- 0:05Speaker 1: Yorkville approves one hundred and forty nine dollars six hundred
- 0:09Speaker 1: dollars engineering contract to help power data center. Written by
- 0:14Speaker 1: Joey Weslow, This article is being read by an automated
- 0:19Speaker 1: voice brought to you by ever Litt. As the design
- 0:24Speaker 1: on Yorkville's first data center takes another step forward, the
- 0:28Speaker 1: city is laying the groundwork for the complicated process of
- 0:31Speaker 1: hiring contractors needed to pull off the high powered engineering
- 0:35Speaker 1: for these developments. A critical component of the already approved
- 0:40Speaker 1: five hundred megawat two hundred and twenty eight acre Cyrus
- 0:43Speaker 1: one data center with eight one story warehouses is the
- 0:47Speaker 1: installation of a four hundred thousand square foot electrical substation.
- 0:53Speaker 1: The City Council approved a one hundred and forty nine thousand,
- 0:56Speaker 1: six hundred dollars contract for electrical engineering consulting services with
- 1:00Speaker 1: Sergeant and amp lundy LLC regarding the data center's medium
- 1:03Speaker 1: and high voltage electrical components. The contract includes five hundred
- 1:07Speaker 1: and sixteen billable hours at two hundred and fifty one
- 1:10Speaker 1: ers per hour. All costs associated with the contract will
- 1:14Speaker 1: be passed through expenses to the developer and will not
- 1:17Speaker 1: impact the city's general Fund. Christy Barksdale Noble, the city's
- 1:20Speaker 1: Community Development director, said during the February twenty fourth City
- 1:23Speaker 1: Council meeting timely engagement of a qualified consultant is essential
- 1:27Speaker 1: to avoid delays of any plan reviews, testing, or commissioning.
- 1:32Speaker 1: Developers currently project the electrical substation to be completed later
- 1:37Speaker 1: this year and the data center campus energization complete in
- 1:40Speaker 1: early twenty twenty seven. Full construction of all the warehouses
- 1:45Speaker 1: could take between ten to twenty years, according to the developers.
- 1:50Speaker 1: Given the scale, technical complexity, and safety implications of high
- 1:54Speaker 1: voltage transmission and substation systems, the city must retain specialized
- 1:59Speaker 1: electrical engineering expertise. According to city documents, the energization phase
- 2:06Speaker 1: of such a high powered campus is described by city
- 2:08Speaker 1: staff as one of the most critical risk points in
- 2:10Speaker 1: the life cycle of a data center development. The work
- 2:15Speaker 1: of the electrical consulting specialists is intended to complement all
- 2:18Speaker 1: the other inspection and review services conducted by city staff.
- 2:23Speaker 1: The city is planning to engage in similar limited scope
- 2:26Speaker 1: consulting agreements for each future data center project. According to
- 2:30Speaker 1: city documents, the city currently is entertaining more than a
- 2:35Speaker 1: dozen data center campus proposals across three thousand acres in
- 2:38Speaker 1: the Elder Main Road corridor. The city said laying down
- 2:42Speaker 1: the groundwork for consulting agreements now ensures future consistency across
- 2:46Speaker 1: multiple large scale developments. The work performed by city staff
- 2:51Speaker 1: includes services on low voltage electrical systems. It also includes
- 2:54Speaker 1: architectural and structural plan reviews, mechanical systems inspections, and site
- 2:58Speaker 1: planning work. The city council recently passed more costly data
- 3:03Speaker 1: center permit fees to cover the costs of increased city
- 3:05Speaker 1: inspection work, including the necessary new city hires. The city
- 3:11Speaker 1: is looking to hire a full time electrical inspector and
- 3:13Speaker 1: a full time mechanical inspector in the next few years,
- 3:16Speaker 1: according to city documents.