- 0:05Speaker 1: Underground construction part of the Routes forty seven and seventy
- 0:08one expansions in the Yorkville area. Written by Joey Weslow,
- 0:15this article is being read by an automated voice brought
- 0:18to you by Everlett. Drivers have had to be patient
- 0:23navigating construction congestion on the south side of Yorkville while
- 0:26the Illinois Department of Transportation widens Illinois Route seventy one.
- 0:31The area is also undergoing a significant Illinois Route forty
- 0:34seven expansion that should alleviate rush hour traffic. To continue
- 0:39a leg of the roadwork south along Route forty seven
- 0:41from Canton Farm Road to Route seventy one, the City
- 0:44of Yorkville will relocate underground utilities out of the proposed
- 0:47roadway area. The city is digging up and relocating a
- 0:51water main that stretches along Route forty seven from the
- 0:54wind Debt Ridge Subdivision out to the intersection of Route
- 0:56seventy one and Root forty seven. While get Out as
- 0:59respet fondsible for a large portion of the project, the
- 1:01city is responsible for covering the costs of the utility's relocation.
- 1:06The City Council approved a proposal of one hundred and
- 1:08fifty one thousand, seven hundred and thirteen dollars, with an
- 1:11additional fifty six thousand, five hundred dollars in direct expenses,
- 1:14with Engineering Enterprises, Inc. To perform all fieldwork, complete the plans,
- 1:19permit the plans, and bid the project. Overall, idot's multi
- 1:24year plan allocates forty three and a half million dollars
- 1:27for the reconstruction with additional traffic lanes of a four
- 1:31point two mile section of Route forty seven from Route
- 1:34seventy one to Campden Farm Road, id as widening Route
- 1:39seventy one from a two lane to a four lane
- 1:41highway with a raised median from Illinois Route one twenty
- 1:45six to Orchard Road in Oswego. This project is projected
- 1:50to be completed by the end of this year. Further north,
- 1:53i DOT is undergoing a massive expansion of the Route
- 1:56forty seven corridor from Kennedy Road in Yorkville out to
- 1:59Sugar Grove's Cross Street. I DOT is involved in all
- 2:03parts of the project, including widening the intersections at Root
- 2:06forty seven and Galina Road. Once completed, Root forty seven
- 2:10will be widened and expanded and will feature pathways and bridges.
- 2:13More accessible to pedestrians. IDOT has slated sixty seven point
- 2:18two million dollars for the four point three mile section
- 2:21for Route forty seven extending from Galena Road in Yorkville
- 2:24to Cross Street in Sugar Grove. I DOT is spending
- 2:28fifty seven point five million dollars more on the two
- 2:30point three mile section from Root forty seven from Galena
- 2:34Road to Kennedy Road in Yorkville. The city is relocating
- 2:38underground utilities in their portions of the roadways slated for construction.
- 2:43The construction is expected to take at least two years
- 2:46to complete. All of the projects are part of a
- 2:49larger design plan to improve traffic congestion in the region,
- 2:53which has seen population growth far outpace the roadway infrastructure,
- 2:57causing traffic headaches. Yorkville Public Works Director Eric Doozy previously
- 3:03said the construction will cause temporary traffic congestion, but will
- 3:07be well worth it in the long run. He said
- 3:10drivers will see a huge improvement on traffic flows, hopefully
- 3:14alleviating the half mile backups during a rush hour A
- 3:16long Route forty seven