Snow's Cut Shoreline Stabilization Moves Forward | Wilmington News
Snow’s Cut finally gets the green light after years of delays — the U.S. Army Corps of Engineers has awarded a $7M contract to Cape Romain Contractors to stabilize 7,500 feet of eroding shoreline, part of a $15M Bipartisan Infrastructure Law investment. Originally slated for January, the project was delayed while engineers conducted a value study to ensure cost-efficiency. With banks collapsing and the waterway swelling from 90 to 600 feet wide, this is a critical fix before the land becomes unsafe. The seasoned contractor, with decades of marine and bridge experience, is expected to finish…