Latest / Views and News with Clarence Ford / R797 million Van Schoorsdrift Road Safety Improvement Project along the N7 north of Cape Town
Transcript
- 0:00Speaker 1: The Western Cape Government put out this interesting press release
- 0:05Speaker 1: yesterday on the 20th of October, and it was by
- 0:08Speaker 1: the Minister of Infrastructure, Tarsia Simmers. They're making a significant
- 0:12Speaker 1: progress on the R797 million Fundsquare Drift Road Safety Improvement Project.
- 0:18Speaker 1: That's along the N7. Excuse me, earlier I said the N2.
- 0:21Speaker 1: I meant the N7 north of Cape Town, and completion
- 0:24Speaker 1: is scheduled for just now, March 2027. There's a lot
- 0:28Speaker 1: happening in this project, and we're going to pick that apart.
- 0:31Speaker 1: In the meantime, Tashia Simmers, good morning.
- 0:34Speaker 2: Hi, good morning, and good morning to all of the
- 0:35Speaker 2: Cape Talk listeners.
- 0:37Speaker 1: Thanks for joining us. Now, your construction milestones with this
- 0:40Speaker 1: massive project include, and I quote, 95% of stormwater drainage
- 0:45Speaker 1: being completed, 98% of curb construction completed, significant progress on
- 0:51Speaker 1: bridge structures and new road alignments, and the installation of
- 0:54Speaker 1: street lighting infrastructure underway. Tatius, for those who have not
- 0:58Speaker 1: been following this potentially, when did all of this, when
- 1:00Speaker 1: did these projects start?
- 1:03Speaker 2: Well, this project started a bit more than 50 months ago.
- 1:06Speaker 2: So we are within budget, I must say, and we
- 1:09Speaker 2: are actually on schedule with this project. So in under
- 1:14Speaker 2: 36 months, we are close to completion already.
- 1:17Speaker 1: It's a big number. And I think for those of
- 1:19Speaker 1: us who are, you know, not too schooled on what
- 1:21Speaker 1: things cost, 797 million rand, it's a staggering amount of money.
- 1:25Speaker 1: I wonder, and not to put you on the spot,
- 1:27Speaker 1: but if we can understand a little bit more about
- 1:30Speaker 1: how far this money goes and to what. There's obviously
- 1:33Speaker 1: an unbelievable amount of manpower necessary. And I know that
- 1:36Speaker 1: a lot of work opportunities have been created, 394 of them.
- 1:40Speaker 1: And then there's, of course, the price of materials and machinery, etc. Again,
- 1:45Speaker 1: without putting you on the spot, could you give us
- 1:47Speaker 1: a rough breakdown of how these funds are split and
- 1:51Speaker 1: what goes to what?
- 1:53Speaker 2: Well, no, indeed, a fair portion of the cost is
- 1:56Speaker 2: obviously material, which is the bulk of the cost, which
- 2:00Speaker 2: does include, I mean, we fold a number of bridges
- 2:04Speaker 2: and culverts as part of the van Schoorstreef N7 interchange,
- 2:08Speaker 2: also building a new bridge over the N7. We've built
- 2:12Speaker 2: the second longest bridge over a span, but also the
- 2:18Speaker 2: longest bridge bridge in South Africa with a double spine.
- 2:23Speaker 2: So again, these are all phenomenal figures and sizes that
- 2:27Speaker 2: I'm talking to. But then there's also the small works,
- 2:30Speaker 2: which is a requirement, obviously, with the current water price
- 2:34Speaker 2: of bitumen has fluctuated quite a lot, which is the
- 2:36Speaker 2: phase where we are. And then obviously a fair portion
- 2:40Speaker 2: then goes to the remuneration and the appointment of subcontractors
- 2:44Speaker 2: and emerging contractors as part of our project. But the
- 2:46Speaker 2: bulk of the money goes into material projects and the
- 2:50Speaker 2: unique concrete designing that we needed to do in terms
- 2:57Speaker 2: of our bridges which were designed for this mega project
- 3:00Speaker 2: at Transcoast.
- 3:04Speaker 1: 83,102 person days of employment have been generated with this project.
- 3:08Speaker 1: and R131. 8 million has been spent on targeted enterprises that
- 3:12Speaker 1: support local economic participation. This according to the media release
- 3:16Speaker 1: that I have in front of me. Minister, in terms
- 3:19Speaker 1: of the purpose of this project, of course we're improving roads,
- 3:24Speaker 1: but we're also trying to keep people safe. I know
- 3:26Speaker 1: that the N7 doesn't have nearly the pedestrian problem that
- 3:29Speaker 1: the N2 has, but it does have its fair share
- 3:31Speaker 1: of pedestrian-related accidents and crashes, and I assume that a
- 3:35Speaker 1: lot of what's being done will hopefully try to curb
- 3:38Speaker 1: that as well.
- 3:40Speaker 2: You know, indeed, because if you don't understand that the
- 3:42Speaker 2: N7 is also a critical economic and transport corridor for
- 3:45Speaker 2: goods to the West Coast and beyond to Namibia and
- 3:48Speaker 2: so forth, but it also connects the surrounding communities which
- 3:52Speaker 2: falls within the city of Cape Town's jurisdiction. So, indeed,
- 3:56Speaker 2: all the safety aspects that we have built into this
- 3:58Speaker 2: was to incorporate, A, to enhance the safety aspects, A,
- 4:03Speaker 2: to bring this intersection up to a world standard to
- 4:08Speaker 2: ensure even enhanced safety. But again, because the city of
- 4:11Speaker 2: Cape Town are expanding and the one part of our
- 4:15Speaker 2: design does make into cognizance the expansion of the communities
- 4:20Speaker 2: which will form part of that corridor within the next
- 4:23Speaker 2: 10 to 15 years, ensure that as those future housing
- 4:27Speaker 2: developments will be implemented by the City of Cape Town
- 4:30Speaker 2: and the possible private sector partners, that the aspect of
- 4:33Speaker 2: free-flowing traffic, free-flowing various forms of mobility, that safety for
- 4:39Speaker 2: pedestrians is and remains key, given the number of people
- 4:43Speaker 2: that do currently use that part of the N7 corridor. Yeah.
- 4:47Speaker 1: You're in conversation with the Provincial Minister of Infrastructure, Tarsia Simmers,
- 4:51Speaker 1: and you're welcome to send through questions related to this
- 4:53Speaker 1: project on 021-446-0567 or WhatsApp 0725671567. Minister, of the 394
- 4:55Speaker 1: work opportunities, how many of those jobs are temporary? How
- 4:57Speaker 1: many are sustained? And what happens to these people who
- 4:58Speaker 1: have been fortunate enough to work on this project when
- 5:00Speaker 1: it concludes next year?
- 5:17Speaker 2: Well, look, indeed, we have a number of emerging and subcontractors.
- 5:20Speaker 2: A lot of the localized labor come from the area
- 5:24Speaker 2: of the movements in the surrounding communities, which does mean
- 5:27Speaker 2: that in March, when the contract comes to an end,
- 5:32Speaker 2: the project-linked contracts do come to an end. But what
- 5:36Speaker 2: we have seen in a number of projects in this world,
- 5:38Speaker 2: including the Panskouras Drift Project, is the fact that those
- 5:41Speaker 2: emerging contractors which we have employed over the duration of
- 5:45Speaker 2: this project We have invested over R151. 8 million in Target Enterprise,
- 5:50Speaker 2: not only ensuring that they're part of the contract, but
- 5:53Speaker 2: also taking them through a process where we invest in
- 5:57Speaker 2: terms of scaling them up in terms of business savvy.
- 6:00Speaker 2: Many of them, the CIDB grading has been improved, and
- 6:03Speaker 2: what we tend to do is, because there is a
- 6:06Speaker 2: few other projects which I will be announcing in the
- 6:08Speaker 2: new year as part of my budget, where we then
- 6:11Speaker 2: ultimately take a lot of these emerging contractors which we
- 6:14Speaker 2: have invested in during the course of this project and
- 6:17Speaker 2: other projects along the same corridor, they will then be
- 6:20Speaker 2: afforded a subcontractor opportunity with the future projects. And just
- 6:26Speaker 2: as a personal example for our listeners to understand, when
- 6:29Speaker 2: we did the refinery interchange, again, a phenomenal piece of
- 6:34Speaker 2: roads infrastructure on the same corridor, we actually took three
- 6:38Speaker 2: of the emerging contractors along two different squares of site,
- 6:42Speaker 2: and one of those three today Ultimately, from doing 5
- 6:46Speaker 2: million rands worth of work to about 40 million rands
- 6:48Speaker 2: worth of work. With that, as we invest in our
- 6:51Speaker 2: emerging contractors, the value of the quantum that we then
- 6:54Speaker 2: allocate to them in future projects do tend to increase
- 6:58Speaker 2: in value as well.
- 6:59Speaker 1: Got you. And you're saying as well, for those workers
- 7:02Speaker 1: who are only temporarily employed, by the time they're done here,
- 7:04Speaker 1: they should also be more and more employable, is what
- 7:07Speaker 1: I hear you saying.
- 7:09Speaker 2: Yes, indeed, because a number of them, as part of
- 7:11Speaker 2: our contract with the main contractor, It does focus on
- 7:14Speaker 2: SACWA-accredited training and skills development, because once the project is done,
- 7:20Speaker 2: we do want to leave behind a much more empowered
- 7:23Speaker 2: and much more up-skilled local community base, which, you know,
- 7:27Speaker 2: in future, other contractors will be able to use them
- 7:29Speaker 2: as well, given the various types of skill sets that
- 7:31Speaker 2: we've invested in, in terms of the Van Squares Drive-in
- 7:34Speaker 2: Serial Interchange project.
- 7:36Speaker 1: Minister, we've got an interesting question in here because it's
- 7:40Speaker 1: transport month in October, as you well know, and we've
- 7:43Speaker 1: got a question here around scholar transport and reckless taxi drivers,
- 7:46Speaker 1: but we're going to get to that in a second.
- 7:47Speaker 1: I just want to focus on this project for one
- 7:49Speaker 1: more second. The N7, as you've just mentioned, is a
- 7:54Speaker 1: huge corridor for freight and commuters, especially I think there's
- 7:57Speaker 1: a lot of trucks on there up to the west coast.
- 7:59Speaker 1: Have there been huge disruptions on that route, and if so,
- 8:03Speaker 1: how's that being managed? Because I can imagine... that traffic
- 8:07Speaker 1: there was bad before with added congestion and added construction.
- 8:11Speaker 1: Likely you're sitting with quite the situation there at times.
- 8:15Speaker 2: Well, look, I must say for the duration of the project,
- 8:18Speaker 2: I mean, we've had no incidents along that corridor. Our
- 8:22Speaker 2: communication was crystal clear when we would, you know, close
- 8:26Speaker 2: certain sections of that corridor, given when we built the
- 8:29Speaker 2: bridge over the N7, for instance. There was a Saturday
- 8:33Speaker 2: where one lane was closed for the entire day because
- 8:35Speaker 2: over 1,000 ducts with concrete had to get to pour
- 8:39Speaker 2: in and move and move in and pour and so forth.
- 8:41Speaker 2: But again, no incidents. Our communication was crystal clear. I
- 8:45Speaker 2: want to thank media, such as Scape Talk, for ensuring
- 8:48Speaker 2: that they informed our road users when these closures did occur.
- 8:51Speaker 2: So we've had very limited to no incidents at all.
- 8:56Speaker 2: And I also want to thank my partner, which is
- 8:58Speaker 2: the Department of Mobility, towards ensuring the mobility aspect of safety,
- 9:02Speaker 2: because we also look at them as part of this journey.
- 9:06Speaker 1: As you speak on safety, and as we've said now,
- 9:08Speaker 1: October's Transport Month, I don't want to divert too much
- 9:11Speaker 1: from this particular von Squirstreff Road safety project, because that's
- 9:15Speaker 1: why you've joined us to speak. Although, seeing that it's
- 9:18Speaker 1: Transport Month, I wonder if you could talk on Scholar
- 9:20Speaker 1: Transport Month, And recklessness, not only among taxi drivers and
- 9:24Speaker 1: other drivers. Now, that route as well, especially when you're
- 9:26Speaker 1: coming past Dune and heading further up to Atlantis, there's
- 9:29Speaker 1: a lot of scholar transport that uses that area. There's
- 9:32Speaker 1: a lot of public transport, taxis and otherwise. As part
- 9:35Speaker 1: of this improvement, are we seeing bus lanes? Are we
- 9:39Speaker 1: seeing dedicated pedestrian zones? What is this improvement project doing
- 9:45Speaker 1: for safety?
- 9:48Speaker 2: Well, in terms of the safety aspect in our road design,
- 9:51Speaker 2: There's a number of roads which join the N7 from
- 9:55Speaker 2: the side. Now, because we are taking this to a
- 9:57Speaker 2: level one nationality, road level, and we have both actually,
- 10:03Speaker 2: you know, slip-ons and slip-downs onto the N7, we are
- 10:06Speaker 2: going to close down all these side roads on both sides,
- 10:10Speaker 2: which actually link into the N7, because the new corridor,
- 10:14Speaker 2: which we have constructed, is part of a much bigger safety,
- 10:17Speaker 2: focusing to the future. So there will not be dedicated
- 10:19Speaker 2: bus lanes because the N7 itself must be free-flowing. What
- 10:24Speaker 2: we have ensured is that on the sidewalks, on the
- 10:29Speaker 2: side of the road, we have actually widened in certain
- 10:32Speaker 2: aspects where even cyclists can utilize the road itself, obviously
- 10:37Speaker 2: in a safe way, as you rightfully highlighted in your introduction. Also, streetlights,
- 10:44Speaker 2: which will be on the bridge that goes across to
- 10:46Speaker 2: a certain corridor of the slip-offs that enhances safety in
- 10:50Speaker 2: terms of at night so that our motorists can actually
- 10:55Speaker 2: see in the ease of pedestrian. But I think what's
- 10:57Speaker 2: most important to understand is that if you are a
- 10:59Speaker 2: pedestrian or a cyclist, you know, you are required to
- 11:03Speaker 2: wear quite visible and bright colors to be visible to
- 11:07Speaker 2: traffic during the day and during the night as well. Yeah.
- 11:10Speaker 1: Minister, my last question before I let you go. I've
- 11:12Speaker 1: just gotten a question in here on our WhatsApp number.
- 11:14Speaker 1: Is it true that Mossel Bay will complete a R530
- 11:17Speaker 1: million upgrade to Louis Fourier Road, the R102? Can you
- 11:21Speaker 1: verify that?
- 11:23Speaker 2: Well, I actually opened that new road on Friday. It's
- 11:26Speaker 2: open already. It has been completed again within budget on time.
- 11:30Speaker 2: And Transkouros is another big project, which is actually, like
- 11:33Speaker 2: I said, under budget, but on schedule as well. So,
- 11:37Speaker 2: Those of you that are planning your festive break to
- 11:40Speaker 2: the Garden Route, Louis-Pierre has been, again, a dual carriageway
- 11:43Speaker 2: from a single carriageway. It's to enhance traffic. But again,
- 11:46Speaker 2: similar like on Squares, they're connecting communities to the economy
- 11:49Speaker 2: and ensuring that we have enough future economic opportunities and
- 11:52Speaker 2: empowerment opportunities for all of our people who use our
- 11:55Speaker 2: provincial road network.
- 11:58Speaker 1: Thank you very much for your time. Provincial Minister of Infrastructure,
- 12:01Speaker 1: Tarsia Simmers, joining you in conversation there to speak on
- 12:04Speaker 1: this massive, and I do mean massive, R797 million upgrade
- 12:08Speaker 1: of Van Squirstrift Road. And we only hope that we
- 12:11Speaker 1: can see value for money there in terms of our
- 12:14Speaker 1: and your lived experience when using that road. We can
- 12:17Speaker 1: only hope for the best.