Latest / Kendall County News - Shaw Local / Oswego School District 308 Board approves $117,800 in emergency repairs to Boulder Hill School
Transcript
- 0:05Speaker 1: Oswego School District three hundred and eight board approves one
- 0:08Speaker 1: hundred seventeen thousand, eight hundred dollars in emergency repairs to
- 0:13Speaker 1: Boulder Hill School. Written by Eric Shelkoff, This article is
- 0:19Speaker 1: being read by an automated voice brought to you by Everlett.
- 0:24Speaker 1: Oswego School District three hundred and eight is moving ahead
- 0:27Speaker 1: with emergency repairs to a cooling system at Boulder Hill
- 0:30Speaker 1: Elementary School that is not working. Two chiller compressors at
- 0:35Speaker 1: the school have given out and require immediate replacement, District
- 0:39Speaker 1: three hundred and eight Operations Director Andre Scoonci told school
- 0:43Speaker 1: board members at a special meeting on July twenty first,
- 0:47Speaker 1: board members unanimously voted to purchase two rebuilt replacement compressors
- 0:52Speaker 1: through Bullock Logan and Associates at a cost of one
- 0:55Speaker 1: hundred five thousand, six hundred sixty eight dollars. Also voted
- 1:00Speaker 1: unanimously to approve a twelve thousand, one hundred and sixty
- 1:04Speaker 1: nine dollars and seventy three's contract with Johnson Controls to
- 1:08Speaker 1: install the two rebuilt compressors. The project carries a one
- 1:12Speaker 1: hundred seventeen thousand, eight hundred and thirty seven dollars and
- 1:16Speaker 1: seventy three cents price tag. It will be funded through
- 1:20Speaker 1: the district's Operations and Maintenance fund. We need to get
- 1:24Speaker 1: this fixed or we will not be able to have
- 1:26Speaker 1: school on the first day of school about a month
- 1:28Speaker 1: from now, District three hundred and eight chief financial Officer
- 1:32Speaker 1: and chief school business Official Rafael Obovmi told school board members.
- 1:38Speaker 1: Staff members returned to the school on August third, and
- 1:41Speaker 1: school is back in session for students on August twentieth.
- 1:45Speaker 1: The work is set to be done by the end
- 1:46Speaker 1: of July. The compressors were originally installed in twenty thirteen
- 1:51Speaker 1: and have reached the end of their service life. Scuonci
- 1:54Speaker 1: said recent monitoring of indoor temperature has demonstrated the impact
- 1:58Speaker 1: of the failing equipment. He told school board members the
- 2:02Speaker 1: district anticipates that during peak summer conditions, indoor temperatures could
- 2:06Speaker 1: exceed ninety degrees. These conditions would create an unacceptable learning
- 2:10Speaker 1: environment and post significant health, safety and comfort concerns for
- 2:15Speaker 1: both students and staff. Officials said the equipment had been
- 2:20Speaker 1: identified through a recent district wide facility audit as nearing
- 2:24Speaker 1: the end of its useful life, with fewer than three
- 2:26Speaker 1: years of service remaining. This situation underscores the value of
- 2:30Speaker 1: the district's facility audit, part of the Long Range Facility Plan,
- 2:34Speaker 1: which was completed to quantify the scope of aging mechanical
- 2:37Speaker 1: systems across all twenty two district buildings. Officials said that
- 2:43Speaker 1: assessment gives the district a clear strict wide picture of
- 2:47Speaker 1: which systems are approaching end of life, allowing leadership to
- 2:50Speaker 1: plan ahead where possible and respond quickly when necessary, as
- 2:54Speaker 1: is the case at Boulder Hill, The district has said.
- 2:58Speaker 1: The school district serves portions of Kendall, Will and Kane Counties,