Latest / Talking Michigan Transportation / Rebuilding the third segment of I-696 begins soon
Transcript
- 0:07Jeff Cranson: Hello, welcome to the Talking Michigan Transportation Podcast.
- 0:10Jeff Cranson: I'm Jeff Cranson.
- 0:11Jeff Cranson: Today I'm going to be talking about one of the major projects coming up in this construction season.
- 0:21Jeff Cranson: This one will extend through 2027, and that's rebuilding the final segment of I-696, a major freeway that runs across Oakland and Macomb counties, north of the city of Detroit, and carries a heck of a lot of traffic, some of the biggest traffic volumes of any roads in the state.
- 0:39Jeff Cranson: As a matter of fact, Brian Travis, the project manager, spoke with me about what he expects to go on during construction and about the public involvement that's gone on leading up to this, and also some interesting history to the freeway and the freeway's original concept and how it was built in three different segments, with the central segment being delayed for lots of various reasons and some other interesting things.
- 1:06Jeff Cranson: So I hope you enjoy the conversation.
- 1:08Jeff Cranson: Okay, again I'm with Brian Travis, who is already finishing up a major project, the I-96 flex route in Oakland County, and as he sees that to fruition, he's about to jump into another big one, which is the final segment of rebuilding 696, major thoroughfare through Oakland and Macomb counties.
- 1:28Jeff Cranson: Heavy traffic, one of the heaviest volume routes in the state and it comes with inconvenience.
- 1:35Jeff Cranson: As always, there's some short-term pain for what we hope is long-term gain, which will be a much smoother road where concrete chunks aren't flying up anymore and people's commutes will be reliable, which is what we all hope for.
- 1:50Jeff Cranson: So, Brian, thanks for taking time to be here.
- 1:53Brian Travis: Absolutely yeah.
- 1:53Brian Travis: Thanks for having me, Jeff.
- 1:55Jeff Cranson: So let's talk a little bit.
- 1:57Jeff Cranson: I want to get into some history.
- 1:58Jeff Cranson: You and I were both kind of fascinated by what we learned about 696 and its origins.
- 2:03Jeff Cranson: Kind of fascinated by what we learned about 696 and its origins.
- 2:06Jeff Cranson: But before we get into that, could you talk about the project overall, the various phases and what's coming next in 2025 through 2027?
- 2:16Brian Travis: Sure, yeah.
- 2:16Brian Travis: So I mean we are, as everyone knows, just kind of finishing up the segment there to the west from I-275 to Losser.
- 2:22Brian Travis: We've been working on that for the past two seasons and the next step is to move to the east from Lahser to Dequinder Road.
- 2:30Brian Travis: That is sort of the last segment of the whole corridor of I-696 that needs attention.
- 2:36Brian Travis: That's a pavement from the late 80s.
- 2:39Brian Travis: So, although it's not as quite in dire condition as you know, this last segment that we're reconstructing, it's time to do it.
- 2:47Brian Travis: So we will be starting here in March 1st actually.
- 2:51Brian Travis: So about a month and a half away from now.
- 2:52Brian Travis: We will detour eastbound I-696.
- 2:57Brian Travis: Traffic will be detoured south on M-10, the Lodge Freeway to the Davison M-8, back to I-75, northbound to 696.
- 3:08Brian Travis: So we'll be fully reconstructing that pavement between Lahser Road and I-75.
- 3:15Brian Travis: From I-75 to Dequindre we're going to patch that concrete pavement that's a bit newer, that was constructed, I believe, in 1999.
- 3:21Brian Travis: And this will happen over a three-year period.
- 3:24Brian Travis: So the detour route is two continuous seasons that will conclude at the end of 2026.
- 3:31Brian Travis: And then we'll finish that last season in 2027, working on that stretch from Lahser to the Dequindre, patching the pavement there.
- 3:39Brian Travis: There's also a lot of bridge work on this corridor.
- 3:42Brian Travis: There's about 60 bridges that we're touching, doing a lot of extensive rehab on those.
- 3:47Brian Travis: Those will happen over all three seasons.
- 3:49Brian Travis: We're also reconstructing one of the tunnel bridges, or the plaza bridges.
- 3:54Brian Travis: That is, the Church Street Plaza, which we call it carries Church Street.
- 4:00Brian Travis: This is an oak park.
- 4:01Brian Travis: A lot of people driving on the freeway probably know these as the tunnels.
- 4:05Brian Travis: They have the lights in them.
- 4:06Brian Travis: So that's a very, very major bridge for us that that will take all three seasons to reconstruct we should talk as we talk about the history.
- 4:14Jeff Cranson: We should talk later about how those came to be and why there are plazas, which is a little bit unique to most of michigan's freeways.
- 4:21Jeff Cranson: But first I was hoping you'd talk a little bit about the outreach and public engagement that goes on for a project like this that touches so many cities along the corridor, and how difficult it is in modern times with such a fractured media environment.
- 4:38Jeff Cranson: I mean, in the olden days you put a legal ad in the free press and the Detroit News and everybody knew what was going on and they had plenty of heads up.
- 4:48Jeff Cranson: But now there's just no way to target everybody and no matter what you do, there are people that might not hear about it until the project actually starts.
- 4:55Jeff Cranson: So could you talk about the challenges of public engagement?
- 4:59Brian Travis: Sure, this project has been in design for a few years now and, like you say, there's a hundred different ways to get news these days traditional, tv, newspaper or social media.
- 5:10Brian Travis: Right, if it's not capturing your attention in a matter of a few seconds, people aren't paying attention to it.
- 5:15Brian Travis: So we've issued press releases, we've had public meetings, we've had graphics out there, but it's really difficult to, I think, grab especially motorists' attention when something is two or three years away.
- 5:29Brian Travis: We will hold another public meeting next month to try to, you know, alert everybody that, hey, this is coming, but it is challenging and it's not something that we take lightly.
- 5:41Brian Travis: We coordinate very, very closely with all the local communities that we take lightly.
- 5:45Brian Travis: We coordinate very, very closely with all the local communities throughout this process.
- 5:47Brian Travis: They have input on the design, they voice their concerns with projects that they have going on or things with, you know, emergency response or access or pedestrians.
- 5:56Brian Travis: So we take all of that into consideration.
- 5:59Brian Travis: So all of these local communities, the governments, they're aware of the project that's coming.
- 6:03Brian Travis: I think it's the citizens, the commuters that aren't always in tune with.
- 6:08Brian Travis: You know, traffic's going to be detoured for two seasons, so the word is starting to get out now, and that's why we're trying to really, you know, get as much accurate information as we can to the public as we can to the public.
- 6:27Jeff Cranson: Well, I think one of the frustrations for the people in the department and for you as a project manager are that you don't really have any means of making people use the official detours, and so you know people are going to find their own way in a lot of cases, and that might put them on local streets and have an effect on the local grid.
- 6:43Jeff Cranson: How do you talk about that when local officials say, hey, they're going to clog up my streets because you closed down the freeway?
- 6:51Brian Travis: Yeah, again, we do the best we can.
- 6:53Brian Travis: We have a posted detour.
- 6:54Brian Travis: We typically post detours freeway to freeway.
- 6:57Brian Travis: We know in this case a lot of people probably won't follow that posted detour.
- 7:02Brian Travis: Maybe some trucks will or people from out of town.
- 7:05Brian Travis: But people are going to use 8 mile, 10 mile, 12 mile, whatever route is most convenient for them, and we can't completely shut down all the construction that's happening in the area for the next two years.
- 7:16Brian Travis: We can't plan for every single scenario.
- 7:20Brian Travis: So you know, we do the best we can to get the word out.
- 7:24Brian Travis: We do the best we can with trying to adjust signal timings, trying to coordinate projects.
- 7:29Brian Travis: But you know certain communities have certain money that's allocated that has to be spent in a certain year.
- 7:36Brian Travis: So you again can't control every project and every schedule that's going on around town.
- 7:42Brian Travis: But we do the best we can to mitigate inconveniences, congestion, whatever the case may be with, you know, signal timings or trying to encourage traffic to use certain routes whenever we can.
- 7:57Jeff Cranson: I think the history of this is interesting.
- 7:59Jeff Cranson: I know you were looking into it, as was I.
- 8:01Jeff Cranson: I just assumed it was a newer concept overall relative to some of the other interstates from the original 1950s, you know Eisenhower era interstate system.
- 8:11Jeff Cranson: So I-75, i-94, i-69, a little bit later than those, but as it turns out, 696, which I think one of the reasons I thought it was newer is because it's a three number shield instead of the traditional two numbers.
- 8:26Jeff Cranson: It was supposed to be I-98.
- 8:29Jeff Cranson: And, for whatever reason, the Federal Highway Administration rejected that, but it was in some original plans and yet the three segments took a long, long time to build.
- 8:41Jeff Cranson: What did you find most interesting as you looked into that background?
- 8:44Brian Travis: Yeah, it is very interesting.
- 8:46Brian Travis: So this whole corridor it's about 28 miles and it goes from I-275 to I-94.
- 8:52Brian Travis: And it was built in three separate segments.
- 8:54Brian Travis: So actually the first segment built was the west segment from I-275 to M-10.
- 9:00Brian Travis: And that was finished, I believe, in 1964.
- 9:04Brian Travis: 275 to M10.
- 9:05Brian Travis: And that was finished, I believe, in 1964.
- 9:06Brian Travis: And so for a handful of years if you're coming from the West you're forced off at the Lodge Freeway, you go downtown or wherever your destination is.
- 9:12Brian Travis: And the rest of 696, actually the eastern portion from I-75 to I-94, was constructed second.
- 9:20Brian Travis: That was completed in 1979.
- 9:23Brian Travis: And that middle piece from M10 to I-75 kind of sat in controversy for years.
- 9:30Brian Travis: I believe it was, you know, discussed right in the beginning with the rest of these, the corridor, the other two segments.
- 9:37Brian Travis: But because it intersected some important communities, you know I think it touches eight or nine different cities through the corridor.
- 9:46Brian Travis: You know, if you look at the layout of that middle segment it drops down, it's got curves, it's avoiding certain certain communities.
- 9:56Brian Travis: You know, downtown Royal Oak has to avoid, it had to avoid the Detroit Zoo.
- 10:01Brian Travis: It goes through Oak Park which has a large Orthodox Jewish community.
- 10:05Brian Travis: There was a lot of discussions with that community about how to construct a freeway but also maintain pedestrian access for them, and that's the reason for those three plaza bridges.
- 10:17Brian Travis: So a lot of unique considerations went into that middle segment.
- 10:21Brian Travis: Considerations went into that middle segment.
- 10:25Brian Travis: In fact I think, Jeff, we read the same thing that the governor at the time, George Romney, locked a group of decision makers in a room until they could agree on a way forward with this segment.
- 10:33Brian Travis: So all said and done I think it was talked about for 20 years or so.
- 10:40Brian Travis: I think it was finally completed in 1989.
- 10:43Brian Travis: So, yeah, interesting history.
- 10:44Brian Travis: So this is the newest segment but, like I said, it's at this point 36 years old.
- 10:50Brian Travis: It's time to address it.
- 10:52Jeff Cranson: Well, and it's going to last a good long time because you're doing for the most part, you're doing a major rebuild.
- 10:58Jeff Cranson: I think you pointed out earlier that some of this doesn't have to be completely rebuilt, but a lot of it is, and it's going to give you a long shelf life.
- 11:07Jeff Cranson: Now, on the new pavement, Absolutely yeah.
- 11:10Brian Travis: So it's again not as in dire condition as the other two segments were when we built them, but this again is going to give us a new pavement.
- 11:19Brian Travis: It's going to improve safety and reliability.
- 11:21Brian Travis: It's going to give us a new pavement.
- 11:22Brian Travis: It's going to improve safety and reliability.
- 11:24Brian Travis: And the reason behind reconstructing the ZL3 bridge that's the plaza bridge.
- 11:29Brian Travis: The number designation is ZL3.
- 11:31Brian Travis: That's the bridge that has the water leaking through it.
- 11:35Brian Travis: We've got some icicles that form in the wintertime.
- 11:37Brian Travis: It's a safety hazard.
- 11:38Brian Travis: The new design of that bridge is going to eliminate that problem.
- 11:42Brian Travis: So again, when it's all said and done, it's going to be a much safer, much smoother corridor.
- 11:54Jeff Cranson: Yeah, I think that addressing that specifically those leaks at the plaza, make a lot of sense and that is very interesting history what the department did at the time to accommodate the community and the people that basically walked to synagogue.
- 12:03Jeff Cranson: I think that showed a lot of sensitivity and that's really interesting.
- 12:06Jeff Cranson: But I sure wish there was a recording of Governor Romney in the room with those local officials forcing them to get an agreement on the route.
- 12:16Jeff Cranson: It would be fascinating to listen to now.
- 12:18Jeff Cranson: Totally agree, we'll be right back, stay tuned.
- 12:27Brian Travis: Totally agree.
- 12:27Brian Travis: We'll be right back.
- 12:28Brian Travis: Stay tuned, know before you go.
- 12:28Brian Travis: Head on over to MiDrive to check out the latest on road construction and possible delays along your route.
- 12:47Jeff Cranson: For a detailed map head over.
- 12:48Jeff Cranson: Doing that 96 project was huge.
- 12:50Jeff Cranson: I mean it's got to be the biggest thing you've been involved in as a PM.
- 12:53Jeff Cranson: I would think Could you talk a little bit about what you think you learned along the way?
- 12:57Jeff Cranson: That'll be a benefit to you as you manage this one.
- 13:00Brian Travis: Yeah, I've had the honor of working on the 96 Flex Route project.
- 13:04Brian Travis: I was on the eastern reconstruction of I-696 in Macomb County a few years back, so definitely have learned a lot about how to manage a schedule this large and what it takes to complete a job of this size.
- 13:19Brian Travis: You know these are huge jobs.
- 13:20Brian Travis: It does require a lot of people, a lot of effort.
- 13:23Brian Travis: Size these are huge jobs.
- 13:25Brian Travis: It does require a lot of people, a lot of effort.
- 13:27Brian Travis: It requires a contractor that's able to deliver a quality project and work day in and day out to lay down material, produce concrete, get trucks in and out of the corridor and doing it safely.
- 13:38Brian Travis: Safety is probably the biggest thing that we've learned throughout the corridor is we still have to build these freeways while also having traffic right adjacent to us, two-way traffic or traffic on the bridges.
- 13:54Brian Travis: Whatever the scenario is, there's always incidents that happen, that happen.
- 13:59Brian Travis: There's coordination that we have to have with emergency response personnel to get you know, fire trucks in police cars, ambulances in to respond to incidents, and so I kind of want to touch on this particular project we get.
- 14:15Brian Travis: The question is you know, why are we detouring eastbound?
- 14:18Brian Travis: Why don't we have traffic maintained on one side of the freeway, like the last two jobs that we did, and it really does come down to safety.
- 14:26Brian Travis: This section of freeway is what we call a depressed section of freeway.
- 14:30Brian Travis: We've got the large, like 25-foot tall, retaining walls on both sides and to maintain two lanes each direction on one side of the road.
- 14:40Brian Travis: You know you're taking away shoulders.
- 14:43Brian Travis: You have very limited room as it is there.
- 14:46Brian Travis: So to have something happen on the freeway a fire, an incident very, very difficult to get responders in there.
- 14:53Brian Travis: In fact, between M-10 and I-75, there is a restriction for any explosive material or flammable material.
- 15:03Brian Travis: You can't be transported on that route.
- 15:05Brian Travis: Just for that reason You're in the depressed section of freeway.
- 15:08Brian Travis: So it really comes down to safety.
- 15:10Brian Travis: Also, schedule right.
- 15:12Brian Travis: You know if we have traffic pushed on one side of the roadway, there's a certain section on the west part of this job that we go down to three lanes near Southfield Road.
- 15:24Brian Travis: Lahser again kind of presents an issue with width of construction to build some of the stuff that we need to build in the median.
- 15:33Brian Travis: That would probably push construction another six months into a third season.
- 15:37Brian Travis: So having traffic detoured is really our best option here.
- 15:41Jeff Cranson: Yeah, I was going to ask you about that.
- 15:43Jeff Cranson: Oftentimes it's obviously safety is first and it's much safer to not have workers right there with the heavy traffic, but it also makes the project more efficient overall.
- 15:55Jeff Cranson: Right, it's less time doing the rebuild.
- 15:58Brian Travis: Yeah, certainly.
- 15:59Brian Travis: And again, a lesson learned here is access for us and the contractor.
- 16:05Brian Travis: We have to get in and move around the job efficiently and when you're trying to maintain too much traffic it really limits our access with ramps and the amount of room that we have to stage equipment and materials.
- 16:17Brian Travis: So, Really, building eight miles of freeway, both bounds, in two years is about as aggressive as a schedule as we can produce here.
- 16:31Jeff Cranson: Yeah, I mean, we all take freeways, roads for granted.
- 16:35Jeff Cranson: There's an armchair engineer in everybody and they drive by and think, whatever, however long it's taking, it's taking too long right, because it's inconveniencing me.
- 16:45Jeff Cranson: So, yeah, I know you got to deal with that.
- 16:47Jeff Cranson: You probably hear it from friends and family and have to spend time explaining and there's probably sometimes you wish that nobody knew you worked for MDOT, right.
- 16:55Brian Travis: Yeah, yeah, it happens all the time.
- 17:00Jeff Cranson: So, as you look toward this and the benefits obviously smoother pavement, nicer ride what else would be added benefits once this is completed and kind of modernized?
- 17:14Brian Travis: I mean, I think it's a benefit to all.
- 17:16Brian Travis: This is one of our busiest corridors in the state.
- 17:18Brian Travis: Traffic numbers range from 180,000 to 200,000 vehicles a day, depending on what part of this corridor you're on.
- 17:26Brian Travis: So I think, as commuters, we can all appreciate a brand new freeway and, like I said, from 275 to 94, that's a 28-mile stretch.
- 17:37Brian Travis: If you include the I-96 flex route to Kent Lake Road, that's another 12 miles.
- 17:43Brian Travis: That's 40 miles of freeway.
- 17:44Brian Travis: That's going to be basically brand new.
- 17:46Brian Travis: That we've done since 2018.
- 17:49Brian Travis: I mean, that's a huge accomplishment, not only for us but for the area.
- 17:53Brian Travis: It affects everybody.
- 17:55Brian Travis: It affects business, commerce, safety.
- 17:58Brian Travis: So it's hard to argue with the benefit that everyone's going to see when this is all said and done.
- 18:05Jeff Cranson: Well, one of the things we came across in that history was a reference to the American Autobahn and I can see where that came from, because it certainly feels like that sometimes.
- 18:14Jeff Cranson: I know the state police have done targeted enforcement there and been amazed at the number of citations just in a matter of a few hours, just in a matter of a few hours.
- 18:23Jeff Cranson: So that probably goes as much as anything to your point about the safety of having the freeway completely closed because people drive really fast on 696.
- 18:32Brian Travis: They do.
- 18:32Brian Travis: Yeah, the speed limit in our work zones is 60 miles an hour.
- 18:35Brian Travis: A lot of people don't follow that and it's concerning and that's a major reason we have crashes and fender benders and you know congestion out there.
- 18:47Brian Travis: It's people want to get to where they're going as soon as possible and don't consider the consequences a lot of times.
- 18:54Brian Travis: So you're right, this helps.
- 18:55Brian Travis: You know, westbound is going to be maintained both years.
- 18:59Brian Travis: They're going to have a shoulder, so it's much safer if you, if you, have a crash out there, it's more like it functions right now when traffic is in its normal configuration.
- 19:09Brian Travis: So I think you know, although the detour will be painful for commuters, I think people are going to find their route.
- 19:16Brian Travis: They're going to find their way and hopefully be appreciative that they're not stuck two-way traffic with no shoulder and having sort of just unpredictable commutes every day.
- 19:27Jeff Cranson: Yeah Well, thank you for talking about that and you know I wish you luck.
- 19:32Jeff Cranson: Let's pivot real quickly to your other big project, wrapping up the I-96 Flex route in western Oakland County.
- 19:39Jeff Cranson: Where do we stand with that?
- 19:42Jeff Cranson: And the follow-up would be talk a little bit about ramp metering and how that will work.
- 19:47Brian Travis: Sure.
- 19:47Brian Travis: So we've completed basically all of the physical construction out there on the flex route.
- 19:52Brian Travis: We'll have a few things that we have to go tackle in the spring, just some some minor concrete work and some some bridge epoxy overlay work.
- 20:01Brian Travis: But the main focal point is is the actual flex route infrastructure right?
- 20:06Brian Travis: So if you've commuted that route since December, you've probably seen the red Xs that are currently present over the shoulder.
- 20:14Brian Travis: We're testing the system right now, internally testing all the different scenarios, testing the software, the equipment, the electronics.
- 20:25Brian Travis: We are planning to go live, hopefully by the end of next month, end of February, with the flex route.
- 20:31Brian Travis: So you know that's again going to function during peak periods People will have an extra lane on eastbound in the morning, an extra lane on westbound in the afternoon.
- 20:40Brian Travis: The ramp metering is also going to be part of that.
- 20:44Brian Travis: We're testing that as well.
- 20:46Brian Travis: So you've probably seen traffic signals at the end of some of the on-ramps throughout the corridor.
- 20:52Brian Travis: There's eight ramps that are going to be affected by this and the ramp metering is there to kind of go hand in hand with the flex row.
- 20:59Brian Travis: The meters will function when traffic is congested on that mainline freeway and what that does is just allows traffic to be integrated in that corridor one by one, rather than sending a platoon of, say, 10 to 20 cars on at one time, just causing more downstream congestion on the freeway.
- 21:23Jeff Cranson: This is the first time that we've.
- 21:24Jeff Cranson: Yeah, go ahead.
- 21:25Jeff Cranson: I'm just going to say it's proven to make for much safer entry on freeways when it's been used in other states.
- 21:33Brian Travis: Yeah, and it's used in a lot of other states.
- 21:36Brian Travis: We had it here briefly, I think, in the 1980s on the Lodge and maybe 94.
- 21:42Brian Travis: But for most drivers here it's going to be brand new, so I think there's going to be a learning curve.
- 21:48Brian Travis: It's fairly simple.
- 21:50Brian Travis: There's a signal that you're going to be required to stop at when it's activated, and other times of day when it's not activated, it's going to flash yellow.
- 22:01Jeff Cranson: Yeah, no, I'm looking forward to the technology.
- 22:05Jeff Cranson: Obviously, that section is as busy as US 23 is where the first flex route is.
- 22:10Jeff Cranson: That section of 96 in Oakland County is is is very busy certain times of day and I think it'll it'll be a real nice bonus for the people that have to travel that.
- 22:21Jeff Cranson: So is there anything else you want to say about either one of these things, brian, before we wrap up?
- 22:25Brian Travis: I'll just say the 696 project we've been working on the last couple years.
- 22:30Brian Travis: We'll have a bit more work in the spring to put in permanent pavement markings on eastbound 696.
- 22:38Brian Travis: We have some tree plantings to do, so you'll see some activity out there as well.
- 22:42Brian Travis: But for the most part, with that project and the FlexRoute you know, we're substantially complete as far as traffic impacts.
- 22:50Jeff Cranson: Yeah, no, that's great.
- 22:52Jeff Cranson: It'll be a nice thing to celebrate.
- 22:54Jeff Cranson: Well, thank you, as always, for taking time to talk about these things.
- 22:57Jeff Cranson: I really appreciate the effort you put into communicating with the public and various people that are affected by these things.
- 23:05Jeff Cranson: It's a very important part of what you do.
- 23:08Brian Travis: Yeah, appreciate the opportunity to talk through this.
- 23:11Brian Travis: You know we're expecting another successful project and excited to get started.
- 23:18Brian Travis: Yeah, that's great.
- 23:20Jeff Cranson: I'd like to thank you once more for tuning in to Talking Michigan Transportation.
- 23:24Jeff Cranson: You can find show notes and more on Apple Podcasts or Buzzsprout.
- 23:28Jeff Cranson: I also want to acknowledge the talented people who help make this a reality each week, starting with Randy Debler, who skillfully edits the audio, Jesse Ball, who proofs the content, Courtney Bates, who posts the podcast to various platforms, and Jacke Salinas, who transcribes the audio to make it accessible to all.