Latest / Catalyst with Shayle Kann

Getting more energy on the wires
Want to build a power plant in the U.S.? Here are three things to know.
First, connecting a wind farm, utility-scale battery, or other big source of power to the grid means getting in line. A typical project’s wait time has increased from around two years in 2005 to four years in 2020, according to the Lawrence Berkeley National Laboratory.
Second, the interconnection queue is a crowded place. In 2020 there were 1.44 terawatts of projects in the queue. That’s more than the U.S.’s current fleet of generation.
Third, dropouts are the norm. Only 25% of projects make it to completion. Projects…
The skinny
The skinny isn't ready yet — notes appear once the transcript is processed.