Latest / Contractor Business Builder Podcast / Estimating Mastery: Pricing Projects Without Losing the Job or Your Shirt
Transcript
- 0:00You never finished the job and wondered where all the money go.
- 0:03This video is for you. I'm going to show you how to
- 0:05price project without undercutting yourself or scaring
- 0:08off good clients. Alright, so this video is part
- 0:11of a series of videos on all things estimating, estimating
- 0:15mastery. Make sure you check out the
- 0:17other videos after this one. The first thing I mentioned
- 0:19about pricing is markup versus margin.
- 0:22We're gonna get into all the nitty gritty details of, of
- 0:24specific pricing, of oversights, things to include labour
- 0:28materials, all that kind of stuff.
- 0:29But I need to get started with a really important stuff first,
- 0:32which is markup versus margin and knowing the difference and
- 0:35why it even matters. You may have heard it and
- 0:37they're like, isn't it like kind of the same thing?
- 0:39What does it really matter? Well, a 20% margin is equal to a
- 0:4325% markup. The difference of this is when
- 0:46you calculate for overhead and your expenses.
- 0:49So if you're running an overhead type calculation, you're looking
- 0:52at your books and you may look for the past year you made like
- 0:56$1,000,000 and let's say you spent $100,000 on overhead.
- 1:00That is a 10% margin of overhead.
- 1:03Now if you are marking up your estimates by 20% and you figure
- 1:08you've got a 10% margin, you're actually selling yourself short
- 1:12because of 20% markup is not a 20% margin.
- 1:16And it's actually probably about like a, I don't know exactly
- 1:191617%. So really make sure that you're,
- 1:22you're understanding the margin and markup and the difference
- 1:25between it, because typically speaking, overhead is going to
- 1:28be somewhere around 10:50. And I've even seen it up, you
- 1:31know, higher 2025 percent in some contracting companies.
- 1:34So your markup is probably gonna need to be around 25 to 30% to
- 1:39operate a larger business. If you're hiring a management
- 1:42team with, you know, project managers and, and different
- 1:45admin people and things like that in the mix.
- 1:47If you're still kind of the lone wolf or, you know, the head
- 1:50honcho leader in your business and you're running all your
- 1:53projects and everything, you can't afford to have a little
- 1:56bit lower markups. But the problem is that when you
- 2:00start to grow, if you want to hire and bring in these other
- 2:03people, your pricing is not in a position to facilitate that type
- 2:08of growth. And you're not going to be able
- 2:09to sell the same type of projects with the same, you
- 2:13know, level of abilities that you have as you have to raise
- 2:16your prices in the future. So better to get that out of the
- 2:18way now, have a healthy markup and make sure that you're
- 2:22covering your overhead as well as your personal salary profits,
- 2:26as well as some contingency. No project goes as planned.
- 2:29No estimate is bulletproof. You know, there's always going
- 2:32to be things that pop up and you're probably always going to
- 2:34have something, it ends up decreasing your margins
- 2:37throughout. So make sure you're you're
- 2:38pricing accordingly and you know the difference.
- 2:41We mark up margin and that's why it matters.
- 2:43Alright #2 moving on to #2 here is common oversights.
- 2:47So again, I wanna get some stuff out of the way right off the
- 2:49back here. And if you want a free templates
- 2:52for estimating the full template that we have for a new home
- 2:55build as well As for home walkthroughs and an SOP, we got
- 3:00a three template stack. It's all free.
- 3:02Check out the links in the description below.
- 3:03Go grab that stuff for yourself. Right now, the common oversight
- 3:06is project management. I know a lot of guys, especially
- 3:10starting out in doing GC type work, they feel like the project
- 3:13management is something that you include in the markup.
- 3:17You know, I'm going to mark it up 25% of 30% and that's kind of
- 3:20my salary as, as the project manager or have project managers
- 3:23and that's how I pay them. The problem with this is you
- 3:26can't really attribute the hourly rate of your project
- 3:29manager to the project that they're managing.
- 3:32And how many, how many projects do we need to imagine manage to
- 3:35afford their, their hourly rate or their salary or whatever it
- 3:38may be? So that's why you need to
- 3:39include a separate line item for project management that
- 3:42typically I like to do this by how many hours per day are gonna
- 3:45be spending on the project. So if you're building a new
- 3:47home, maybe they're there, you know, 2 hours a day.
- 3:49And it's not that they're on site 2 hours a day, but they're
- 3:51talking with trades, they're talking with clients, they're
- 3:54ordering materials, they're maybe meeting inspectors, you
- 3:57know, whatever it may be that the amount of time and then
- 4:00times it by was just going to be a 7-8 month, you know, home
- 4:03build. How much time are they going to
- 4:05be there times that by their hourly rate plus, of course, the
- 4:08a healthy markup, which I'm gonna get to like how to price
- 4:11labour. But typically for project
- 4:12management, you're probably gonna be in the $100.00 an hour
- 4:15range. Figure out what makes sense for
- 4:16you. But that way, even if you are
- 4:18the one project managing, you know that you can hire project
- 4:21manager and their salaries covered in the estimate making
- 4:23sense here. Can you see how that's very,
- 4:25very important and set yourself up for growth and scaling.
- 4:29Now, the other thing that's common oversight is
- 4:30miscellaneous. And you may be a little afraid
- 4:32to like put miscellaneous in an estimate because the clients
- 4:35like, why am I paying for miscellaneous?
- 4:37What's this, right? But essentially, you could tell
- 4:39them every project that we've ever done in entirety of
- 4:43construction always has something that was not accounted
- 4:46for, something that comes up. There's a lot of variables, a
- 4:48lot of things that can go wrong. And we've found that there's
- 4:52always something. So instead of trying to, you
- 4:54know, come back later, we had a little bit of miscellaneous, you
- 4:56know, labour, little bit of miscellaneous materials because
- 4:59there's always something that we have about oversight.
- 5:01Or if there's small things that pop up in a project, we can take
- 5:04care of it without change. Ordering you to death for a
- 5:06couple 100 bucks here, a couple 100 bucks there, right?
- 5:08So add a little bit of miscellaneous into your budget.
- 5:11And then the final thing that's common on oversights is a risk
- 5:14assessment. Do a little bit of of forward
- 5:16thinking. And is this project far away?
- 5:19Is, you know, if it's a remodel, I mean, there's risks all over
- 5:22the place, right? Is this 100 year old home that
- 5:25who knows, you know, what's behind the walls or is there
- 5:27asbestos or aluminum wiring or or whatever, right?
- 5:30So obviously you're gonna check for these things before you
- 5:32start construction, but do a risk assessment.
- 5:34What are the risks involved? Do I need the price differently
- 5:37based off of these risks? Risk could be, I'm not too sure
- 5:40about this client. Maybe they're like a lawyer or
- 5:42you know, some, some big way or something like that.
- 5:44And they've talked about the other contractor that they
- 5:47fired, you know, last year or whatever, right?
- 5:49So what are the risks price accordingly?
- 5:51Alright, still with mayor #3 these are things that you do not
- 5:55include. So when you're presenting budget
- 5:58estimate proposal to a client, there's things that you don't
- 6:01want to have in your estimate. Now feel free to add these, but
- 6:04generally speaking, especially early on before you know, kind
- 6:08of where this is going, the first real like rough estimate,
- 6:11itemized estimate that you provide to a client, present
- 6:14them with this is, you know, doable.
- 6:16This is like base pricing. And then from here, depending on
- 6:19what they select or the options and where things go, the price
- 6:23will, you know, kind of go up from there.
- 6:24And things that you don't want to include like permits, unless
- 6:27you know specifically every, you know, project like this, the
- 6:30permit is $5000. Put that in there.
- 6:32If it's a variable thing that has to do with the county, the
- 6:35city, your district, whatever it may be, where it's like service
- 6:38upgrades for, you know, water connections or electrical
- 6:42connections or stuff like that, that, that is very variable.
- 6:45And essentially the, you know, the government districts, city,
- 6:48whatever, whoever is gonna send, send a bill for that and leave
- 6:50that out and just let the client know that these things are
- 6:53variable. I don't really know how much
- 6:54they're gonna cost because you know, we get charged from XYZ at
- 6:58the government by their people that come out.
- 7:00And this is an unknown cost. That's why I have not included
- 7:03it. But you can expect that having,
- 7:05you know, these upgrades, which you may or may not have to do,
- 7:09it could be anywhere from 20 to 40,000, which right.
- 7:11So you let them know you're open and in front of buddy, you're
- 7:14not trying to like hide anything, but you're just trying
- 7:16to remove variables. Alright.
- 7:19Other things that you want to exclude don't include.
- 7:23This is extras. So if they're like, yeah, you
- 7:27know what, like we want to remodel our whole home and we're
- 7:30also thinking of maybe like extending our garage or
- 7:34finishing our basement as well, but we might just stick to the
- 7:36main floor. If you want to give them
- 7:38different versions, that's fine, but typically speaking,
- 7:41definitely do a separate. Don't just give them the one big
- 7:44shot, everything included and then tell them you can remove
- 7:46stuff later. Have either options for it or
- 7:48have like a base one. This is for your main floor.
- 7:51If you choose to do the basement as well, that's gonna be an
- 7:54extra 60 grant or whatever it may be, right.
- 7:56Again, you wanna like chunk the numbers for options so that you
- 8:00can keep the the main scope of work as low as possible.
- 8:03And if they want extras or considering other things, have
- 8:05it as like a secondary option as well as like Gray area.
- 8:08So if, if there's again, like some sort of Gray area where
- 8:12they're not sure or you're not sure, like landscaping is, is
- 8:15one of these things. If you get a set of plans for a
- 8:16new home build, it's often that, you know, they've got the floor
- 8:19plans and elevations and all that kind of stuff, but they
- 8:22don't really have like a landscape plan then either just
- 8:25leave it out and say to be included upon, you know, final
- 8:29plans or, or selections or whatever.
- 8:31Alright, so we've talked about a lot of things that are sort of
- 8:34contingent and that's the, those are really important things a
- 8:37lot of people don't think about, like when you think about
- 8:39pricing, but those influence the entire kind of sales process and
- 8:42budget for the client a lot more than some of the other things
- 8:45which I'm going to get into now. Even though these are more
- 8:47important because they will eventually either, you know, let
- 8:51you know if you've actually making money or losing money.
- 8:53Grab these templates and the description.
- 8:55They will help you make sure that your pricing is on point
- 8:57and you're not forgetting anything in your estimate.
- 8:59Alright, so #4 is labour pricing.
- 9:02Labour pricing is the easiest way to lose money on a
- 9:05construction project is what I've found.
- 9:07It's often the thing that kind of goes out the window and is
- 9:10very hard to know exactly for a lot of reasons.
- 9:14You know, guys are kind of all over the place or can be, you
- 9:17know, weather you got site conditions, you got lots of
- 9:20different things that could happen with labour.
- 9:22Often, especially if you're an entrepreneur, your vision of the
- 9:25future is generally optimistic and maybe a little bit rosy and
- 9:28you're not really taking account of all the things that can go
- 9:30wrong, which is why you're risk assessment.
- 9:32But what you want to be thinking about labour pricing is you're
- 9:34going to have a wage. So if you're paying a guy, let's
- 9:36say, you know, $30.00 an hour, you ought to be adding the
- 9:39things like any taxes, workers comp, even things like having to
- 9:44buy them clothing or training, all that big downtime kind of
- 9:48stuff, admin costs that go along with having that employee,
- 9:51anything that, that employee costs you money, you need to be
- 9:54accounted for on top of their wage.
- 9:56And then on top of that, I would say you probably want at least a
- 9:5950% markup on the labour. Because that 50% markup is sort
- 10:03of contingency where if you've estimated 30 hours for this,
- 10:06this item in the, in the budget, it's very easy.
- 10:09That could go to 40. And of course, you want to
- 10:11always add a little bit extra hours more than you think, but
- 10:13it's just, it gives you that ability to make sure that if you
- 10:17give them raises in the future or something goes wrong in the
- 10:20project, you've got that, that padding built in there so that
- 10:23you've got that 50% markup. And then on top of that, you've
- 10:26got another, you know, whatever, maybe 2530% markup for the whole
- 10:30project. So how this looks is you like
- 10:32$30, typically it's going to be about double for the burden and
- 10:36the 50% markup for contingency. So that thirty goes to 60,
- 10:40potentially higher, but let's say 30 goes to 60.
- 10:42And then you're gonna on top of that sixty, you're gonna put an
- 10:45additional 2530% for your project, you know, overhead and
- 10:49margin and, and everything like that makes sense.
- 10:51And then the next thing with pricing for labour is what I
- 10:55like to do is do a mental walkthrough of what the person's
- 10:59actually gonna be doing. And if you've worked in the
- 11:01trades before, you're going to know this a lot better.
- 11:03If not, you may need to talk to, you know, somebody else on site
- 11:07or something like that and maybe get their input.
- 11:08But if it's like, you know, they've got a demo this wall
- 11:11and, and build this wall or they've got to build this house,
- 11:14like framing wise, it's sort of like with my history, how long
- 11:18has it taken? How can things go wrong?
- 11:20And what are they gonna need every day, you know, or, or that
- 11:23day, if let's say you've got 20 hours in there, Well, they gonna
- 11:25have to show up on site every day.
- 11:26They're gonna have to clean up. They're gonna have to do this.
- 11:28So just do a little mental walkthrough of the work.
- 11:30And often that'll help you sort of chunk things into like, OK,
- 11:33that will take two hours and that will be 5.
- 11:35And then, you know, they got another 8 or there's like this
- 11:37many days and they've got to take down set up, you know, so
- 11:40do a mental walkthrough and that really helps you get a lot
- 11:43clearer of a picture of how many hours or days of project is
- 11:46actually gonna take. Alright, so moving on to point
- 11:49#5 we are talking about material pricing.
- 11:54So how much of the material is gonna cost going into this
- 11:56project? You should be using some sort of
- 11:57software ideally, or at least have a database of spreadsheets,
- 12:01something like that. There's gonna be some pricing
- 12:04database and there's two different types of pricing
- 12:06databases. Typically there is going to be
- 12:08kind of your online resources. These are things like Rs means
- 12:11or Build 1 or there's a number of them out there where it's a
- 12:15essentially a live database that you can reference or pricing at
- 12:19anytime and it's going to have pricing for your area at that
- 12:22specific point in time. But you may also have things
- 12:25where you've got your own pricing database.
- 12:28Those things are gonna be pricing that you've just kind of
- 12:31figured out over time and then you put in your database.
- 12:33A good way to save time is if you're ever looking up pricing
- 12:37online or anywhere else and it's not in your online, you know,
- 12:41database that I mentioned where it's live, make sure you put
- 12:43that into your hard copy pricing database so you don't have to go
- 12:47and look it up every single time. 1 caveat is if you put a
- 12:50price in there last year and you're like one or two years
- 12:53later, you probably need to update that price.
- 12:55So that's the the problem with having like a hard database
- 12:58you're just putting numbers into.
- 13:00It's very helpful, but just remember that you do need to
- 13:02check it and update it from time to time to make sure that the
- 13:05pricing isn't old and there hasn't been, you know, inflation
- 13:07or changes in the cost of items. Next thing is make sure you're
- 13:10putting on a little bit of waste.
- 13:11So five 1015% even depending on the material and what it is,
- 13:15always have some if you need 1002 by fours, you probably want
- 13:19to order 1200, right, or 1500. That's a little much maybe.
- 13:22But anyways, if you need 1000 like thousand 100,150 something
- 13:28like that, right, 10 to 15% at least for things that are more
- 13:31critical, like tile or flooring where you can't just run to the
- 13:35store and get more, especially if it's special ordered, make
- 13:37sure you're ordering like or at least estimating like an extra
- 13:4020% of waste because you do not want to have to try to, you
- 13:44know, skimp on it. Order and then something you
- 13:47know doesn't come in or whatever you got to order more and, and
- 13:49now you're paying extra for delivery as well.
- 13:52So make sure you put your delivery costs in your
- 13:54materials. This typically I would have a
- 13:56separate line item of like deliveries and however many
- 14:00deliveries you think you can need for the project, because
- 14:02there's always something that you need, you know, shipped to
- 14:04the, to the site or you need some guy to go pick up, whether
- 14:07that's one of your guys or what have you.
- 14:09So make sure you're, you're including the delivery as well.
- 14:13And then assemblies are always an easy way to have built in
- 14:17kind of pricing and assemblies depending on your estimating
- 14:20software, but you'll have sort of several pricing for stuff.
- 14:23But let's say like a 2 by 6 wall exterior wall.
- 14:25Well, you're gonna have the studs, you're gonna maybe have
- 14:27some bolts or fasteners, your nails, your, your glue or sill
- 14:31plate. You know, you have to double top
- 14:33plates and OSB sheeting and tie typar, Tyvek house wrap,
- 14:36whatever you wanna call it. All of that could sort of be
- 14:38built into it in assembly. And you can have like a overall
- 14:41price for something like that without having to price all
- 14:44those things individually. And that's where assemblies come
- 14:46in really handy and get speed up your estimating a lot quicker
- 14:50and help you price things a lot quicker as well.
- 14:52And of course, you know, you gotta double check your numbers
- 14:54every now and then if you don't have that live pricing in in
- 14:57your model. So next thing we're moving on
- 14:59here is number six, and that is selection.
- 15:01So your client is gonna have selections or preferences that
- 15:04they want installed in their home or their their office
- 15:07space, you know, commercial property, whatever it may be.
- 15:09When you're starting out, if you're doing like a rough budget
- 15:12type of a budget where they haven't made selections yet,
- 15:14you're just kind of pricing out the project.
- 15:16Always do sort of mid to low allowances because again, you
- 15:20don't want to scare off your client by pricing these these
- 15:23high end fixtures or luxury kind of things.
- 15:26And then the the price be inflated and they balance
- 15:29because it's you know, well, well over what they expected or
- 15:32whatever. For the estimates, make sure
- 15:33that you have like solid allowances in there and it's
- 15:36clearly stated allowance. Also for allowances, make sure
- 15:40you have some sort of documentation in there if taxes
- 15:43are included or not. If you're going to pay taxes on
- 15:45top of materials, then, you know, is that part of the
- 15:48allowance or not part of allowance?
- 15:50And you want to make sure that that is understood as well as
- 15:52your elections, right? If they have a, a bathtub in
- 15:55there for, you know, $1200 or something like that, and you've
- 15:58got whatever taxes may be on top of that, you wanna make sure
- 16:02that it's clear to them that that allowance includes taxes or
- 16:05doesn't include taxes. And, and obviously the, the
- 16:08adjustment would have to be made and then have your preferred
- 16:10vendors somewhere. So when the client is going in
- 16:13to get selections, even if you're not dealing with this and
- 16:16designer is dealing with this, make sure you're talking with
- 16:18the designer and letting them know that these are your
- 16:21preferred vendors. Have a list of preferred vendors
- 16:23because first of all, it's easier to do business with
- 16:26someone recurring. You probably have, you know,
- 16:28contractor pricing, discounts, whatever with certain vendors.
- 16:31So you may as well be referring those vendors to clients to make
- 16:35selections. And it's just easier getting
- 16:37pricing from a few different people that you already know
- 16:40than the client just going out there and shopping around or
- 16:42some designer just using all these different suppliers all
- 16:45over town. You know, they've got three
- 16:47different type of tile from three different type of
- 16:48suppliers and it's just a mess, right to go in and actually get
- 16:51this stuff or price it out. So have a list of preferred
- 16:54vendors, provide that to the client, provide that to the
- 16:56designer. Yes, they can go off, you know,
- 16:58out of those, but at least you are trying to kind of rein them
- 17:02in as far as like which suppliers that they should be
- 17:05selecting from. Alright, now we got the seven
- 17:08thing here. This is equipment.
- 17:09Alright, So equipment is things like rentals.
- 17:13And if you're supplying your own equipment, you can rent it out
- 17:17to the client if it's big things because that way the client is
- 17:20paying for the the use of it. Essentially, this is going to
- 17:24work everything like you're not gonna rent out your skill saws
- 17:26or, or some basic thing that's very expected.
- 17:29But if you've got to rent like a, a large generator or you
- 17:33know, pumps to pump out their, their lot because there's a lot
- 17:37of water in it or something like that.
- 17:38And you happen to have a pump. But typically you'd have to rent
- 17:41that, put stuff like wear and tear on machinery or, or rentals
- 17:45into your budget and have a little bit of rental space in
- 17:49there. Again, even if you're like, I'm
- 17:51not sure if I really need a rental here.
- 17:53There's always things that come up sometimes need to rent a
- 17:55bunch of humidifiers because maybe the, you know, humidity is
- 17:59really high and you've got hardwood floors going in and you
- 18:02need to keep, you know, the humidity down or whatever rate.
- 18:04So just be thinking forward, scaffolding, fencing, site
- 18:07protection, whatever it may be that you have some sort of
- 18:11rental in there. And then the last thing I want
- 18:13equipment is security. What kind of security do you do?
- 18:16You setting up cameras nowadays is a really great way to make
- 18:20sure the site's taken care of, make sure your materials aren't
- 18:22going off site and have that as a line item in your, in your
- 18:25estimate, you know, $100 a month or whatever it may be for on
- 18:30site security and let the client know you'll get access to the
- 18:32security. You can check the footage
- 18:34Commission live. You can see what's happening on
- 18:37site, all this kind of stuff, right.
- 18:38So this is a big boat like bonus both to you as a builder and the
- 18:42client. And then just put it in there,
- 18:44have the client pay for it because it's it's an added
- 18:46service, added value. You can buy your own cameras and
- 18:49your own security equipment if you want and again, rent it to
- 18:52the client, if that makes sense, whatever, however you want to
- 18:55set it up, but it's it's something that can be done and
- 18:57just price it into your project. Alright, so now you should know
- 19:00how to price your project well without losing money.
- 19:02Make sure you go check out the next video in the series.
- 19:05This is estimating mastery. This next one is on fixing
- 19:08proposals. So now that you've got the
- 19:09pricing and everything in place, you've got to go fix your
- 19:12proposal to make sure you can put the proposal in front of a
- 19:14client and sell the project. You don't want to miss that.
- 19:17Go check out the next video.