously and always consider what might
- 20:01happen. To to to affect this
- 20:04immediately. That will make people think
- 20:06negatively because that's the way we talk talk and earlier on
- 20:10you actually said something about how do we mitigate this
- 20:13mitigate is a negative word. It's a word that pervades risk
- 20:15management in APM's term. We in the APM body of knowledge,
- 20:19we use the term response because you can't mitigate an upside
- 20:22risk, but because that's a oxymoron in that sense, you know
- 20:27you don't want to reduce an upside risk.
- 20:29Going back to go back to what you actually said, I would, you
- 20:32know, take it seriously but also make it happen to the point
- 20:37where senior management wanted, many years ago when I was
- 20:42working with David Hilson and Ruth Murray Webster for a
- 20:45company we all worked at together, we worked with some
- 20:49big companies that actually no longer exist in name, but they
- 20:53do as part of other big organisations and we work with
- 20:55them. And to make risk management work
- 20:58in those organisations, it needed to be pulled.
- 21:01And what I mean by that is senior management needed to want
- 21:04it. They needed to want it by always
- 21:07asking questions. We'd want to bid for some work.
- 21:11And what are the risks? Ohh, we're a client, we want to
- 21:14go ahead with this. But what are the risks they they
- 21:17they ask, rather than it being bottom up.
- 21:19So mismanagement needs to come be demanded from the top and
- 21:23supported from the bottom. It needs the term we often use
- 21:27as a champion in the organisation.
- 21:30Have you got any advice to senior project professionals who
- 21:34would like to influence senior leadership within an
- 21:39organisation so that they appreciate how serious risk
- 21:43management should be taken? So you're trying to create a
- 21:46champion within the broader organisation who is able to
- 21:51place more emphasis and legitimacy on the importance of
- 21:54risk management within that organisation.
- 21:57In some organisations they do have a CR Chief Risk Officer.
- 22:02That's not as uncommon. Or it sits somewhere under
- 22:06finance, which I don't always think that's a good place, but
- 22:09some organisations already recognise this.
- 22:12But parts of allowing risk management to influence the
- 22:15C-Suite is they have to also have to take project management
- 22:17seriously and and recognise what that is delivering and the
- 22:23change it brings about. But I think it's it.
- 22:27It does need a very special person to do that.
- 22:29Someone who who is charismatic you.
- 22:33You can't just get and want to say not everybody can do it.
- 22:37But it does take a certain person because you have to be
- 22:39able to story and you have to make people understand the
- 22:42consequences of failure and also understand how much and you
- 22:49might have heard the term, how much risk they can tolerate.
- 22:52What is their attitude towards risk.
- 22:55So it built, it builds up into the the cost of failure if, if,
- 23:00but it has to have a an outcome that people really want to
- 23:04achieve and so the influence will come from.
- 23:09It has to be understood the C-Suite level.
- 23:12I don't think you can come necessary to them and make it,
- 23:16you know, open the door and fly in and say you've got to
- 23:19consider the risks. They've also got to realise how
- 23:22important it is to deliver whatever they're delivering.
- 23:25And I think the big organisations do that now and
- 23:29and the government even mandates it, since since Nick Smallwood
- 23:35who I knew from Shell has got into the into IPA, he's changed
- 23:40things dramatically and made it more palatable in that sense.
- 23:44So I don't think there is, as I said your silver bullet on how
- 23:47you can make it happen. But you have to emphasise the
- 23:51and find out what what happens if we fail in this.
- 23:55And one way of preventing failure is making sure that you
- 24:00understand what's realistic at the beginning.
- 24:02That takes into account in the risk and then when you enter
- 24:07into the delivery of the project making sure that you stop those
- 24:11risks delaying or having a detrimental effect.
- 24:16One thing about risk management, it's about making good decisions
- 24:20in projects so. So when you tell someone this
- 24:24project is going to take so long and cost so much and deliver
- 24:27these benefits that should be risk should be factored into
- 24:32that to try and take away some of that optimism bias.
- 24:36But then once you've told everybody it's going to be
- 24:39delivered in this time frame for this budget at this performance
- 24:44and deliver these benefits on whatever, then you use risk
- 24:46management to protect it. And that's what risk management
- 24:49does and it's it, if you think about it the two setting the
- 24:54baseline if you like and then ensuring you meet the baseline
- 25:00and then if you can make people the C-Suite understand that,
- 25:03then I think it will work. Typically, when are these risks
- 25:09assessed or considered in a business case?
- 25:12Are they right from the very start?
- 25:16Does that happen in practise? The organisations I have worked
- 25:20for and work with, when they put a business case together, they
- 25:25will always include in it the major risks and they'd all be
- 25:30negative. So in the business case and then
- 25:32as you go through an Apms like our lifecycle through the
- 25:35definition phase and develop your project management plan,
- 25:38then there would be an intense understanding of the risks and
- 25:43risk register would be put in place and then the plans are
- 25:46produced at the end of the definition place should all take
- 25:50into account the risks that have been identified and where
- 25:54relevant responded to. I worked many years ago for BP
- 25:58and they actually said the prime role of a project manager was as
- 26:03a risk management risk manager because if everything's going to
- 26:08plan, you have nothing to do. It's only the things that might
- 26:12happen that will cause you to deviate from the plan, or any
- 26:15things that go wrong that you need to worry about.
- 26:19So you work the plan. So the prime role of a project
- 26:22manager is to manage the things that might happen which will
- 26:25cause that deviation. Now that's a very high level
- 26:29broad statement and a lot of people might not agree with
- 26:31that. But when you think about it, but
- 26:34you can sit behind your desk with your feet up, everything go
- 26:37to plan. Someone says we've just found
- 26:39out this might happen or we're going to do something about that
- 26:41though. Or using APM language, something
- 26:44has gone badly wrong and we have an issue which we can't ignore
- 26:47because we've looked outside of our tolerances or something's
- 26:50gone. Is there anything you'd like to
- 26:53add or any other points of advice you'd like to pass on
- 26:57when it comes to risk management?
- 26:59Well, I would like to everybody please have a look at the the
- 27:02survey report and it it comes out, it may change the language
- 27:07and I know that there are people in a PM willing to think about
- 27:10that and there's a new body of knowledge coming out in the not
- 27:13too distant future that may bear that in mind, but there's a lot
- 27:17out there about about risk management.
- 27:19It's not difficult to practise it do it is integral part of
- 27:25project management. Have a go and make sure your
- 27:29plans are risk based but. It's been fantastic talking to
- 27:34you. Thank you so much.
- 27:35Just mentioned to listeners that the report will be published by
- 27:40a PM in the autumn. So very much looking forward to
- 27:43for everyone to get hold of a copy.
- 27:45So thanks so much again, Peter. Thank you.
- 27:54Thanks again to Peter for joining us and to you for
- 27:56listening to the APM Podcast. Don't forget to look out for
- 28:00more episodes or to rate and review us wherever you get your
- 28:02podcasts. We'd welcome you to get in touch
- 28:05with your comments, feedback and suggestions by emailing us at
- 28:08apmpodcast@thinkpublishing.co.uk. This podcast has been brought to
- 28:15you by APM, The Chartered Body for the project profession.
- 28:18For more information on APM, visit apm.org.uk.