Latest / Safe As Podcast / E75: Better indicators for your risk control system
Transcript
- 0:00The absence of incidents doesn't prove the effectiveness of
- 0:03controls. Controls can degrade even while
- 0:06an organisation is handing out awards for two years.
- 0:09LTI Free Nancy Levinson describes the challenge.
- 0:13There are always warning signs before a major accident, and
- 0:16such weak signals are often perceived only as noise.
- 0:20So how can we identify and measure those signals before the
- 0:23fire and brimstone? Everyone welcome to SAFE as I'm
- 0:26Doctor Ben Hutchinson. Now the question I probably get
- 0:30the most is what indicators should we be using?
- 0:33I've covered dozens of studies on indicators in safety and
- 0:37broader organisational indicators.
- 0:39Check them out on my site. There's so much there to read.
- 0:42Now today I'm going to try and sidestep that whole debate and
- 0:45we're going to focus on one specific element of indicators,
- 0:48focusing on the effectiveness of our risk control system.
- 0:52So there's extensive debate regarding indicator typologies,
- 0:56lead verse lag, drive, verse monitoring, proactive verse
- 1:00reactive, and more. Andrew Hopkins provides a more
- 1:02focused thread. He notes that the primary
- 1:04purpose of performance indicators must be to evaluate
- 1:08the effectiveness of the specific controls upon which the
- 1:11risk control system relies. From this perspective, the
- 1:15concern isn't the volume of audits or inspections completed,
- 1:18but whether the specific barrier is designed to prevent a serious
- 1:21incident or unwanted event. A healthy step one.
- 1:25The risk control system. The U KS HSG 254 guide focuses
- 1:30on assurance and indicators for major hazards.
- 1:33It assumes management systems are already in place and shifts
- 1:36emphasis towards checking whether risk control systems are
- 1:40operating as intended. GC254's contribution is the
- 1:44system of dual assurance. For every risk control system,
- 1:48you require both a leading and a lagging indicator.
- 1:51The process involves 1. Identifying the risk control
- 1:54systems and their required outcomes 2.
- 1:56Setting lagging indicators for each system to monitor what can
- 2:00go wrong, effectively monitoring the failure of immediate causes
- 2:033. Identifying critical elements of
- 2:05each system, the specific components that must function
- 2:09for the whole system to work 4. Setting leading indicators to
- 2:13monitor the health of these critical elements Step 2
- 2:16Defining performance and criticality.
- 2:18Moving really into the heart of this logic, the ICM Ms critical
- 2:22control management framework targets high consequence
- 2:25material unwanted events. The goal is to define the
- 2:28critical controls, objectives, performance requirements and how
- 2:32that performance is verified in practise.
- 2:34Critical control is distinct from a standard or regular
- 2:37control. It's crucial to preventing the
- 2:39event and its absence or failure would significantly increase
- 2:43risk, despite other existing controls.
- 2:45To ensure these work, the ICMM defines 3 specific performance
- 2:49lenses. 1 Availability is the control in place and accessible
- 2:54to reliability and the control performance function to the
- 2:58required standard. 3 Survivability will the control
- 3:01function during the stresses of the event.
- 3:04To bridge the gap between high level risk assessment and field
- 3:07verification, both the ICMM and QGN 35 utilise a critical
- 3:12control information summary. Here's a work example.
- 3:15Methane ignition on a long wall. So consider the material
- 3:18unwanted event of a methane ignition.
- 3:19Unidentified critical control is the automatic methane power
- 3:22trip. The objective is to
- 3:24automatically isolate electrical power to the long wall face when
- 3:28methane concentration exceed a certain threshold, preventing a
- 3:32potential ignition source performance requirements.
- 3:34Well, the trip must activate exactly that threshold and
- 3:37complete the power isolation in less than two seconds or
- 3:40whatever the criteria is. We have support activities and
- 3:43these are the background tasks ensuring the control stays
- 3:46healthy, such as regular sensor calibration and physical
- 3:49protection of the sensor heads, and then the verification.
- 3:52The indicators in part weekly in situ gas testing, which is a
- 3:56formal workplace monitoring and monthly software trip testing, a
- 4:00form of formal auditing, provide the leading indicators of the
- 4:04controls health. And there's probably a range of
- 4:06other things you could do. And here's a potential shortcut.
- 4:09If you've already produced bow ties as part of your risk
- 4:11management or critical control framework implementation, then
- 4:15you've done most of the heavy lifting already.
- 4:17Use your bow ties to guide your risk control system indicators.
- 4:21Identify the ways to monitor and verify the barriers or critical
- 4:24controls and the support structures and the degradation
- 4:27factors that either enable their success or affect their
- 4:31integrity. It doesn't need to be a gigantic
- 4:34list. Identify the few critical things
- 4:36that have to go right first time, every time, or just
- 4:40otherwise critical and particularly susceptible to
- 4:43reliability or erosion. Step three.
- 4:45Condition verse compliance. This example illustrates Hopkins
- 4:49point. We must distinguish between
- 4:51compliance and condition. Compliance could be like did we
- 4:54finish the weekly gas testing and condition what was the
- 4:57failure rate during those tests? Indicators must report the
- 5:01actual condition, the defect rate or trigger breaches, rather
- 5:05than just the activity of checking whether it was done or
- 5:07not. For triggers and tarps, a
- 5:10performance trigger is a point at which a control is considered
- 5:13not maintained. Trigger set the criteria for
- 5:15what action must be taken, by whom and when.
- 5:18So if that critical methane reading requires immediate
- 5:23action, let's say it's 5% requires immediate action, but
- 5:26the reading is 4.95%, what action should the operator take?
- 5:30This is where triggers and tarps come into it.
- 5:32So tarps are your if their mechanism if trigger level X,
- 5:36action set Y, escalation Z. This is a real example where
- 5:41let's say it was 5% and they measured it at 4.98%.
- 5:44Some incidents have shown that people just didn't take action
- 5:47because it's technically they only had to escalate the issue
- 5:50if it was 5%. Let's say.
- 5:51In summary, effective assurance requires moving past broad
- 5:55organisational metrics to monitor the specific
- 5:58performance, specifications, availability, reliability, and
- 6:02survivability of the barriers we rely on to prevent catastrophe.
- 6:06You can still set broader measures and indicators, but
- 6:10they shouldn't come at the expense of the effectiveness of
- 6:13your risk control system and being laser focused on
- 6:16understanding and monitoring the effectiveness of your systems.
- 6:20I highly recommend you check out these sources that I've linked
- 6:22today, including Nancy Levinson's work on indicators.
- 6:25Maybe I'll cover that paper alone on another episode.
- 6:29The short of it is identify the things that have to happen or
- 6:33cannot happen, implement the controls or constraints and then
- 6:36design indicators to measure the health of those constraints and
- 6:39assumptions and controls. That's targeted.
- 6:41It's focused on the things that are most important to your
- 6:44organisation and its risk control systems and it doesn't
- 6:47involve really lofty, pie in the sky broad organisational
- 6:52indicators. It's targeted on the things that
- 6:54have to happen or can't happen. That's it on safe as.