- 0:05Welcome back to the Remodel Report, brought to
- 0:08you by USA Cabinet Store. I am Chris, and today
- 0:12we are answering the question every homeowner
- 0:14asks in the first five minutes of a design meeting.
- 0:18How long is this going to take? Jessica is here
- 0:20with the real numbers. Jessica, give me the short
- 0:24answer. Hey, Chris. The short answer is eight
- 0:27to 16 weeks from the first design meeting to
- 0:29the finished kitchen for most projects. But the
- 0:32part that matters to your daily life is shorter.
- 0:35The crew is actually in your house for about
- 0:37two to six weeks on a cosmetic update, six to
- 0:39ten weeks on a mid -range remodel, and 12 to
- 0:4220 or more weeks on a high -end renovation where
- 0:45walls or plumbing move. And those are general
- 0:48ranges across 13 showrooms in seven states. Where
- 0:52you live moves the number, and I will explain
- 0:54why in a minute. So there are two different clocks.
- 0:57Days the crew is there, and days until I can
- 0:59cook again. Exactly. And that is where most of
- 1:03the surprises come from. On site means a crew
- 1:06in your kitchen. Door -to -door includes the
- 1:08design meetings, the cabinet lead time, and the
- 1:11quiet days when your countertop is being cut
- 1:13in a shop across town. A kitchen that is six
- 1:16weeks on site can still be a 14 -week project.
- 1:19When you get a quote, ask which clock they are
- 1:22quoting. Now, if I search this online, I get
- 1:24three to six months everywhere. Why is your number
- 1:27shorter? Because those guides describe a typical
- 1:30general contractor. They buy cabinets from a
- 1:33dealer. wait for them, and then book five separate
- 1:36trades one after another. USA Cabinet Store is
- 1:39the cabinet store and the remodeling contractor.
- 1:42The order goes in the day you sign off on the
- 1:44design, delivery is scheduled to the install
- 1:47date, and the designer who drew the kitchen runs
- 1:49the build. That removes the two biggest gaps,
- 1:53the handoff between dealer and contractor, and
- 1:56the weeks a kitchen sits demolished waiting for
- 1:58boxes. And one more number you will see out there.
- 2:02Who's surveyed more than 20 ,000 homeowners this
- 2:05year and found kitchen projects average nine
- 2:07and a half months of planning and almost six
- 2:09months of construction? That sounds frightening
- 2:12until you realize it counts every month of thinking
- 2:14before anyone is hired. It is not a schedule.
- 2:18It is a warning that the calendar starts long
- 2:20before demolition. Let us talk about those boxes
- 2:24because you told me cabinets are the whole game
- 2:26on timing. They are the longest lead item in
- 2:29the kitchen, counting from the day the order
- 2:31is placed. Locally stocked, ready -to -assemble
- 2:34cabinets are ready in days. Stock lines take
- 2:37about 2 to 5 weeks. Semi -custom is 4 to 9 weeks.
- 2:42Custom is 7 to 12. And European frameless, the
- 2:46German -engineered, handle -less look is 10 to
- 2:4814 weeks because it is built in Europe. The spread
- 2:52inside each range is partly geography. Some lines
- 2:55ship from a plant or a distribution center that
- 2:58is close to one showroom and far from another.
- 3:00So the same order can land a few days apart.
- 3:03We plan the order date around that, and the shipment
- 3:06is ready for install day wherever you are. So
- 3:09the tier you pick is the single biggest decision
- 3:11on your calendar, and your showroom quotes the
- 3:14number for your address. And I'm guessing the
- 3:16lead time does not start until the order is complete.
- 3:20Right. A missing sync model or an unconfirmed
- 3:23range holds the whole order at the factory. That
- 3:26is why we ask for appliance model numbers at
- 3:28the first meeting. A 30 inch range and a 36 inch
- 3:32range need different cabinets on both sides.
- 3:35Decide the appliances first and the design is
- 3:37usually final in one round instead of three.
- 3:40Okay, the cabinets have arrived. Walk me through
- 3:43what happens once the crew shows up. Every kitchen
- 3:46follows the same order because each step depends
- 3:48on the one before it. Protection and demolition
- 3:51first. A few days for a cabinet swap. Up to two
- 3:54weeks if flooring or a wall comes out. Then rough
- 3:58and plumbing and electrical with an inspection
- 4:00if there is a permit. Anywhere from a few days
- 4:02to four weeks. Drywall and paint one to two weeks.
- 4:07Then cabinets go in three to five days. Then
- 4:10the countertop is measured on the installed cabinets
- 4:12and it goes off to fabrication for one to three
- 4:15weeks. Counters back in one to two days. Back
- 4:19splash two to three days. Then appliances, lighting,
- 4:24hardware, trim and the walkthrough. That fabrication
- 4:28stretch. Is that the part where people call and
- 4:30say, nobody came today? Every single time. The
- 4:35quiet week is not a stalled project. It is the
- 4:38slab being cut, or an inspection slot, or a delivery
- 4:41in the queue. Your designer can always tell you
- 4:44the reason and the next date. And here is the
- 4:47tell when you compare quotes. Ask whether the
- 4:50contractor's eight weeks includes those waiting
- 4:52days or only crew days. Two calendars can look
- 4:55identical on paper and be a month apart in real
- 4:58life. What about permits? Do they blow up the
- 5:01timeline? Only when the layout changes. A cabinet
- 5:04and countertop swap in the same layout usually
- 5:07does not need a building permit. Moving plumbing,
- 5:10adding circuits, relocating a gas line, or taking
- 5:13out a wall does. And then it adds roughly six
- 5:16to eight weeks and somewhere between $200 and
- 5:18$1 ,500 in fees, depending on where you live.
- 5:23The trick is to file it the day the order goes
- 5:25in, so the permit runs during the cabinet lead
- 5:28time instead of after it. That is how we do it
- 5:31in Fairfax County, and the same idea holds in
- 5:33Maryland, Houston, Tampa, everywhere we work.
- 5:37How long the county takes to review it is the
- 5:39part that changes by geography. Six to eight
- 5:42weeks is the general figure. Your showroom knows
- 5:45its local office. Let us do the honest part.
- 5:49Why do remodels run late? Six reasons, and most
- 5:52are decided before demolition, demolishing before
- 5:56the materials arrive, an incomplete order stuck
- 5:58at the factory, change orders after work starts,
- 6:02hidden conditions like a soft subfloor from an
- 6:05old dishwasher leak, which is why we recommend
- 6:07a 10 -20 % contingency at the top of that range
- 6:11in an older house, permit and inspection queues,
- 6:15and trades booked one after another instead of
- 6:17in advance. A contractor on Reddit described
- 6:21his in -laws' 1920s kitchen, a one -month estimate
- 6:24that finished after six months because of a load
- 6:26-bearing wall and a panel upgrade. His line was,
- 6:30the older the home, the more interesting stuff
- 6:32will be found. So give me the takeaways. Someone
- 6:36is signing a contract this month. What do they
- 6:38need to remember? Five things. One, ask for both
- 6:42clocks, on -site and door -to -door, and ask
- 6:45for a start date. because the average remodeler
- 6:48is booked about six weeks out right now. Two,
- 6:51pick appliances before the design is final. Three,
- 6:55match the cabinet tier to your deadline. A December
- 6:58kitchen signed in October is a stock kitchen.
- 7:01Four, order everything before demolition and
- 7:04make every decision before the order, because
- 7:06anything after that is a change order with a
- 7:09change order's delay. And five, do not anchor
- 7:12the finish date to Thanksgiving dinner. Give
- 7:15yourself a two -week cushion, and you will be
- 7:16pleasantly surprised. Perfect. The full week
- 7:20-by -week guide with the tables is on the USA
- 7:22Cabinet Store website, and a free design consultation
- 7:25ends with a real calendar for your kitchen, not
- 7:28an average. 13 showrooms across. Virginia, Maryland,
- 7:32North Carolina, Texas, New Jersey, Florida, and
- 7:34Tennessee. Jessica, thanks as always. Anytime,
- 7:38Chris. Happy remodeling, everyone. Plan the calendar
- 7:41first, and the kitchen takes care of itself.